IEEE 400.2: VLF waveforms, test-set capacity, and reporting

IEEE 400.2-2024 addresses field tests that energize shielded power cable systems with AC below 1 Hz. It covers withstand testing and diagnostic measurements, including their application to connected cable accessories. A test plan needs the waveform, frequency, voltage convention, duration, and purpose together. These parameters establish the exposure and instrument capacity; a voltage rating alone does not specify an acceptance test or establish the workmanship of a termination.

Current edition: IEEE 400.2-2024 (2024)
Updated

Official publisher page

Applies to

Testing contractors, commissioning engineers, utilities, and cable owners use this guide when the project testing specification calls for VLF work. IEEE lists the 2024 edition as replacing 2013. Its public scope includes complete cable systems and diagnostics as well as withstand testing. Access to the current document is through IEEE’s official purchase or subscription page. IEEE scope and edition

Key topics

Peak kilovolts and RMS kilovolts are different entries

High Voltage Inc. rates its sinusoidal VLF-34E at 34 kV peak and 24 kV RMS; those are two descriptions of the same output ceiling. Write the unit convention beside the requested voltage and the recorded result. An export labeled only “24 kV” leaves a material ambiguity when compared with another instrument. The waveform also belongs in the record: a sine-wave peak-to-RMS conversion cannot simply be carried over to a cosine-rectangular test. VLF-34E ratings

Cable capacitance determines the available frequency

High Voltage Inc. specifies a VLF-34E load capacity of 0.5 µF at 0.1 Hz and 34 kV peak. At the same voltage, High Voltage Inc. lists 1.0 µF at 0.05 Hz and 5.0 µF at 0.01 Hz. These equipment ratings explain why a voltage-capable test set can still be undersized for a long circuit. Obtain the circuit capacitance before booking the instrument, including the cable sections and accessories that will remain inside the test boundary. Frequency and load limits

Preserve the boundary between fault location and acceptance

A fault-locating trace identifies a distance or event; it does not record a completed VLF exposure. Give the repaired circuit a new test record linked to the fault-location report and splice identification. Mark any cable section omitted from the test and any accessory replacement between tests. A later reviewer needs to know whether an apparent improvement followed insulation repair, a shorter connected length, or a different measurement setup.

How it is used in the field

Take a circuit with measured capacitance of 0.8 µF and a specified test level of 34 kV peak. High Voltage Inc.’s VLF-34E ratings put that load above its 0.1 Hz capability and within its 0.05 Hz capability. The corresponding cycle periods are 10 and 20 seconds. Resolve the frequency and exposure with the test-plan author or supply a larger set before mobilization; instrument load capacity does not select the IEEE test parameters.

Build the submittal around a complete parameter set: referenced edition, installation or maintenance purpose, cable identification, insulation construction, connected length, accessories, waveform, frequency, voltage convention, duration, and any diagnostic channels. Include the instrument model and its load-versus-frequency data. That lets the reviewer approve a test the supplied equipment can actually perform.

Deliver the original instrument export with the circuit drawing and a readable result sheet. Retain interruptions, instrument alarms, actual frequency, and the start and finish of the exposure. A report containing only a pass box conceals whether the programmed test completed. Keep insulation findings separate from the electrical-safety and isolation records.

Frequently asked questions

Can I compare two tan-delta reports taken at different frequencies?

Treat them as different measurement conditions. Preserve frequency, voltage steps, temperature, cable boundary, and insulation type alongside each result. A trending program needs comparable acquisition conditions before a change in the reported value becomes evidence of insulation deterioration.

Does a newer IEEE edition automatically change an existing test contract?

The specification identifies the contractual edition. Submit the proposed revision with the affected parameters and acceptance basis, then retain the approved disposition with the test package. IEEE’s publication date is edition evidence, not a project change order.