ANVILFIELD Try FieldOS

Field glossary · process

Disposition

A disposition connects an inspected defect to the authority that decides its outcome. The record identifies the affected location or lot, the failed criterion, the approved action, and the evidence needed for release. A repair approval authorizes work; closure records its completion and verification. Keeping those two dates separate prevents an authorized but unfinished repair from disappearing from the open-defect register.

The decision on nonconforming work: rework, repair, use-as-is, or reject, with engineering dispositions set by the engineer

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Separate the decision, the repair, and the release

The NRC's 10 CFR 50 Appendix B, Criterion XV, requires nuclear quality programs to control nonconforming items through identification, documentation, segregation, disposition, and notification as appropriate. Its acceptance, rejection, repair, and rework decisions follow documented procedures. The useful construction lesson is that a decision belongs to identified material, not an unbounded category of similar defects.

A repair instruction for anchor A-17 does not release anchors A-18 through A-24. Give each affected location an explicit relationship to the decision. Record whether the approved disposition covers a single item, a traced manufacturing lot, or a defined inspection population.

Who accepts a deviation from the original requirement?

For federal construction contracts containing FAR 52.246-12, paragraph (f) requires correction or replacement of nonconforming work unless the Government accepts it in the public interest with an appropriate contract-price adjustment. A contractor's proposed solution therefore does not itself establish acceptance.

Route the technical question and the contractual decision to their assigned authorities. In the construction ITP, cross-reference the NCR number, drawing revision, decision authority, and repeat inspection. Preserve the original requirement, the proposed departure, the technical rationale, and the actual acceptance together. A revised drawing without that trail hides what changed.

Close the item against the approved repair criteria

A bracket is located 18 mm from its required position; the drawing permits ±5 mm. The defect exceeds the permitted offset by 13 mm. If the approved repair changes the bracket detail, inspect the completed assembly against that repair detail and its stated tolerances; retaining the original failed inspection prevents the repair from being mistaken for initial compliance.

NRC Criterion XVI requires significant conditions adverse to quality to have their cause determined and corrective action taken to prevent repetition. That adds a separate question after fixing the bracket: why did the layout process produce the error? Closing the physical repair does not establish that the next bracket will be located correctly.

Disposition outcomeEvidence that closes the item
ReworkNew readings establish compliance with the original requirement.
RepairThe completed modification meets its specifically approved repair detail.
Accept as-isThe authorized acceptance identifies the deviation and the exact item or lot covered.
RejectRemoval or segregation records prevent the rejected item from re-entering the installation.

Distinctions

Disposition versus corrective action
An item can have its repair completed while the cause investigation remains open. Track the physical acceptance and the prevention action under separate owners and closure evidence.

Frequently asked questions

Can an NCR close when the repair is approved?

Approval authorizes the specified action. Closure follows implementation and the required verification, with unresolved testing or inspection kept visible in the record.

Sources checked

Where this shows up

Next step: Find construction QA work

Back to the full field glossary