FAT

A FAT (factory acceptance test) establishes a pre-shipment performance baseline tied to the equipment serial numbers, settings, loading and simulated interfaces. Those details let the site team compare a later discrepancy with the factory condition. USACE's generator guide specification starts with at least one hour at rated output before inspection; that preparatory run is only one part of the factory acceptance scope.

Factory acceptance test, the Level 1 test at the manufacturer before shipment; the plan identifies required witnesses

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Separate the factory test agreement from the product standard

IEC 62381:2024, edition 3.0, covers acceptance and integration testing for process-industry automation, with responsibilities and activities agreed against the automation specification. The 2024 revision adds optional factory integration testing (FIT). List that scope separately when a purchase includes both an automation-system FAT and factory tests of its connections to other systems.

IEC 62040-3:2021, edition 3.0, addresses UPS performance tests, including the complete UPS and applicable functional units and interacting switches. Use the equipment standard to identify product performance tests and the purchase specification to identify the project sequences and witnesses. Index each required result to its test clause so a vendor's production report can be matched to the acceptance scope.

Generator FAT duration, notice and stabilization

In its February 2026 generator guide specification, UFGS 26 32 15, USACE specifies a run of at least one hour at rated output before factory inspection. The project specification selects the applicable factory test package. That preliminary operating period does not set the duration of the subsequent acceptance tests.

UFGS 26 32 15 requires notice of proposed factory inspection and test dates at least 14 days before testing begins. Its factory-test provision treats a parameter as stabilized only after at least four consecutive readings remain within the specified band. Put the selected band and reading interval on the test sheet so four readings establish an interpretable result.

For assembled-set factory tests, UFGS 26 32 15 lets the specifier select the parameter-schedule power factor or enter another required power factor. Its design guidance identifies 0.8 as the usual generator rating basis. At 1,000 kW and 0.8 power factor, apparent power is 1,250 kVA; a 1,000 kW unity-power-factor test produces 1,000 kVA. Equal kW therefore does not establish equal alternator loading.

Keep a configuration baseline that survives shipment

Match the report to the serial numbers, controller software, protection settings and options actually tested. UFGS 26 32 15 permits factory testing without the final project controls and switchgear when those items are outside the generator manufacturer's standard package. Identify each substitute, simulated input and omitted field device beside the affected result.

UFGS 26 32 15's factory report package includes instrument calibration certificates, measurements and plots, specified conditions, signed results and adjustments. Preserve both the initial and corrected settings in the module handoff records so the site team can distinguish a shipment change from an accepted factory correction.

Distinctions

Routine production test
A manufacturer's recurring production checks and a project FAT can overlap. The purchase specification identifies which production results are accepted and which additional tests or witnesses are required.

Frequently asked questions

Must the owner attend every FAT in person?

Attendance follows the purchase order and approved witness requirements. A FAT is a defined acceptance activity; the acronym alone does not establish who must attend.

Does a factory-tested module arrive ready for integrated operation?

Use the report's simulated-input list to identify interfaces awaiting site evidence. A factory test harness that supplied a run permission does not establish that the installed site controller will send it at the required time.

Sources checked

Also defined as

  • Factory acceptance test, the witnessed test of a module at the manufacturer's plant before it ships