AI and BI are measurements received by a controller; AO and BO are commands sent from it. Analog points carry a range of values, while binary points carry two states. The letters describe the point's role, not its terminal hardware: a BI can occupy a configurable universal input, and a BO can switch through a triac that needs external power. Specify both the point type and the electrical interface.
Analog input, analog output, binary input, binary output, the four I/O point types
Choose terminals from the electrical interface
Johnson Controls' F4-CG installation guide, revision C, permits voltage, current, resistance and dry-contact modes on universal inputs; configuring the mode is part of assigning the point. Its voltage-output mode requires a load of at least 1,000 ohms, while its 4 to 20 mA analog-output mode supports a load from 0 to 300 ohms.
| Point | Field example | Interface detail to retain |
|---|---|---|
| AI: analog input | Differential-pressure transmitter | Signal span, engineering span and whether the loop supplies power |
| AO: analog output | Valve position command | Voltage or current mode and permitted actuator load |
| BI: binary input | Run-proof contact | Dry-contact mode and the equipment meaning of open and closed |
| BO: binary output | Fan enable | Relay or semiconductor switching, external supply and load rating |
Scale the signal before judging the sensor
A current transmitter has an electrical span and a measurement span. AutomationDirect's transmitter troubleshooting guidance identifies 4 mA as live zero and 0 mA as an open-loop failure indication. A zero engineering reading therefore differs from a zero-current reading. Record the transmitter's range at the device and in the controller, including whether its pressure reference is gauge or differential.
DATAQ's current-loop application note shows that a 250-ohm shunt converts 4 to 20 mA into 1 to 5 V. Adding that resistor to an input already configured for current changes the circuit; first identify the input hardware and its existing shunt. A voltage measurement across the known resistor tests the signal without treating a voltage terminal as a current terminal.
Prove the receiver and the field device separately
AutomationDirect identifies signal simulation as a way to separate receiver faults from transmitter faults. Inject the low end, midpoint and high end of the configured span and record the displayed value at each. A midpoint alone misses a span error: both a 0 to 2 in. w.c. scale and an incorrect 0.2 to 1.8 scale display 1.0 at midspan.
An actuator can occupy an AO for command and a separate AI for position feedback. In the BMS functional-test record, give each its own terminal, scale and trend column. A displayed output percentage copied into a feedback field would make a disconnected actuator appear to follow every command.
Record contact logic without hiding its meaning
Johnson Controls specifies externally powered 24 VAC triacs for the F4-CG binary outputs. A command changing on the screen does not supply that external voltage or demonstrate load current. Identify the supply and output common on the terminal drawing, then compare commanded state, switched voltage and independent equipment proof.
For contact inputs, record the normal state and the alarm interpretation separately. A normally closed fault loop opens on either a fault or a broken wire; a normally open run contact gives no such distinction when it stays open. Keep that behavior visible in the point schedule instead of storing only the words normal and alarm.
Distinctions
- BACnet object
- An exposed network value does not establish a spare physical terminal or the electrical capabilities of that terminal.
Field example
A differential-pressure transmitter spans 0 to 2 in. w.c. over 4 to 20 mA. Its scale is pressure = (mA - 4) / 16 x 2. At 12 mA it should display 1.00 in. w.c.; across a 250-ohm shunt the same signal measures 3.00 V. These are calculated checks on the configured span.
Frequently asked questions
Can a binary output prove that a fan is running?
The output records the command. Independent run proof requires its own input and a documented status device; compare both during checkout.