Field glossary · measurement
Finish grade
A finish-grade elevation must identify the surface being delivered: top of paving, prepared soil, or installed turf. At a building, that target also has to preserve cladding clearance and usable doorway transitions. A soil grade of 124.40 ft beneath siding ending at 124.90 ft leaves 6 inches of separation. Naming both surfaces makes that dimension checkable before the crew spreads soil or sets the adjoining walk.
The surface elevation when the job is done, carrying the drainage slope; rough grade is left low for topsoil
Read the surface named beside the spot elevation
Treat each spot elevation as a point-and-surface pair. A curb top, gutter flow line, and adjacent soil need separate identifiers even when they fall within the same survey station. Add those identifiers to the earthwork handoff so the paving and landscape crews do not build to each other's target.
Record both sides of a paving joint, the finished entrance landing, and the cladding termination beside a planting bed. A broad grid of lawn elevations does not describe those interfaces. Rounding 124.37 ft to 124.4 ft discards 0.03 ft, or 0.36 inch, already larger than the ADA allowance for an unbeveled vertical change. Measure small joint lips directly instead of inferring them from rounded survey elevations.
Protect siding clearance when grades rise
James Hardie's HardiePlank HZ5 instructions, HS11117 dated September 2019, show 6 inches of clearance from ground to siding. James Hardie also specifies a 2-inch minimum above adjoining slabs, paths, and steps in those HZ5 instructions. A topsoil addition and a new paved walk therefore need different clearance checks, even where they share a building wall.
With the siding bottom at elevation 124.90 ft, the 6-inch ground clearance limits adjacent soil to elevation 124.40 ft. A proposed bed at 124.65 ft would leave only 3 inches below that siding. If the level's horizontal sight line is at elevation 128.00 ft, a rod standing on the target soil surface reads 3.60 ft; a 3.35-ft reading identifies the high bed and a required 0.25-ft cut. This translates the clearance into a setting the grading crew can use.
Mulch replenishment, raised edging, and later overlays change the completed interface. Identify the soil and added surface layers separately so maintenance does not gradually close the clearance left at turnover.
How much lip is allowed at an accessible walk?
The 2010 ADA Standards, section 303.2, permit an untreated vertical change in level of at most 1/4 inch where changes in level are allowed. The 2010 ADA Standards, section 303.3, require changes above 1/4 inch through 1/2 inch to be beveled at a slope no steeper than 1:2, measured as vertical rise to horizontal run. Section 303.4 sends larger changes to the ramp or curb-ramp provisions.
Applying the 2010 ADA Standards section 303.3 to a 3/8-inch paver-to-concrete lip, a bevel spanning the full rise needs at least 3/4 inch of horizontal run. Measure both dimensions at the joint. A larger earthwork tolerance does not relax that transition geometry, and meeting the bevel limit does not establish the walk's running or cross slope.
Release the finished interfaces to the next trade
Use a short elevation schedule that pairs the surface name, design elevation, measured elevation, and adjoining constraint. Include the instrument datum once and retain point identifiers that match the plan. Photograph the measurement location so a later overlay or landscape change can be compared with the original handoff.
Connect the entrance landing, paving edge, and receiving soil on the drainage grading sketch. Show both the finished target and the clearance that limits it. When preserving the siding gap lowers a walk edge, that revision must reach the landscape drawing as well as the paving drawing.
Distinctions
- Subgrade elevation
- The supporting formation lies below the completed surface by the installed section thickness. A finish elevation identifies the destination; the section determines the necessary excavation elevation.
- Finish floor elevation
- The building floor datum establishes an interior reference. It does not automatically set the exterior landing, threshold top, or adjacent soil at the same elevation.
Frequently asked questions
Is finish grade the top of soil or the top of sod?
Use the surface identified by the grading and landscape details. Where the documents label both, retain separate elevations instead of treating the sod thickness as an unspecified allowance.
Can a lawn grading tolerance be used at a sidewalk joint?
The joint must satisfy its applicable surface-transition requirements. The surrounding landscape elevation tolerance does not authorize an oversized vertical lip on an accessible route.
Sources checked
Also defined as
- The smooth final surface at the design elevation, topsoiled and ready for sod, seed, or paving