Field glossary · process
WMA
WMA means warm-mix asphalt, a reduced-temperature production approach whose qualification includes coating and compactability. NCHRP Report 691 recommends at least 95 percent of coarse particles fully coated and compares gyrations at the planned compaction temperature with a test 30°C, or 54°F, cooler. These laboratory checks establish more than an additive name on a ticket. Field acceptance still uses the project's approved mixture, production targets and density requirements.
Warm mix asphalt, the same mix produced and placed roughly 30 to 100°F cooler than hot mix
Coating is tested at the proposed mixing temperature
NCHRP Report 691 recommends at least 95 percent of coarse aggregate particles fully coated in its WMA design evaluation. That criterion tests whether the reduced-temperature mixing process distributes binder effectively. A specimen that reaches the target laboratory density still needs the separate coating evaluation.
NCHRP Report 691 bases its 95 percent coating criterion on laboratory mixing with a planetary mixer; its training appendix reports lower coating with a bucket mixer using the same mixing times. Identify the mixer and preparation method in the qualification record for the proposed warm-mix process.
The compactability ratio measures temperature sensitivity
NCHRP Report 691's 2011 proposed design procedure compares gyrations needed to reach 92 percent of maximum theoretical density at the planned compaction temperature and at 30°C, or 54°F, below it. Appendix A, item 8.3.12, recommends a lower-temperature-to-planned-temperature gyration ratio no greater than 1.25. This is a laboratory comparison, separate from in-place pavement acceptance.
A mixture requiring 40 gyrations at its planned compaction temperature and 48 at the lower temperature has a ratio of 1.20. If the lower-temperature result requires 54 gyrations instead, the ratio is 1.35 and exceeds the report's recommended criterion. Preserve both original gyration counts so the reported ratio can be reproduced.
Report fuel savings against an identified production baseline
FHWA's Every Day Counts WMA reference describes production temperatures 30 to 120°F below conventional HMA and typical manufacturing fuel reductions of 20 percent. That reported benefit is a plant-production comparison, not a promise that every load or technology saves the same amount.
For a plant baseline of 2.5 gallons of fuel per ton, a 20 percent reduction corresponds to 2.0 gallons per ton. Over 1,000 tons the difference is 500 gallons. Compare runs with the same fuel-accounting boundary and document aggregate moisture, recycled content and throughput, because they affect the measured result.
Record the production temperature, laboratory gyration ratio and fuel per ton separately in the plant production file. Comparing those measured results with a matched HMA run establishes what changed; the technology name alone does not.
Distinctions
- Warm-mix technology at hot-mix temperature
- The technology can serve as a compaction aid during conventional-temperature production. Identify the actual temperatures before classifying the production as reduced-temperature WMA.
Frequently asked questions
Does 92 percent in the compactability calculation set the road density requirement?
No. It is the laboratory comparison point used to calculate gyrations. The project specification establishes the in-place pavement acceptance requirement.
Sources checked
Also defined as
- Warm mix asphalt, the same mixes produced and placed at a lower temperature