Field glossary · process
Cut and fill
Cut-and-fill balance compares usable excavation with placed soil after converting both quantities to the same volume state. At a project yield of 0.90 compacted cubic yard per bank cubic yard, 1,800 bank cubic yards provide 1,620 compacted cubic yards. The remaining 180 cubic yards on a 1,800-cubic-yard fill requirement are a compacted-volume deficit, before accounting for haul volume or rejected soil.
Excavating soil from high areas (cut) and placing it in low areas (fill) to reach the design grade
Calculate volume between cross sections
Iowa DOT's Design Manual, Section 5A, calculates average-end-area volume as the mean of two end areas multiplied by their spacing. For cut areas of 120 and 200 square feet, 50 feet apart, the volume is (120 + 200) ÷ 2 × 50 = 8,000 cubic feet, or 296.3 cubic yards.
Calculate cut and fill areas separately at each station. Netting a cut area against a fill area can conceal the movement required even where the net result approaches zero. Keep the station range with each quantity so the calculation can be traced back to the surveyed sections.
Iowa DOT Section 5A calls for a new end area whenever entrance geometry changes and identifies entrances, ditch checks, and similar features as possible additions outside the main corridor calculation. These are quantity boundaries to inspect when the model total disagrees with the estimator's takeoff.
Balance reusable soil by volume state
Write the conversion direction beside every shrink or swell factor. A factor expressed as bank volume required per compacted volume is the reciprocal of compacted yield per bank volume. Applying the same numeric factor in both directions creates a false balance.
With a project-established yield of 0.90 compacted cubic yard per bank cubic yard, 1,800 bank cubic yards of reusable cut produce 1,620 compacted cubic yards. A requirement of 1,800 compacted cubic yards leaves a 180-cubic-yard compacted deficit. Rejected material and separately stripped topsoil belong outside the reusable-cut subtotal. Supplying that deficit from the same material requires 180 ÷ 0.90 = 200 additional bank cubic yards.
Iowa DOT Section 5C weights shrink factors by the volumes actually reused in fill, excluding the portion designated for waste. An equal average of two material factors would give a small soil deposit the same influence as the dominant excavation material.
| Quantity on this takeoff | Volume basis | Calculated amount |
|---|---|---|
| Reusable excavation | Bank | 1,800 cubic yards |
| Yield from that excavation | Compacted at 0.90 yield | 1,620 cubic yards |
| Remaining fill requirement | Compacted | 180 cubic yards |
| Additional reusable excavation | Bank at the same yield | 200 cubic yards |
Separate the pay quantity from the haul plan
In Iowa DOT Section 5A, Class 10 Roadway and Borrow excavation is measured as cut volume without adding shrink to that cut quantity. Truck capacity, compacted fill requirement, and excavation payment therefore describe different quantities even when all are labeled cubic yards.
Use the earthwork guide for placing and controlling the work, and preserve the quantity basis with the estimate. A haul subcontract priced per load needs the agreed loading basis; the design surface comparison alone does not supply it.
Distinctions
- Grade-control cut or fill
- A machine display usually reports a vertical distance to the design surface at a point. Multiplying that reading by a whole site area is not a surface-volume calculation.
Frequently asked questions
Does balanced earthwork mean no imported soil?
Only when usable cut, required fill, material restrictions, and volume conversions balance. Equal unadjusted surface volumes leave those material questions unresolved.
Sources checked
Also defined as
- Paving: The difference between existing ground and design grade: cut where high, fill where low