Affinity laws

Use affinity laws to scale a pump's performance curve before finding its intersection with the installed system curve. Applying Hydraulic Institute's speed relationships at 80% speed gives 80% corresponding flow, 64% head and 51.2% pump input power under unchanged-efficiency assumptions. Static lift can shift the actual flow away from that ratio. Impeller trimming needs its own manufacturer curves because trimming also changes internal geometry.

Flow scales with speed or impeller diameter, head with the square, and power with the cube of the change

Used across 3 Anvilfield field guides, most in HVAC.
Updated

Scale the curve before finding the duty

The Hydraulic Institute formula reference gives speed ratios of r for flow, r² for head and r³ for pump input power, where r is new speed divided by original speed. These are corresponding-point relationships. Moving every point creates a new pump curve; its intersection with the system curve establishes the delivered flow.

When predicting a new hydronic balance, retain the system's static-head intercept in the calculation. A closed circulating loop dominated by friction behaves differently from a transfer pump lifting water between reservoirs.

Static lift creates a minimum useful speed

Hydraulic Institute's system-curve guidance separates static head from friction head and notes that static head remains when flow is zero. Speed reduction removes pump head while leaving that elevation or pressure requirement in place. Flow therefore falls faster than the simple speed ratio in a system with appreciable static head.

Take a transfer pump with 100 feet of full-speed shutoff head and a 36-foot static requirement. The limiting speed ratio is the square root of 36 / 100, or 0.60. At 60% speed, the scaled shutoff head only equals the static requirement, leaving no head for friction and no useful delivery. The minimum speed for the required operating flow must be higher.

At 80% speed, the corresponding head and power ratios are 0.64 and 0.512. The 48.8% theoretical power reduction is not a prediction that the same volume will be transferred in the same time. Compare energy per delivered volume when production, turnover or irrigation demand fixes the quantity moved.

Impeller trimming and electrical measurements

Hydraulic Institute's pump-curve reference places the constant-efficiency assumption and limited diameter changes beside its affinity equations. Trimming changes the relationship between the impeller and its casing; use the manufacturer's trim curves for selection rather than treating a cut impeller as a geometrically scaled pump.

Compare measured shaft speed, flow and differential head with the scaled curve, then measure electrical input separately. A drive-frequency command is not a power reading. Motor and drive losses remain between pump input power and the electricity meter, especially near the bottom of the operating range.

Distinctions

System curve
The head required by the connected piping at each flow; it determines where the scaled machine curve operates.

Frequently asked questions

Does half speed always mean one-eighth of the electricity?

The cube relationship describes corresponding pump operating points under the affinity assumptions. Static head, changed efficiency and electrical losses alter the installed result.

Can affinity laws predict two pumps running together?

Use the combined pump curve and the system curve. Adding a parallel pump changes the available flow at each head; the intersection does not generally double the original flow.

Sources checked

Also defined as

  • Datacenter: Airflow scales with fan speed, static with speed squared, power with speed cubed
  • Datacenter: Airflow scales with speed, static with speed squared, power with speed cubed