Valve authority

Valve authority of 0.50 means the fully open control valve accounts for half the design pressure loss within the defined controlled circuit. The rest of that circuit loses the other half at the same flow. Draw that boundary before using pressure readings: throttled-valve readings, pump discharge pressure and losses outside the controlled path are not interchangeable inputs. An actuator percentage supplies none of these hydraulic quantities.

Ratio of the valve's pressure drop to the controlled branch drop; aim high, commonly 0.3 to 0.5 or better

Used across 3 Anvilfield field guides, most in HVAC.
Updated

Draw the pressure boundary before calculating authority

Use N = ΔPv / (ΔPv + ΔPr), where ΔPv is the fully open control-valve loss and ΔPr is the remaining controlled-circuit loss at design flow. Identify which coil, pipework and balancing devices are inside that boundary. A pump discharge gauge includes losses that may not belong to the circuit being controlled.

Spirax Sarco’s water-valve sizing tutorial recommends authority close to, but not above, 0.5 and no lower than 0.2 for its sizing method. Treat those as the bounds of that manufacturer’s recommendation. Raising authority by selecting a higher-loss valve spends more pump head; the aim is the specified control response at an acceptable pumping duty.

An oversized valve changes the denominator too

At 6 US gpm, a control valve losing 8 psi in a circuit with another 8 psi of loss has authority 8 / 16 = 0.50. For water, calculate US Cv as Q / √ΔPv; the original selection is approximately 2.12. Keep the same design flow and remaining circuit loss when comparing another valve.

Doubling Cv reduces valve pressure loss to one-quarter at the same flow. Both the numerator and the total-circuit denominator change, so authority falls from 0.50 to about 0.20. The table uses rounded Cv values. Carry the pressure-tap locations and measured flow into the balancing record before changing controller tuning.

Selection at 6 US gpmUS CvValve lossOther circuit lossAuthority
Original valve2.128 psi8 psi0.50
Twice the flow coefficient4.24About 2 psi8 psiAbout 0.20

Separate installed response from actuator travel

Spirax Sarco defines a linear valve characteristic as flow proportional to lift under constant differential pressure. The constant-pressure condition matters: circuit pressure changes as neighboring valves move, so a linear actuator command does not guarantee the same installed flow relationship.

For a three-port valve, Spirax Sarco calculates authority against the variable-flow part of the circuit. On a mixing schematic, color that path before listing its losses and keep the common constant-flow leg in a separate column. This exposes an incorrect denominator before a calculator produces a plausible ratio.

A valve that is already nearly closed at normal load needs a hydraulic check before another round of tuning. Compare the selected flow coefficient, actual differential pressure and operating flow with the design. The low-delta-T guide connects that poor flow control to plant consequences.

Distinctions

PICV operating range
A pressure-independent valve regulates only within its specified differential-pressure range. Its name does not establish that sufficient differential pressure exists at the installed location.

Frequently asked questions

Is authority measured with the valve half open?

The design calculation uses the fully open valve pressure drop at design flow. A throttled operating reading describes another condition and should be labeled separately.

Can authority be improved by changing the actuator?

An actuator can correct travel or torque problems, but it does not change the selected valve’s fully open flow coefficient. Establish whether the hydraulic selection or the mechanical travel is actually wrong.

Sources checked

Also defined as

  • The share of loop pressure drop the control valve takes when open; low authority makes the valve hunt
  • Control valve pressure drop divided by total circuit drop; low authority causes hunting

Where this shows up