Field glossary · process
Acceptance criteria
Acceptance criteria specify which measured results receive a pass, including the test conditions and treatment of uncertainty. Under JCGM 106:2012's guarded-acceptance approach, a 300 Pa upper specification limit with a 4 Pa inward guard band accepts results only through 296 Pa. A 299 Pa reading therefore fails that agreed rule even though it is below 300 Pa. Write the decision boundary before testing so a borderline result has an agreed pass/fail decision.
The standard or value a test result is measured against to pass, from the project spec, the discipline standard, or the manufacturer
Specification limits and acceptance limits are different
NIST's 2014 paper Assessment of Conformity, Decision Rules and Risk Analysis distinguishes the zone of conforming product characteristics from the zone of acceptable measurement results. A specification describes what the finished work must achieve. An acceptance limit describes which measured results establish that achievement under the selected decision rule.
JCGM 106:2012 describes simple acceptance as accepting a measured value inside the tolerance interval, with producer and customer sharing the risk of an incorrect decision. Guarded acceptance moves the acceptance boundary inward to reduce false acceptance. These approaches answer the same specification with different treatment of uncertainty; changing between them after a borderline result changes the basis of acceptance.
A 300 Pa limit with a 4 Pa guard band
JCGM 106:2012 expresses an upper guarded-acceptance limit as the upper tolerance limit minus the agreed guard-band width. For a project limit of 300 Pa and a 4 Pa guard band, the acceptance boundary is 296 Pa. The comparison below uses corrected readings and accepts equality at each boundary; JCGM 106 section 3.3.9 includes the acceptance limits in the acceptance interval unless the specification says otherwise.
If the 4 Pa band equals the report's expanded measurement uncertainty, write that relationship explicitly. An instrument's display resolution is a different quantity. A display advancing in 1 Pa steps does not establish a 1 Pa uncertainty, and its calibration correction still belongs in the reported measurement.
The 299 Pa result is a recorded failure to meet the agreed acceptance rule. It does not, by itself, establish that the actual pressure exceeds 300 Pa. Keep those statements separate when preparing a nonconformance report or an engineering disposition.
| Corrected result | Simple acceptance, limit 300 Pa | Guarded acceptance, limit 296 Pa |
|---|---|---|
| 296 Pa | Pass | Pass at the boundary |
| 299 Pa | Pass | Fail |
| 301 Pa | Fail | Fail |
What a reviewer needs beside a pass mark
A usable acceptance statement identifies the measured property and its location, the reference revision, test configuration, units, decision boundary, and treatment of uncertainty. Include whether the boundary itself is accepted. Write a minimum as greater than or equal to its limit when equality is permitted; a minimum and a strict greater-than requirement produce different decisions at the boundary.
Attach the unrounded result where available. With the 296 Pa guarded boundary, a corrected 296.4 Pa reading fails a comparison using the unrounded value; rounding it to 296 Pa first would produce a pass. Record whether rounding occurs before the decision, and keep the original value so the reviewer can reproduce it.
Put the decision-rule identifier in the applicable ITP row and on the test report itself. The turnover proof packet then carries the measurement, uncertainty, boundary, and decision together, even when the report is separated from its original inspection form.
Distinctions
- Test method
- Two laboratories can use the same measurement method and report the same value yet issue different conformity decisions if their agreed guard bands differ.
- Disposition
- A signed concession can authorize use of work that failed its original criterion. Retain the failed result and decision rule beside that concession so the acceptance history remains reproducible.
Frequently asked questions
Does a calibrated instrument guarantee a passing result?
Calibration supplies measurement information. Acceptance still depends on the corrected result, applicable uncertainty, and agreed decision rule.
Should every acceptance limit include a guard band?
Use the rule required by the governing specification or agreed test contract. JCGM 106 documents both simple and guarded acceptance; the selected rule belongs in the test agreement.
Sources checked
Also defined as
- The documented results, healthy nodes, clean fabric, passing benchmark, that gate the cluster to production
- The measurable standard the work must meet, a tolerance, test value, or pass-fail from the spec or code