IEEE 1184: selecting batteries for UPS duty
IEEE 1184-2022 connects UPS load requirements with the battery performance data needed to select a string. The active edition adds lithium-ion coverage and addresses the battery, charger, and converter relationship; UPS component design and DC-output rectifier backup are outside its scope. A usable selection schedule states real power, efficiency boundary, discharge duration, cell endpoint, temperature, and the age at which the promised runtime must be delivered.
Applies to
Specifying engineers, UPS vendors, battery suppliers, commissioning authorities, and owners use IEEE 1184 at the interface between a UPS procurement and its battery package. The selection record should identify load duty, battery-side power, discharge duration, DC operating window, environmental basis, and recharge requirement.
Use the energy-storage types guide for the chemistry comparison, then issue the same electrical duty to each battery supplier. A bid stating only UPS kVA and cabinet count leaves the supplier to choose the power factor, discharge endpoint, and battery-age basis, making the proposals difficult to compare.
Key topics
Convert AC load into battery-terminal power
ABB's UPS Battery Handbook calculates battery output demand from apparent load power, power factor, and inverter efficiency. When the load is already in real kilowatts, divide by efficiency without multiplying by power factor again. Identify where that efficiency is measured: an inverter-input result still needs the battery-cable losses and separately supplied DC auxiliaries added to describe the full demand at the battery terminals. NorthStar's UPS application manual likewise adds a separate cable-loss allowance to the load and efficiency calculation.
An ampere-hour rating has a discharge-time basis
ABB notes that nominal lead-battery capacity commonly uses a ten-hour discharge basis and nickel-cadmium a five-hour basis. Short UPS duty draws a different usable capacity from those nameplate ampere-hours. Request the manufacturer's constant-power or constant-current performance data for the selected duration, temperature, and cutoff voltage. Equal ampere-hour labels alone do not establish equal short-duration UPS performance.
Reconcile the cell endpoint with the UPS DC window
ABB's handbook identifies cutoff voltage as a battery-sizing input and discusses discharge endpoints such as 1.65 and 1.70 V per lead-acid cell. A string of 240 cells at 1.65 V per cell has a 396 V terminal endpoint. The UPS low-voltage limit, battery-cable drop, and selected discharge data must describe a compatible endpoint, rather than three independently chosen numbers.
The 2022 revision includes lithium UPS batteries
IEEE's Energy Storage and Stationary Battery Committee reported that the reissued IEEE 1184 added lithium-ion UPS coverage, including sizing. This expands the guide beyond an exclusively lead-acid selection basis. It does not expand the stated scope into design requirements for the UPS converter itself or make a UPS battery selection report an approval of a separate grid-service storage installation.
How it is used in the field
A 1,000 kVA load at 0.90 power factor draws 900 kW. At 96 percent inverter efficiency, the inverter DC input is 900 ÷ 0.96 = 937.5 kW, or 156.25 kWh over ten minutes. Add battery-cable losses and DC auxiliaries at the battery-terminal boundary. Submit that power and duration with the manufacturer's discharge endpoint; multiplying kW by time alone does not select an ampere-hour rating.
Issue one duty schedule to every bidder. Require each response to identify its battery model, cell count, parallel strings, performance-data revision, selected endpoint, temperature basis, and the point at which autonomy is guaranteed. A proposal guaranteeing runtime at new-battery condition answers a different procurement question from one guaranteeing it at the contract's end-of-life condition.
At turnover, connect that selection schedule to the tested installation. A changed cell count, different battery model, or altered UPS low-voltage setting changes the selection basis even when the cabinets look identical. The UPS battery testing guide covers the discharge work; retaining the selected rating curve makes the acceptance comparison reproducible.
Edition history
IEEE lists IEEE 1184-2022 as active, superseding IEEE 1184-2006. Board approval was March 24, 2022 and publication was May 16, 2022. Identify the 2022 guide in a new battery selection basis rather than carrying forward an undated 'IEEE UPS battery' reference.
Adoption
IEEE 1184 is an application guide used in procurement and engineering specifications. Its scope sets what the selection document addresses. Installation approvals, equipment certification, and the acceptance obligations in the supply contract remain identifiable deliverables alongside that selection document.
Battery suppliers comparing agency procurement scopes use PorchRocket Bid Control for earlier awards, including who won, before preparing a response to the next UPS renewal.
Frequently asked questions
Can UPS kVA be used directly as battery kilowatts?
Convert apparent power to real power using load power factor, then account for inverter efficiency. When real kilowatts are already known, apply the efficiency conversion without applying power factor a second time.
Does a ten-minute energy calculation select the battery model?
It establishes energy over the stated duration at the stated measurement point. Specify the battery-terminal demand after cable losses and DC auxiliaries, then use the manufacturer's performance data at the chosen endpoint and temperature, with the contract's aging and recharge basis.
Sources checked
- IEEE 1184-2022: active edition, UPS battery scope, and excluded DC rectifier applications
- ABB UPS Battery Handbook: battery capacity, sizing equation, performance curves, and cutoff voltage
- IEEE PES ESSB 2022 annual report: lithium-ion coverage added to IEEE 1184
- NorthStar/EnerSys UPS Battery Application Manual, section 10.15: load conversion and separate cable-loss allowance (manufacturer manual hosted by Helios)