Proof-roll

Proof-rolling maps the response of prepared ground to a documented wheel load. Tire pressure, ballast, moisture and pass coverage define the test, so a firm track under one vehicle does not establish the response under another. NCDOT's 2024 specification calls for a proof roller with 48 to 50 tons load capacity and 68 to 72 psi tires. Its observed movement remains separate from a laboratory-referenced percent-compaction result.

A loaded pass to find soft subgrade; on a permeable section it can itself compact the infiltrating soil, so it is often prohibited

Used across 2 Anvilfield field guides, most in Paving.
Updated

Define the load case before interpreting movement

NCDOT's 2024 Standard Specifications, Section 260, specify proof-roller load capacity of 48 to 50 tons and tire pressures of 68 to 72 psi unless otherwise authorized in writing. A pass by lighter equipment or one with different tire pressure establishes a different loading condition. Record the actual ballast and tire pressures with the observation.

FHWA's Geotechnical Aspects of Pavements distinguishes density verification from field observations of support. A density test establishes the state of the sampled material against a reference; a proof roll exposes a response over a moving loaded footprint. Locate each density sample on the same plan as the proof-roll observations in the base-compaction record.

A pass and complete coverage are not the same thing

NCDOT's 2024 specification starts proof rolling after the roadbed is completed within 0.5 foot of final grade and specifies operating speeds of 225 to 300 feet per minute. The test elevation and speed belong in the report alongside the load, because they define the observed response. That speed range is about 2.6 to 3.4 mph.

NCDOT's 2024 specification defines coverage as contact between the pneumatic tires and the entire width being tested. Count covered ground, not trips by the machine. Gaps between tires and shifts in the travel path can leave strips untouched; sketch the pass pattern and tie each failure to station and offset.

Separate a permanent impression from rebound

NCDOT's Construction Manual, Section 260 distinguishes material that compresses and stays compressed from material that compresses and then rebounds appreciably; the latter triggers further investigation. Photograph or video the response immediately behind the tires, because a still photograph after the vehicle has passed can miss the rebound.

NCDOT's 2024 Section 260 requires the Engineer to be present and corrected areas to be proof-rolled again. Match repeat coverage to the repair boundary and retain the same recorded loading conditions. In an infiltration footprint, establish the permitted verification method from the permeable installation plan before trafficking the exposed soil.

Distinctions

Proof compaction
Compaction deliberately densifies material. A proof roll observes support under an established load and is not an instruction to keep loading a pumping surface until it stops moving.

Frequently asked questions

Does passing a proof roll mean the soil has 95 percent compaction?

No. Percent compaction comes from dry density divided by the specified laboratory reference density. A proof-roll record contains observations, loading and coverage instead.

Sources checked

Also defined as

  • Landscaping: Driving a heavy loaded vehicle over the subgrade to find soft spots that pump or rut

Where this shows up

Related guides

Next step: Find roadbed preparation work

Back to the full field glossary