Field glossary · process
L1 to L5
Read an L1-to-L5 tag as a claim about accepted evidence. BCxA's 2024 mapping uses L1 for factory verification, L2 for delivery condition and correct installation, L3 for startup, L4 for operating sequences, and L5 for system interconnections. A quote stopping at L3 therefore needs a startup allowance; completed L4 records leave integrated testing outstanding. The level number reports a test boundary, not a share of total commissioning labor.
The commissioning levels, from factory test through receiving, installation, functional, to integrated test, with boundaries set by the plan
What evidence does each level actually accept?
Use BCxA's May 2024 level descriptions to build an evidence register, with a separate acceptance question for each row. Each record below ties a test boundary to the evidence an incoming team needs.
| Level | Acceptance question | Evidence to request |
|---|---|---|
| L1 | Does the factory result cover the equipment being shipped? | Test report matched to the serial number, approved rating and witnessed test scope |
| L2 | Are delivery and storage condition, and correct installation, verified? | Receiving record, storage observations and accepted installation checks |
| L3 | Has startup established readiness for functional testing? | Manufacturer startup record and disposition of startup findings |
| L4 | Has the system demonstrated its operating sequence? | Measured results for the required operating modes and accepted functional test revision |
| L5 | Have the connected systems demonstrated their combined response? | Integrated scenario result linked to the participating systems, configuration and event logs |
Resolve the installation and startup boundary in the bid
BCxA includes correct installation in Level 2 and equipment startup in Level 3. CxPlanner's August 2026 description instead calls Level 2 a pre-installation inspection. That difference affects a purchase order: spell out installation-check labor and the manufacturer's startup visit alongside the proposed level so the two contractors' definitions leave no unassigned task.
Use the release-gate guide to assemble the task list, then ask each bidder to identify which party supplies each test, instrument and load bank. Put repeat visits after failed tests on the same responsibility schedule. Comparing the words L1 to L5 alone will not expose a missing startup visit.
A local Level 4 count does not release Level 5
BCxA allows individual equipment to advance independently through Level 4, but describes Level 5 as following completion of Level 4 for all equipment. A phased integrated test needs an expressly defined and accepted phase boundary; a contractor's local completion register does not establish that boundary. Include shared controls and supporting plant in the prerequisite review recorded by commissioning management.
For 12 cooling units with 10 accepted functional tests, 10 / 12 = 83.3% is the cooling-unit L4 acceptance fraction. It leaves two units outstanding and says nothing about acceptance of their common controller. Four completed levels out of five likewise do not prove 80% of commissioning labor is complete: level numbers carry no labor weighting.
The evidence boundary grows beyond the equipment tag
Give each accepted test a searchable key comprising the equipment or system identifier, test revision and tested configuration. A replacement controller can retain the same equipment tag while changing the sequence behind an accepted functional performance test. Keeping the software version beside the tag makes that difference visible.
Attach participating power and cooling paths, controller versions and scenario revision to the integrated systems test record. A controller change then identifies connected results for a documented retest decision instead of silently inheriting the former pass. Keep failed attempts and successful reruns together under the same required test; an extra attempt is not an extra accepted scope item.
Distinctions
- Five acceptance levels versus the complete commissioning service
- BCxA places the five levels within construction, one of its four commissioning phases. Its predesign, design, and occupancy and operations activities extend beyond that level-testing package. List those services separately when appointing a CxA.
Frequently asked questions
Does L1 always mean a witnessed factory test?
BCxA identifies L1 as factory testing; that label alone does not specify an owner's witness trip. A factory report and a travel-and-witness allowance are separate bid inclusions. Identify which equipment needs witnessed testing and who attends.
Does a Level 5 result establish operator readiness?
BCxA puts training, fine-tuning and owner handover in occupancy and operations. An integrated test report therefore needs separate companion records for training completion and handover acceptance. Those records establish what the operations team received beyond the tested plant.
Sources checked
Also defined as
- Acceptance-testing gates from factory testing through delivery and installation, startup, functional testing, and integrated testing