Quality control (QC)
Quality control (QC) connects inspections and measurements to correction of unacceptable work and verification of the finished result. It includes action on defects as well as records. Keep first-pass quality separate from final acceptance: if eight of 100 installations need correction, first-pass acceptance is 92%, even when all 100 eventually pass. Erasing the failed results hides the rework that the quality program needs to prevent.
The inspection, testing, and measuring of the actual work against the acceptance criteria as it is built
A successful re-test does not erase the first result
The Navy test-results provisions in UFGS 01 45 00, August 2023 with August 2026 Change 4, require actual measurements and a conformity statement against the specified requirements, with immediate notice to the Contracting Officer after a failure. Include those reporting duties when pricing a project that adopts the provisions. A report cover stamped conforming does not replace its underlying test results.
For 100 installations with eight initial failures, first-pass acceptance is (100 - 8) / 100 = 92%. After correction and successful re-testing, final acceptance is 100%. Retain both measures and link each correction to its original finding; the difference identifies repeat work even when the final installation is satisfactory.
Traceability belongs to the measurement result
NIST states that metrological traceability is a property of a measurement result, supported by a documented calibration chain and associated uncertainty. An instrument sticker is one part of that chain. Preserve the instrument identifier, applicable calibration, measurement conditions and any correction used with the field reading.
NIST also explains that traceability alone does not establish fitness for a particular measurement task; the uncertainty must suit the measurement need. A traceable instrument with insufficient accuracy for the acceptance band still produces weak acceptance evidence. Identify the required tolerance and measurement capability before reducing the record to pass or fail.
Take a dimensional acceptance band of 9.5 to 10.5 mm and a corrected measurement of 10.0 mm. A documented expanded uncertainty of 0.2 mm produces an interval of 9.8 to 10.2 mm; an uncertainty of 0.8 mm produces 9.2 to 10.8 mm. The indicated value is unchanged, but the second interval crosses both limits. Apply the project's agreed acceptance decision rule with the uncertainty recorded.
Keep inactive features visible in the daily record
UFGS 01 45 00 keeps a definable feature of work on the daily report after its Initial Phase is completed and until its Final Follow-Up is completed. The report must identify days with no work on that feature. Assign an open status to outstanding tests, reports and corrections so each has a visible owner until closure.
Use those open statuses with the QA/QC control phases to identify the next action, such as correcting an installation or obtaining a missing laboratory report. BSI lists BS EN ISO 9001:2026 as its current quality-management requirements standard. Management-system certification and a particular lot's acceptance remain separate claims, supported by separate evidence.
Distinctions
- Quality assurance
- QA review asks whether the inspection process reliably catches and resolves defects. QC follows a particular finding through the actual measurement, correction and verification. A complete form with an unresolved defect satisfies neither purpose.
- Final acceptance
- Acceptance after correction establishes the finished condition. The earlier nonconformance remains part of the quality history.
Frequently asked questions
Is an instrument calibration certificate enough for QC?
The certificate supports the measurement chain. The field record must still identify what was measured, how, under which conditions and against which acceptance limit.
Should corrected results overwrite failed values?
Retain both. Link the repair and re-test so a later reviewer can reconstruct the original finding and the evidence closing it.
Sources checked
Also defined as
- Concrete: The inspection and testing that detects defects in the work as it is built