OPR / BOD
A requirement identifier connects the owner's project requirements (OPR) to the basis of design (BOD), its supporting calculation and the acceptance test. The owner accepts the outcome; the design team documents the engineering response. Stable identifiers and controlled revisions let a reviewer follow an equipment substitution through those records without reconstructing the decision from meeting notes or treating a substitution request as an approved requirement change.
Owner's project requirements and basis of design, the requirement and the design team's documented answer to it
Turn an owner expectation into an acceptance measure
WBDG's commissioning-document guidance assigns development of the OPR to the owner, assisted by the commissioning provider, and calls for owner acceptance of revisions. Record who accepted the requirement and when. An unsigned meeting preference does not carry the same status as the accepted requirement.
Give each outcome a stable identifier. A project's OPR-C01 calls for rack inlets at or below 27 C for 30 minutes at a 1,200 kW IT load with cooling unit C3 isolated. The owner has selected the temperature, duration and outage condition together. The test record must identify the rack-inlet measurement locations as well as those operating conditions.
Show the design response without rewriting the requirement
WBDG describes the BOD as both narrative and analytical documentation prepared by the design team to explain how the OPR is met. Its contents include system selection, integration, controls and code applications. Attach the actual calculation or selection reference to the requirement identifier rather than copying the owner's sentence into a design report.
For OPR-C01, the BOD response identifies plant capacity with C3 isolated, the water and air conditions used in equipment selections, and the controls that establish that state. Its calculation identifier travels into the commissioning script. Keep that chain with the commissioning-level documents.
| Record | What the reviewer follows |
|---|---|
| OPR-C01 | Owner acceptance criterion, load and outage condition |
| BOD response to OPR-C01 | Capacity calculation, selection data and controls revision |
| Functional test for OPR-C01 | Measured temperatures, duration, operating state and result |
Control a substitution across all affected documents
WBDG's commissioning roles guidance assigns the commissioning provider review of the BOD against the OPR. That review does not transfer design authorship from the design team to the reviewer. Keep the design response, review comment and owner's acceptance as separate approvals.
A substituted cooling unit with a different restart delay affects more than its equipment schedule. Follow the requirement identifier into the load calculation, controls sequence, test duration and operator training. Close the substitution only when those references agree. Retain the preceding revision so a later test discrepancy can be traced to the decision that changed the design.
Distinctions
- Commissioning plan
- The plan assigns verification work, timing and responsibilities. It does not replace the owner requirement or the design explanation.
- Current facility requirements
- WBDG uses CFR for the operating baseline in existing-building commissioning, where present use and operating needs govern the work.
Frequently asked questions
Who approves an OPR change during construction?
The owner or authorized representative accepts the revised requirement. Record the design team response and commissioning review beside that acceptance rather than treating a contractor substitution request as the approval.