SOO

SOO means sequence of operations: the written behavior a controls program must produce when inputs, operating modes or equipment availability change. Each transition needs a trigger, qualifying time, action and reset, with priorities for competing demands. A points list supplies signals but does not supply that logic. Keep the SOO revision and adopted addenda with the controller version because a changed timer or staging condition changes what a passing functional test must demonstrate.

Sequence of operations, the written definition of setpoints, staging, modes, interlocks, alarms, and failure response the controls must follow

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Identify which Guideline 36 behavior was specified

ASHRAE Guideline 36-2024, Addendum a, approved February 27, 2026, changes the default fan-array interstage delay from 15 minutes to 5 minutes. That is a material control change even though the parent guideline edition remains 2024. Identify the addendum in the approved sequence and controller version record.

The same ASHRAE addendum adds a staging response when duct static pressure remains more than 10 percent below its setpoint for five minutes. This additional condition is separate from staging based on the airflow criterion. A test that changes only airflow demand will not demonstrate both branches.

Represent simultaneous demands as explicit priorities

Use a transition table to put the initiating signal, qualifying duration, inhibit conditions, action and reset on one row. A high-load request and an unavailable standby fan need a defined outcome: which available unit is selected, what alarm appears and how the sequence returns to its normal order. Resolve those choices before programming the controller.

For a project adopting the cited static-pressure branch at a 1.00 in. wg setpoint, the ten-percent comparison level is 0.90 in. wg. Establish the precondition, drive the measured input below that level for the specified duration, then confirm the intended stage action and recovery. Use the approved test method to distinguish a simulated input from an actual equipment fault.

Capture the stimulus, response and restoration

NIST Technical Note 2024, published in February 2019, describes functional tests that command operating modes, collect real-time system data and apply rules to detect incorrect operation. The report separates passive monitoring from active testing. Preserve the commanded condition and the observed response together so the result can be interpreted later.

A useful test record includes input values, timer start, timer expiration, output command, proof of equipment response and the return to normal. Record temporary overrides and their removal. An output command proves a software action; the independent run status or measured flow establishes what the equipment did.

Attach the signed controls commissioning result to the approved SOO revision and the installed program version. A later timer or staging edit then identifies the affected demonstrations directly, instead of leaving the owner with a passing test for an unidentified program.

Distinctions

Points list
The points list identifies signals and addresses. It does not define the timing, priority or mode transition that relates them.
Controller program
The program implements the sequence. A downloaded program file and a written SOO require a version relationship to establish that they describe the same behavior.

Frequently asked questions

Does changing an addendum require a new parent edition?

No. Addendum a changes fan-array staging within Guideline 36-2024. Record the specific addenda included in the project rather than relying on the edition year alone.

Sources checked

Also defined as

  • HVAC: Sequence of operations, the written description of how the system is to run
  • Sequence of operations, the automatic logic the plant follows on utility loss, transfer, and recovery