RAP / RAS
RAP means reclaimed asphalt pavement; RAS means reclaimed asphalt shingles. Their percentages describe different feedstocks, not equivalent binder doses. FHWA's 2018 review reports 19 to 20 percent binder in manufacturing-waste shingles, much more than the 5 percent RAP binder used in the worked calculation below. Calculate each stream's binder contribution separately, retain its source identity, and distinguish the total reclaimed binder ratio from the allowable limit for either material.
Reclaimed asphalt pavement and reclaimed asphalt shingles, recycled binder and aggregate reused in the mix
Why equal recycled percentages do not mean equal binder
FHWA-HIF-18-059 reports binder contents of 19 to 20 percent for manufacturing-waste asphalt shingles and 30 to 36 percent for post-consumer shingles. Those reported ranges explain why replacing a pavement-feed percentage with the same shingle-feed percentage changes the binder balance substantially.
FHWA-HIF-18-009 describes typical RAS additions of three to five percent of total mixture mass in its 2018 practice survey. The report attributes higher VMA to hard granules and fibers, with dust offsetting part of that increase. Binder accounting therefore needs the accompanying aggregate and volumetric results.
Calculate reclaimed binder ratio with both streams
FHWA-HIF-18-059 defines reclaimed binder ratio as reclaimed binder divided by total mixture binder. Calculate the binder contribution of RAP and RAS separately, add those contributions and divide by the total binder quantity. Material percentage alone cannot provide that ratio.
In 1,000 tons of mix, 150 tons of RAP at 5 percent binder contribute 7.5 tons, and 30 tons of manufacturing-waste RAS at 20 percent binder contribute 6 tons. With 60 tons of total binder, the reclaimed binder ratio is 13.5 divided by 60, or 22.5 percent. The recycled material fraction is 18 percent. Both numbers are correct because their denominators differ.
The example contains a RAP binder ratio of 12.5 percent and a RAS binder ratio of 10 percent. FHWA-HIF-18-059 cautions against treating those contributions as equivalent when setting allowable limits because shingle binder stiffens the blend more strongly. The 22.5 percent sum is mass accounting; it does not establish compliance with separate RAP and RAS limits.
Processing limits and shingle source remain separate gates
INDOT's 2026 Standard Specifications require RAP entering the plant to pass a two-inch sieve and RAS to pass a three-eighth-inch sieve, with an additional RAP aggregate size check against the mixture being produced. The same specifications prohibit blending pre-consumer and post-consumer shingle streams for HMA use. A stockpile name cannot substitute for those processing and source records.
Keep separate RAP and RAS feed settings in the plant production record and identify the planned temperature when the recipe uses warm-mix production. A change to either stream needs a new binder balance even if their combined material percentage stays constant.
Distinctions
- Binder availability
- Calculated binder content counts binder present in the feedstocks. Availability describes how much participates in the mixture; an accounting ratio does not measure activation or blending.
Frequently asked questions
Are RAP and RAS interchangeable in the same approved recipe?
No. Substituting one changes binder quantity, binder stiffness and aggregate characteristics. The approved design identifies each feedstock and its permitted amount.
Can two mixes have the same reclaimed binder ratio but different stiffness?
Yes. FHWA-HIF-18-059 identifies stronger stiffening from RAS than RAP at an equivalent reclaimed binder ratio. Preserve the two contributions and the blended-binder results when comparing recipes.
Sources checked
Also defined as
- Reclaimed asphalt pavement and shingles; WMA's lower temperature helps carry more of it
- Reclaimed asphalt pavement and recycled asphalt shingles, fed back into new mix