ANVILFIELD Try FieldOS

Field glossary · method

Proportional balancing

Proportional balancing uses measured-to-design flow ratios to judge distribution across unequal circuits or outlets. A pair reading 60 and 120 percent of design remains unbalanced even when its combined flow equals the required total. Once the ratios match, a common adjustment can bring the group to design. The final readings must confirm that the proportions survived; automatic controls and design diversity determine which circuits can be tested together.

Setting outlets and branches as a ratio to the index (lowest-percent) outlet, then scaling the whole system with the fan

Used across 3 Anvilfield field guides, most in HVAC.
Updated

A correct total can hide incorrect circuit proportions

Two circuits designed for 10 and 20 GPM can measure 6 and 24 GPM. Their total is the correct 30 GPM, while their individual ratios are 60 and 120 percent. A pump-total check accepts the sum and misses the distribution error. Calculate each ratio before drawing a conclusion from the total.

The three-circuit worksheet below starts with all circuits at 80 percent of design. Its 48 GPM total needs a common flow multiplier of 60/48 = 1.25. After adjustment, the total reaches 60 GPM but the individual percentages separate. That set has lost proportionality even if each reading falls within a specified tolerance. Use the hydronic system guide to revisit the valve sequence and identify what changed during the common adjustment.

CircuitDesign GPMInitial GPMFinal GPMFinal percent of design
A10810100%
B20161890%
C302432106.7%
Total604860100%

How to balance a system sized with diversity

The 2023 ASHRAE Handbook, HVAC Applications, Chapter 39 calls for full-flow balancing of individual sections in systems that use diversity, with other sections shut off as needed to obtain those flows. A diversified pump duty can be smaller than the sum of every terminal's peak design flow. Forcing all terminals open together then treats an intentional design condition as a pump shortage.

Identify the groups and their required operating combinations from the design. Preserve the settings of completed groups while moving to the next section. The resulting record needs both the terminal ratios and the active-section configuration, so the readings can be recreated without demanding every peak load simultaneously.

Why the compensated method uses a partner valve

IMI's October 2004 TA-CBI technical guidance describes a TA Method that maintains a constant differential at a reference valve using the circuit's main valve while the other terminals are set. It gives 3 kPa as an example reference differential at the correct reference flow, not a universal setting for every valve. That maintained reference compensates for the disturbance each adjustment creates.

A proportional pass and a compensated pass therefore use different ways to manage hydraulic interaction. Label the method on the worksheet. The circuit-setter guide identifies the devices; the reference reading and partner-valve action explain what the technician actually held constant.

What changes when automatic pump control resumes?

ASHRAE's 2023 balancing chapter directs the technician to observe the highest-resistance circuit as other circuits close after establishing variable-speed pump control; its flow should remain at least at the previously established value. This checks the pressure-control handoff beyond the full-flow balance snapshot.

A changing control-valve command changes the resistance network behind the ratios. Separate that operating test from the fixed-configuration balance. Air systems need the same distinction between a fixed damper proportion and an actively regulating terminal; the air-balancing guide covers the duct-side procedure.

Distinctions

Equal-flow setting
Equal measured GPM establishes equal flow. Equal measured-to-design ratios establish proportionality. The two coincide only when the circuits have equal design flows.

Frequently asked questions

Can an entire VAV system be treated as one proportional group?

ASHRAE's 2023 HVAC Applications balancing chapter treats a pressure-independent air terminal and its downstream ductwork as a separate balancing system. The box controller changes its inlet resistance as pressure changes upstream; the downstream diffuser ratios belong to that box's fixed test condition. Record the commanded box flow with its outlet readings.

Sources checked

Also defined as

  • Setting every circuit to the same percentage of its design flow as the index, then iterating

Where this shows up

Next step: Follow mechanical project signals

Back to the full field glossary