NMAS
NMAS means nominal maximum aggregate size, a sieve-based asphalt mixture designation. In the FHWA Superpave convention, a 12.5 mm NMAS mixture has a 19 mm maximum-size designation, so some particles can exceed 12.5 mm. Determine the label from the combined aggregate grading on the job mix formula. The plant mix number and sieve results are needed to establish that delivered material matches the named mixture.
Nominal maximum aggregate size, one sieve above the first to retain over 10 percent; names the mix and sets the lift
Find NMAS from the upper sieves
Use the FHWA Superpave convention as a worksheet: start at the large sieves, calculate the fraction caught on each sieve from successive percent-passing results, and flag the first fraction above 10 percent. Assign NMAS from the immediately larger standard opening. Exactly 10 percent does not cross that threshold.
Take a grading with all material passing 19 mm, 96 percent passing 12.5 mm and 84 percent passing 9.5 mm. The 12.5 mm sieve holds 4 percent, while the 9.5 mm sieve holds another 12 percent. The first retention above 10 percent occurs at 9.5 mm, so the nominal maximum size is 12.5 mm. Enter that result beside the mix identifier in the Superpave design record.
| Sieve opening | Percent passing | Retained on this sieve |
|---|---|---|
| 19 mm | 100% | 0% |
| 12.5 mm | 96% | 4% |
| 9.5 mm | 84% | 12% |
Maximum size and nominal maximum size are different labels
FHWA pairs nominal and maximum sizes by adjacent openings in its standard sieve series: 9.5 mm NMAS pairs with 12.5 mm maximum, and 12.5 mm NMAS pairs with 19 mm maximum. The maximum-size label is a separate column from NMAS, not an interchangeable heading for the same result.
The same FHWA reference lists 9.5, 12.5, 19 and 25 mm among the Superpave nominal mixture designations. Those labels identify grading families, not asphalt binder grades or strength ratings. A finer nominal mixture is not automatically a weaker material, and two mixtures carrying the same nominal size can have different proportions of sand and intermediate aggregate.
How is aggregate size checked after binder extraction?
ASTM D5444-24 determines the size distribution of fine and coarse aggregate extracted from asphalt mixtures by sieving. Use the extracted aggregate grading to compare a production sample with the approved JMF. A gyratory density result measures compaction behavior and cannot supply those missing percent-passing values.
Once the grading is identified, carry its designation into the mix and layer selection guide. A millimeter label copied from an old takeoff is not evidence that the plant supplied the same JMF. Record the approved mix number as well as NMAS when comparing laboratory and delivery records.
Distinctions
- Coarse-graded mix
- This describes the position of the grading curve through intermediate sieves. A nominal size alone does not establish whether the mix is coarse or fine graded.
Frequently asked questions
Is a 12.5 mm mix exactly the same as half-inch stone?
Half-inch is a customary mix label. Use the specified 12.5 mm sieve designation and JMF grading when deciding acceptance.
Does exactly 10 percent retained establish the controlling sieve?
The FHWA Superpave definition uses more than 10 percent. Continue down the sieve series when a retained fraction is exactly 10 percent, using the reporting precision required by the test and project specification.
Sources checked
Also defined as
- Nominal maximum aggregate size, a measure of the largest stone in the mix, read from the gradation