InterNational Electrical Testing Association (NETA)
NETA: ATS versus MTS, commissioning and test-scope acceptance
NETA publishes several electrical testing and qualification standards rather than one document called NETA. ATS-2025 addresses acceptance testing, MTS-2023 maintenance testing and ECS-2024 electrical commissioning. ETT-2026 concerns testing-technician certification, while EMW-2026 concerns maintenance-worker qualification. Specify the document matching the work and the required personnel evidence. The association name alone does not define a test scope, an acceptance value or a worker's qualification.
Applies to
Use NETA's document scopes to select the work: ATS addresses suitability for initial energization, MTS addresses continued service, and ECS verifies the commissioned system against the owner's requirements and design basis. Owners and engineers place that selection in the specification; testing firms price the equipment and methods it identifies. A maintenance visit and a new-installation acceptance visit are therefore different scopes even when they involve the same switchgear lineup. NETA's acceptance scope NETA's commissioning purpose
Key topics
ATS-2025 adds identifiable BESS and photovoltaic sections
NETA identifies Section 7.28 for battery energy storage systems and Section 7.29 for solar photovoltaic systems as new ATS-2025 content. A specification copied from an older ATS edition needs to address those additions when the project includes either system. NETA also identifies revised medium-voltage cable acceptance-test values and cable-test reliability guidance. Put the selected test method and equipment scope into the procurement package rather than carrying an unexplained generic NETA allowance. NETA's ATS-2025 changes
Technician certification and maintenance-worker qualification differ
ANSI/NETA ETT-2026 establishes qualification and certification criteria for electrical testing technicians, according to NETA's published scope. ANSI/NETA EMW-2026 establishes maintenance-worker qualification criteria and was developed to support NFPA 70B implementation. Ask for the credential relevant to the assigned role. A worker's qualification, the company's program status and the equipment's completed test report are separate records. None establishes the other two. ETT scope EMW scope
ECS-2024 gives source interfaces their own commissioning scope
NETA's ECS-2024 summary identifies new source-specific sections for photovoltaics, UPS equipment and automatic transfer switches. Use that scope to allocate responsibility where a source, controller and distribution system interact. Identify who provides the accepted sequence and who records the functional response. An equipment-level report needs to connect to the system performance requirement it supports; the commissioning package should make that relationship visible. NETA's electrical-commissioning scope
A maintenance specification needs its edition and errata
NETA's MTS-2023 scope assesses equipment for continued service, and its publication page supplies a separate errata download. Name both the edition and applicable corrections in the service specification. Preserve the test conditions alongside baseline measurements: a result obtained by a different method or under different conditions is not automatically a comparable trend point. Keep initial-acceptance evidence available without treating its original criterion as the maintenance decision for every later visit. MTS scope and errata
How it is used in the field
Compare proposals with a schedule of equipment tags, NETA document and edition, applicable equipment sections, tests, acceptance references and deliverables. Identify outages, witness attendance and repeat testing separately. For each numeric limit, require the standard or manufacturer reference used by the testing firm; a quotation promising NETA testing without the equipment scope cannot establish what the price includes.
A scope contains 12 tagged breakers. The turnover package contains 11 unique breaker reports and a duplicate of one report. There are 12 files but one breaker has no test evidence. Return the package with the missing tag identified, then reconcile the corrected reports against the scope. This Anvilfield example tests coverage; the technical disposition of each breaker still depends on its recorded measurements and applicable criteria.
Frequently asked questions
Does ATS mean an automatic transfer switch in a NETA citation?
In ANSI/NETA ATS, the letters identify Acceptance Testing Specifications. A drawing can use the same letters for an automatic transfer switch. Spell out the document title in the testing specification and identify transfer-switch equipment by its asset tag.
Is NETA accreditation the same thing as a technician's certification?
NETA's ETT description treats company accreditation and individual technician certification separately. An accredited-company logo on a proposal does not identify the technician assigned to a particular test. State the company requirement, assigned role and individual credential required by the contract, then retain evidence for each.