SAT

A SAT (site acceptance test) documents the installed equipment's acceptance boundary, which can extend from delivery checks to energized functional operation. Put that boundary in the test register before using a commissioning-level label. USACE's generator field-test specification, for example, requires recently calibrated instruments and tests of site-built services that a receiving photograph cannot establish. The FAT baseline identifies the earlier factory condition; SAT must account for the installed condition.

Site acceptance test; JLL uses this label for Level 2. The project plan defines its scope, including receiving and installation verification.

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Resolve SAT before assigning it to Level 2

IEC 62381:2024, edition 3.0, separates site acceptance testing (SAT) from site integration testing (SIT) in process-industry automation. It ties the acceptance program to the automation specification and the parties' agreed responsibilities. Use those named activities to allocate site tests, rather than assuming that a SAT heading means visual receiving checks only.

Anvilfield's commissioning levels guide places the SAT label at a delivery gate. For a package requiring installed operation, use a register with separate rows for receipt, site connections, functional results and interface tests, as needed for the modular deployment handoff. A delivery signature closes only the receiving row.

Generator site readings need stated instrument accuracy

For generator projects using USACE UFGS 26 32 15, February 2026, Section 3.6.1.4 requires field-test instruments calibrated by a recognized standards laboratory within 30 days before testing. Identify the instruments used on site and their calibration dates; an earlier factory report does not establish their current calibration.

UFGS 26 32 15 specifies field-test instrument accuracy within plus or minus 1.5% for voltage, current, real power and reactive power, 0.5% for frequency, and 3% for power factor. These percentages qualify the measuring instruments. They do not define acceptable generator voltage, frequency or load regulation.

The cited clause does not state whether those percentages use the reading, selected range or full scale as their basis. Record that basis from the instrument data and resolve its use in the approved test plan before converting a percentage to volts or hertz. Include any additional count or digit term in the manufacturer's accuracy expression.

Separate shipped equipment from site-built connections

UFGS 26 32 15 Section 3.6.2 requires functional tests of external fuel, coolant and lubricating-oil piping, electrical continuity, insulation and protective devices before connection to the generator set. Mark the package connection points on the test drawing and attach the site results to those boundaries. This identifies the installed work absent from the factory setup.

List factory findings carried forward, shipment changes, installed software and the final connection drawings beside the site results. For a packaged assembly, the report should show where the manufacturer's tested package ends and the site-built work begins. Close the applicable site tests against that boundary before the integrated test relies on it.

Distinctions

SAT in HVAC controls
SAT also means supply air temperature in an air-handler points list. A value in degrees refers to the controlled air temperature, not an acceptance stage.

Frequently asked questions

Can a SAT include energized testing?

Yes. Include the operating mode, permitted test conditions and required participants in the approved site test. A receiving-only SAT and an operational SAT need different evidence even when the project uses the same acronym.

Does site acceptance repeat every factory test?

The accepted scope identifies required repetition, checks for shipment or configuration changes, and tests of site-built interfaces. Map those obligations to the factory baseline rather than duplicating report titles.

Sources checked

Also defined as

  • HVAC: Supply air temperature, the conditioned air leaving the unit, often reset with load
  • Site acceptance test, the on-site re-verification after the module is set and connected