Field glossary · measurement
Benchmark
A benchmark supplies a recoverable elevation for transferring heights with a level or survey instrument. Starting from 100.000 ft, a backsight of 4.215 ft and foresight of 3.770 ft establish the next point at 100.445 ft. That calculation transfers the starting height system; it does not convert a local datum to NAVD 88. Record the mark, datum, height type, and foot definition with the elevation.
A point of known elevation, tied to the project datum, used as the reference for all vertical layout
Transfer a benchmark elevation with rod readings
NOAA NGS's account of differential leveling describes using a reading on known control to establish the instrument's sight-line elevation, then subtracting the rod reading at the unknown point. In field-book notation, height of instrument = benchmark elevation + backsight; new elevation = height of instrument - foresight. Height of instrument here means the elevation of the optical line, rather than the tripod's height above the ground.
For the readings above, the sight line is 104.215 ft and the transferred elevation is 100.445 ft. A repeat run returning to a mark assigned 100.000 ft but calculating 100.018 ft has a +0.018 ft closure error. Enter that discrepancy separately from the assigned elevation. It is a measured check on the transfer, not a reason to overwrite the benchmark's value.
How to identify a published benchmark
NOAA NGS identifies each datasheet record with a six-character permanent identifier consisting of two uppercase letters followed by four digits. That PID retrieves the record; the designation and stamping help match it to the physical monument. Read the recovery history and height-source information as well as the elevation. A disk being present does not establish that its published height was determined by precise leveling.
An imported point named BM1 needs its source PID and height-determination method in the construction layout record. Keep the original datasheet with the import file. A shortened point name should still lead back to the record that establishes whether its height came from leveling, GNSS observations, or another determination.
Why GNSS height and benchmark elevation disagree
NGS datasheet documentation expresses the height relationship as H = h - N, where H is orthometric height, h is ellipsoid height, and N is geoid height. NGS provides a geoid-height service specifically for converting GNSS-derived NAD 83 ellipsoid heights to NAVD 88 orthometric heights. The model and reference frame must correspond to the supplied coordinates.
With h = 82.463 m and N = -30.127 m, the computed orthometric height is 112.590 m. Subtracting a negative geoid height raises the answer. Treating 82.463 m as the benchmark elevation would introduce a 30.127 m discrepancy before any rod reading. Save the original height type and the conversion alongside the imported point.
Which foot belongs in an older control file?
NIST defines the international foot as exactly 0.3048 m and the legacy U.S. survey foot as exactly 1200/3937 m. NIST retired the survey foot for new applications on January 1, 2023, while retaining its use for historical and legacy work. Changing a controller label does not convert an older coordinate file.
An elevation handoff should spell out the foot definition whenever the source uses feet. Preserve the original values and identify any converted copy. This matters when the same control file also carries large horizontal coordinates: the small unit difference scales with the coordinate magnitude. Carry the resolved file into grade control before comparing cut and fill.
Distinctions
- Datum
- Two benchmarks can have different elevations in one datum; the same benchmark can have different published elevations under different datums. A datum name and a mark identifier answer different questions.
- Performance benchmark
- In an estimating or operating report, benchmark means a comparison value. It does not identify survey control or establish a project elevation.
Frequently asked questions
Does a benchmark elevation have to be above sea level?
A project can assign a convenient local elevation. Label it as an assigned project datum and preserve its documented relationship to published control when that relationship is established.
Can I use the elevation stamped on the disk?
Retrieve the identified mark record and its current height information. Stamping identifies the monument; an old stamped elevation is not a substitute for the published or project-assigned value.
Sources checked
Also defined as
- Paving: A fixed point of known elevation that the whole site's grades are referenced to