Field glossary · measurement
Gmb
The bulk specific gravity reported as Gmb comes from a compacted asphalt specimen's mass and bulk volume: the SSD suspension method calculates Gmb = dry mass / (SSD mass - submerged weight). A value of 2.400 has no units and is not a compaction percentage. The measured volume includes the specimen's air voids; water absorption and open voids determine whether the saturated-surface-dry method is usable.
Bulk specific gravity of the compacted mat or core, the in-place number (AASHTO T166 or T331)
Read the three masses behind an SSD result
WAQTC's 2026 field operating procedure for AASHTO T 166-25, Method A, calculates Gmb as A / (B - C). A is dry mass in air, B is saturated-surface-dry mass in air, and C is submerged weight. The denominator represents the mass of water displaced by the specimen's bulk volume. Preserve these readings with the result; they expose errors hidden by a final three-decimal number.
With A = 2400.0 g, B = 2412.0 g and C = 1412.0 g, the denominator is 1000.0 g and Gmb is 2.400. Water absorption by volume is 100 x (B - A) / (B - C), giving 1.20%. Leaving an extra 5.0 g of surface water raises B to 2417.0 g and lowers the calculated Gmb to 2.388. That change comes entirely from weighing technique. The density acceptance guide explains how the resulting bulk value enters the lot calculation.
When water absorption rules out the SSD method
ASTM D2726/D2726M-26 excludes specimens with open or interconnected voids or water absorption exceeding 2.0% by volume from its SSD method. The absorption percentage concerns water entering the compacted specimen during this test. It is different from aggregate absorption by mass and from the specimen's total air voids.
A low reported absorption does not override an open, interconnected void structure. WAQTC's T 166 procedure directs those specimens to a coated or vacuum-sealed method. AASHTO's 46th edition Materials Book, published in 2026, identifies the current automatic vacuum-sealing method as T 331-26. Retain the method designation when comparing results; changing the volume-measurement method changes the basis of the comparison.
Control the immersion, towel and drying intervals
WAQTC's 2026 T 166 Method A specifies immersion for 4 ±1 minutes in water at 25 ±1°C before the submerged reading. It also limits removal, surface drying and SSD weighing to a combined 15 seconds, with surface drying completed within 5 seconds. Use a damp towel to remove the external film while retaining absorbed water. Over-drying lowers B and pushes calculated Gmb upward; leaving a film pushes it downward, as the mass example shows.
WAQTC includes water that seeps from the specimen during SSD weighing in the recorded mass B. Wiping that seepage off the balance pan removes mass the calculation requires. Distinguish removing the external water film before weighing from losing absorbed water during the reading.
Dry mass deserves its own verification. For oven drying, the same WAQTC procedure uses 52 ±3°C and defines constant mass as no more than 0.05% change over successive two-hour drying intervals. A core that still contains moisture does not supply the dry numerator required by the equation. Record the drying determinations rather than treating elapsed oven time as proof of dryness.
Convert Gmb to a density with matching units
ASTM D2726/D2726M-26 converts specific gravity to density by multiplying by water density at the same temperature. WAQTC's 2026 T 209 procedure uses water density of 997.1 kg/m³ or 62.245 lb/ft³ at 25°C. On that basis, Gmb = 2.400 converts to 2393 kg/m³ or 149.4 lb/ft³. Treating 2.400 as 2400 kg/m³ skips the temperature-specific water factor.
Use the converted density for unit-weight or tonnage calculations and retain the dimensionless Gmb for volumetric ratios. The Superpave mix-design guide applies compacted-specimen properties to lab volumetrics, while the Rice value supplies the separate airless reference.
Distinctions
- Laboratory specimen versus pavement core
- Both yield Gmb. A molded specimen describes compaction under its laboratory preparation conditions; a core describes the material recovered from its recorded pavement location. Keep the specimen origin with the number.
Frequently asked questions
Can two asphalt mixtures be ranked by Gmb alone?
For mix A, Gmb = 2.400 and Gmm = 2.500 give 96.0% Gmm. Mix B, with Gmb = 2.450 and Gmm = 2.600, reaches 94.2% Gmm despite its higher bulk specific gravity. The Rice reference accounts for mixture composition; the larger raw Gmb does not establish better relative compaction.
Sources checked
- WAQTC: AASHTO T 166-25 field operating procedure, October 2025, version 2026, Method A
- ASTM D2726/D2726M-26: active edition, SSD exclusions and conversion to density
- AASHTO Materials Book, 46th edition, 2026: current test designations and revisions
- WAQTC: AASHTO T 209-25 field operating procedure, version 2026, density of water at 25°C