Field glossary · process
Compaction window
The compaction window is the time interval available for density-building passes at one asphalt station; its reference time and temperature basis belong with the result. With an eight-minute allowance measured from screed passage at 20 ft/min, a point 120 ft behind the screed has already used six minutes. Two minutes remain there. MnDOT's PaveCool reports average lift temperature, while infrared instruments read the surface.
The time and temperature range in which the mat can be rolled to density before it cools past stop temperature
Enter compacted thickness and identify the temperature basis
MnDOT's PaveCool help specifies final compacted lift thickness and the temperature of mix entering the paver hopper as model inputs. Entering 2.5 in of loose material for a 2 in finished lift adds 25% to the model's thickness input. Use 2 in in the cooling model and keep the loose-depth measurement in the screed record. Attach the cooling run to the station and lift it represents when preparing the rolling plan.
The PaveCool help defines its cooling curve as average lift temperature. Label field readings by instrument and position, such as surface infrared or an in-lift probe at a recorded depth. A surface reading and the modeled lift average describe different quantities; comparing them as though they were identical gives a false temperature margin.
Turn the time allowance into first-pass and last-pass deadlines
For continuous paving at constant speed, elapsed minutes since screed passage equal distance behind the screed divided by paving speed. At 20 ft/min with an eight-minute allowance after screed passage, the last density-building pass must reach each station before it lies 160 ft behind the screed. If completing the pattern at that station takes three minutes, the first pass must arrive by minute five, or 100 ft behind the screed. The 160 ft line marks completion, not the place to begin rolling.
A two-minute paver stop still ages every exposed station by two minutes, although its distance behind the screed stays unchanged. Use the recorded screed-passage time and last-pass time at a marked station during interruptions. Resume the calculation from that station's actual age when paving restarts; its cooling history continues through the stop.
Check roller capacity separately from the cooling deadline
NAPA's 2025 Asphalt Paving Handbook gives 75% to 85% as the typical roller efficiency factor for production calculations that account for reversals and water refilling. Its section 8.5 calculation divides paving width by effective roller width and rounds the track count up to the next whole number. Keep track count across the width separate from passes over each point.
A roller traveling at 264 ft/min, or 3 mph, with an 80% factor has 211.2 effective ft/min. With three tracks across the width and four passes per point, its supported paving speed is 211.2 ÷ (3 × 4) = 17.6 ft/min. At a paver speed of 20 ft/min, unfinished rolling accumulates. Calculate each stage of the rolling and density plan this way, then verify that its passes also finish within the station's time allowance. The efficiency factor discounts production capacity; it does not change the cooling curve.
Keep laboratory compaction temperature off the field stop setting
The Asphalt Institute's December 2016 advisory uses a viscosity of 0.28 ± 0.03 Pa·s to determine laboratory compaction temperatures for unmodified binders. Those temperatures support mix-design volumetrics. The Asphalt Institute advisory explicitly separates them from actual field mixing and compaction temperatures, including modified-binder work. Keep the laboratory temperature beside the mix-design results and record the field starting and stopping temperatures separately in the cooling run.
Frequently asked questions
Can I reuse a daytime PaveCool run for night paving?
Update the date and paving start time along with the measured conditions. MnDOT says PaveCool uses the entered time to calculate sun angle and solar heat input. A saved daytime run carries the wrong solar input into a night shift; save the revised run with the cold-weather paving plan.
Which stopping temperature belongs in a PaveCool record?
MnDOT's PaveCool overview describes cooling to 175°F and says versions 2.4 and later accept user-selected starting and stopping temperatures. Save the selected pair with the run. MnDOT's help gives binder-specific guidance priority for polymer-modified asphalt, so retain the binder supplier's temperature instructions with that selection. The PaveCool overview documents the selectable settings.
Sources checked
- MnDOT: PaveCool help, compacted thickness, hopper temperature, average lift temperature, solar inputs, and modified-binder guidance
- MnDOT: PaveCool overview, 175°F reference endpoint and selectable starting and stopping temperatures
- NAPA: Asphalt Paving Handbook, 2025 edition, section 8.5, roller efficiency and production calculations
- Asphalt Institute: Determining Laboratory Mixing and Compaction Temperatures, approved December 7, 2016