Field glossary · measurement
% Gmm / air voids
Percent Gmm expresses compacted asphalt bulk specific gravity as a percentage of the corresponding mixture's theoretical maximum specific gravity: 100 × Gmb ÷ Gmm. Air voids equal 100 minus that percentage when the bulk and maximum values represent the same mixture. The relationship is exact; uncertainty enters through sampling, specimen-volume measurement and selection of the Gmm reference. Preserve those inputs with the reported percentage.
In-place density as a percentage of the theoretical maximum specific gravity; the remainder is roughly the air-void content
Air voids are a volume fraction
WSDOT's January 2026 Materials Manual, WAQTC TM 13, calculates air voids as 100 × (Gmm - Gmb) ÷ Gmm and reports the result to 0.1 percentage point. The percentage describes air volume within the compacted mixture. It does not describe the weight of air, the percentage of aggregate missing, or the amount of binder absorbed into aggregate pores.
This arithmetic applies to either a compacted laboratory specimen or a field core, but the specimen identity changes what the result establishes. A laboratory design result characterizes the selected compactive effort. A core characterizes the sampled pavement location. Keep that distinction attached to results used in the compaction-window guide and cold-weather paving record.
Calculate Gmb from the core weights
TxDOT's Tex-207-F, January 2020, Part I calculates compacted-mixture bulk specific gravity from dry mass divided by the difference between saturated-surface-dry mass and immersed mass. With a 2,395.0 g dry core, 2,410.0 g saturated-surface-dry mass and 1,410.0 g immersed mass, Gmb = 2,395.0 ÷ (2,410.0 - 1,410.0) = 2.395. These are three measurements of the same specimen, rather than weights from separate cores.
The same Tex-207-F measurements give water absorption of 100 × (2,410.0 - 2,395.0) ÷ (2,410.0 - 1,410.0) = 1.5% by volume. That absorption check screens the bulk-volume method; it is not the calculated air-void result. Retain all three weights with the numerator so a reviewer can trace an unexpected density percentage back to the specimen measurement.
A changed Rice value can move the result
With Gmb = 2.395 and Gmm = 2.520, percent Gmm is 95.0397%, which reports as 95.0%, and air voids report as 5.0%. Replacing the denominator with 2.550 while keeping the same core gives 93.9216%, or 93.9% Gmm and 6.1% air voids. The approximately 1.1-point change comes entirely from the reference value.
Trace the Rice value to the represented production material and the contract's averaging rule before interpreting such a shift as a roller problem. Keep the unrounded ratio through the calculation and round the final report. A spreadsheet that imports the previous lot's Gmm can change the apparent compaction of every core in the new lot.
Match the specimen to the current test method
ASTM D2041/D2041M-26e1 determines theoretical maximum specific gravity on uncompacted asphalt mixture at 25°C (77°F). That loose-mixture test supplies the denominator. ASTM D3203-22 addresses the resulting air-void determination in compacted mixtures; it is a test method, so its designation alone supplies no project acceptance band.
ASTM D2726/D2726M-26 excludes specimens with open or interconnected voids or water absorption above 2.0% by volume from its bulk-specific-gravity method. Thus the 1.5% absorption calculation above answers only the absorption part of that screening. Open or interconnected voids also rule out the method. A specimen's calculated 5.0% air voids is a different property from either test condition.
Distinctions
- VMA
- Voids in mineral aggregate include air plus effective binder volume between aggregate particles. Subtracting VMA from 100 therefore does not give percent Gmm.
- Percent of laboratory density
- A compacted laboratory specimen is a different denominator from theoretical maximum density. The complement of percent laboratory density is not the pavement's air-void percentage.
Frequently asked questions
Why does a density report show more than 100% Gmm?
The reported bulk value exceeds its theoretical reference. Reconcile the mixture and lot identity, the bulk-volume measurement and the maximum-specific-gravity result; the arithmetic is exposing inconsistent inputs.
Does 5% air voids prove the pavement is watertight?
That percentage measures total air space. It does not measure how those voids connect or how fast water travels through them. Permeability requires its own evidence.
Sources checked
- WSDOT Materials Manual M 46-01.48, January 2026: WAQTC TM 13, air-void formula and reporting to 0.1%
- ASTM D2041/D2041M-26e1: maximum specific gravity, current 2026 edition
- ASTM D2726/D2726M-26: bulk specific gravity and the 2.0% absorption exclusion
- ASTM D3203-22: percent air voids in compacted asphalt mixtures
- TxDOT Tex-207-F, January 2020, Part I: three-weight bulk specific gravity and water absorption