Field glossary · equipment
CRAH
A computer room air handler (CRAH) uses fans and a chilled-water coil, but its service boundary must be described in gallons and pressure as well as cooling kW. Vertiv's CW038 coil holds 5.4 US gal; the CW181 holds 33.4 US gal. Those are contained fluid volumes, not flow rates. Isolation and leak-test planning need the exact coil inventory, valve close-off rating and testing medium alongside the cooling selection.
Computer room air handler, the chilled-water air mover whose fans are commonly kept on generator or UPS during the gap
How much water remains inside a CRAH coil?
Vertiv's Liebert CW Installer/User Guide lists a 5.4 US gal coil volume for the CW038 and 33.4 US gal for the CW181. A unit's cooling-size designation therefore does not provide its contained water volume. Retrieve the coil inventory for the exact model when planning draining, refill, treatment or spill containment.
Three CW181 coils contain 100.2 US gal before adding their valve packages, connecting branches or common headers. Isolating those three units establishes a different fluid inventory from isolating the entire row. Mark the valve boundary on the piping sketch and total the components inside it; the hydronic balancing guide covers the operating-flow record after that circuit returns to service.
Keep gas leak checks separate from piping pressure tests
For a Liebert CW included in a leak test, Vertiv's SL-18060 revision 7 prefers liquid pressure testing and recommends no more than 30 psig when gas is used. Its gas-test guidance accepts pressure decay below 2 psig per hour or a suitable tracer-gas detection method. The manual explains that dry valve and pump seals may not retain high gas pressure.
Vertiv recommends isolating the unit during leak checking of field-installed piping. Identify the test medium and isolation boundary on each test record. The 30 psig recommendation concerns gas testing of the unit; it is neither a hydraulic working-pressure rating nor a building-piping acceptance pressure. A factory test also leaves the field-added connections to be checked.
Valve close-off pressure determines whether isolation works
Vertiv's CW guide specifies leak detection that closes both supply and return shutoff valves and recommends spring-return valves with close-off ratings at least equal to supply-water pressure. The valve-and-actuator assembly must seat against the maximum coolant-system pressure during a leak. A valve body's pressure rating alone does not establish that closing capability.
Write the selected actuator and close-off rating beside the valve model. A command to close, a position indication and confirmed cessation of flow are three separate observations. Include all three in the assigned zone's leak detection commissioning record.
Distinctions
- Coil water volume
- This is a static inventory in gallons or liters. Coil flow is a rate in gpm or L/s, so the two numbers serve different calculations.
- CRAC water circuit
- Water in a CRAC can reject condenser heat. Identify the circuit on the piping schematic before applying a chilled-water-coil service record to that equipment.
Frequently asked questions
Can a CRAH be supplied through a water economizer?
Yes. The local coil receives the selected chilled-water conditions regardless of which upstream plant component produced them. The cooling systems guide describes that heat-rejection chain.
Is the coil volume the amount of coolant to order?
It is one part of the refill inventory. Add the branches and fittings inside the drained boundary, then apply the approved treatment concentration to that complete volume.
Sources checked
Also defined as
- HVAC: Computer room air handler, a chilled-water AHU built for a data hall
- Computer room air handler, a chilled water coil unit with no compressor, fed from a central plant