Load bank
A load bank is test equipment with switchable electrical demand, selected for the real and reactive power a source must deliver. Its nameplate capacity belongs to specified voltage, phase and cooling conditions. A bank labeled 600 kW does not necessarily deliver a 600 kW test at another voltage. Before booking equipment, establish the load available at the test voltage, the resulting step sizes and the separate supplies needed by its fans and controls.
Equipment that creates electrical or thermal load to stand in for the IT load during the test
Calculate resistive load at the voltage on site
Avtron's Load Bank Rating Factors white paper states that a resistive bank's absorbed power changes with the square of applied voltage. For an unchanged resistance, available kW = rated kW x (applied voltage / rated voltage)^2. A 600 kW bank rated at 480 V therefore absorbs 450.7 kW at 416 V.
At 208 V, that same 480 V resistance configuration delivers only 112.7 kW: 600 x (208 / 480)^2. A selectable-voltage bank changes its internal configuration, so use the rating for the selected connection. The calculation follows a resistance setting; it does not override a manufacturer's separately published rating. Avtron also prohibits applying voltage above the bank's voltage rating.
The load steps shrink with the total rating
Avtron specifies that individual resistive load steps derate by the same voltage-squared factor as total capacity. A nominal 25 kW step at 480 V becomes 18.8 kW at 416 V. Five such steps produce about 93.9 kW, which matters when a script calls for a measured 100 kW increment.
Write requested and measured steps separately in the generator load-bank test record. The switch labels give nominal steps for a connection setting; source metering shows what was applied at the measured voltage.
Size the reactive section as well as the kW
Avtron publishes combined resistive-reactive banks with 0.8 power-factor ratings. For a 600 kW test at 0.8 lagging power factor, the equipment schedule needs 750 kVA and 450 kVAR: kVA = kW / power factor, and kVAR = square root of (kVA squared - kW squared). Specify those quantities together so the reactive section is included in the rental.
At 480 V, balanced three-phase current for that 750 kVA test is about 902 A. Applying 600 kW at unity power factor produces about 722 A at the same voltage. The real-power readings agree, but the generator and distribution carry different current. Use the intended power factor when checking whether the test loads the alternator to the specified duty.
Cooling capacity belongs on the equipment schedule
Avtron identifies 3,000 ft above sea level as the point beyond which reduced air density warrants application-specific cooling and loading information from the manufacturer. A voltage calculation alone does not establish the allowable test duty at altitude. Put the site elevation and the bank's approved operating conditions next to its electrical rating.
The rating paper also distinguishes resistive-element behavior from blower behavior at different supply frequencies. A fan supplied from the test source must suit that source's voltage and frequency, or use the bank's documented external supply arrangement. The load-bank acceptance guide covers how the applied load enters the acceptance record.
Distinctions
- Heater load in the white space
- A heater fed through the distribution under test loads both that electrical path and the room cooling. An outdoor bank dissipates its heat outdoors. The same electrical kW does not place the same thermal demand inside the hall.
Contractors pricing recurring generator tests follow public electrical solicitations and early capital plans in PorchRocket Bid Control.
Frequently asked questions
Is nominal load-bank kW enough information for a rental request?
Specify the test voltage, phase, frequency, required kW and kVAR, smallest useful step, duty and fan supply. These determine whether the bank can apply the scripted demand at the actual connection point.
Sources checked
Also defined as
- Electrical: Device that applies an artificial electrical load and dissipates the generator's output as heat