An FPT (functional performance test) produces acceptance evidence for a stated operating mode and equipment population. NAVFAC's mechanical commissioning guide specification allows sampling for certain identical single-zone units, with at least three in the sample, while requiring every central plant item to be tested. A passing sample and a fully tested plant are different acceptance claims; identify the tested units and modes beside the result.

Functional performance test, the witnessed demonstration that a system performs its sequence under normal and fault conditions

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Select instruments that resolve the acceptance limit

For projects using NAVFAC UFGS 23 08 00, May 2023 with Change 1 of August 2024, the default temperature-instrument criteria are calibration within the past year, 0.5 degree F accuracy and 0.1 degree F resolution. A display resolving tenths does not establish accuracy to a tenth. Put the instrument certificate and range beside the measured value.

The same UFGS section specifies pressure-sensor accuracy of plus or minus 2% of the value range being measured, rather than the meter's full range, and calibration within the last year. Select the instrument around the actual test range. A broad-range gauge that looks adequate by its dial markings can leave too much uncertainty around a narrow acceptance band.

NIST recommends setting recalibration intervals from the application requirements and demonstrated instrument stability; it does not prescribe a fixed interval for every instrument. Here, the UFGS requirement supplies the project criterion. Its instrument provisions also call for immediate recalibration following repairs resulting from a drop or damage.

Sampling changes what a passed FPT proves

UFGS 23 08 00 calls for testing all central plant equipment, primary air handlers, process cooling or heating equipment, and system-level equipment serving multiple zones. Its sampling option is for large groups of identical single-zone equipment with identical controllers, with a minimum sample of three units. The selected contract percentage defines the initial coverage.

UFGS 23 08 00 requires random selection within each group. Reaching a 10% failure rate in the first sample triggers a second group of the same size, with different units; reaching 10% again triggers testing of every remaining unit. For 80 identical terminals and a contract-selected 25% sample, the resulting coverage is:

The failure denominator is the group just tested. Two failures in the first 20 are 10%, even though they represent only 2.5% of all 80 terminals. Record failed-unit correction and re-testing separately from the additional units required by the sampling rule.

Test groupUnits tested in this groupResult requiring expansion
Initial random sample20Two failures trigger a second group
Second sample, excluding the first group20Two failures trigger the remaining units
All remaining units after both triggers40Complete the full population

Restore the tested controls and preserve the result

UFGS 23 08 00 requires affected equipment and systems to return to their pre-test condition after the test. Log the removal of forced values and temporary loading alongside the results. A satisfactory response produced by an override should not leave the normal sequence dependent on that override.

Attach instrument identity, imposed conditions and unit identifiers to the controls sequence demonstration. A later reviewer should be able to reconstruct the sample size and the control mode from the signed result without inferring either from a generic passed box.

Distinctions

Calibration versus functional performance
Calibration establishes the measurement relationship. An FPT tests system behavior. A controller responding correctly to an inaccurate sensor still needs the measurement problem resolved.

Frequently asked questions

Can one passing FPT stand for every identical unit?

Only when the approved sampling strategy allows that coverage. Identify the sampled units and apply the specified expansion rule when failures occur.

Does the temperature shown on the BMS need another instrument?

Use the calibrated DDC sensor where its evidence meets the test requirements. UFGS 23 08 00 requires separate measuring and logging equipment where calibrated DDC sensors cannot record the required data.

Sources checked

Also defined as

  • Functional performance test, the energized demonstration that a single system performs its sequence of operations
  • Functional performance test, the energized Level 4 demonstration that a single system runs its sequence