ASHRAE Guideline 21 and IEEE 1635: battery ventilation design inputs

IEEE 1635-2022 / ASHRAE Guideline 21-2022 organizes battery-room design around the installed chemistry and its operating modes. The joint guide covers stationary lead-acid, nickel-cadmium, and lithium-ion systems, including identified failure modes. Electrical and HVAC designers need cell count, series and parallel arrangement, charger behavior, and manufacturer heat and gas data for each case. A normal float gas rate supports that one operating condition; it does not establish recharge or failure-case ventilation duty.

Current edition: IEEE Std 1635-2022 / ASHRAE Guideline 21-2022 (2022)
Updated

Official publisher page

Applies to

Electrical designers define the installed battery and charger arrangement; mechanical designers translate its normal and abnormal operating states into environmental requirements. Owners and commissioning teams need those assumptions preserved when strings, chargers, or cabinet arrangements change. The published ASHRAE scope is stationary batteries under expected use, including identified failure modes.

The battery-room ventilation guide covers the room's operating safeguards. This entry concentrates on the battery-specific input data needed to make its design calculations traceable.

Key topics

A battery description needs cells as well as blocks

Manufacturer gas and charging information can use different denominators. EnerSys's June 2022 PowerSafe SBS manual lists six cells per SBS 40 block and a float-charge hydrogen evolution of 1.45 mL/h per block at 2.27 volts per cell. Enter the model and the denominator with the value. Multiplying a per-block gas figure by cell count would overstate that source term by six for this product. EnerSys also specifies a maximum hydrogen accumulation of 1 percent by volume for the SBS battery compartment or room; retain that product limit with the gas source data.

Float data describes one charging condition

The same EnerSys manual gives an acceptable float range of 2.27 to 2.29 volts per cell at 20 C and 2.25 to 2.27 volts per cell at 25 C. Its hydrogen table identifies a specific float voltage. Keep recharge and other design operating states in separate calculation rows instead of carrying that float figure into every case. The charger arrangement and battery manufacturer's data determine which state the mechanical design must accommodate.

Cabinet placement changes the ventilation boundary

EnerSys's DataSafe HX+ manual explicitly prohibits sealed cabinets and calls for adequate ventilation when the batteries are enclosed. A room exhaust fan therefore does not by itself establish airflow through a battery cabinet. Show the cabinet openings, air path, discharge location, and room system on the same design sketch. Identify whether the gas source is dispersed into the room or removed through a dedicated path.

Identified failure modes belong in the design handoff

ASHRAE's published Guideline 21-2022 scope includes identified failure modes alongside the expected operating modes of stationary batteries. Request the installed system's abnormal-state design information as part of the electrical-to-mechanical handoff. Describe what changes at the battery or charger, the associated heat or gas source, and the required ventilation response. An operating-state schedule makes that review explicit instead of leaving the HVAC designer to infer every condition from normal float data.

How it is used in the field

Forty SBS 40 blocks contain 240 cells and produce 58 mL/h of hydrogen at EnerSys's stated 2.27 V per cell float condition. All 40 blocks connected in one series string have a float voltage of 544.8 V. Two parallel strings of 20 blocks each have a float voltage of 272.4 V and the same combined 58 mL/h source at that condition. Gas generation adds across both strings; string voltage adds only across the cells in series. Mark that topology on the electrical-to-mechanical handoff.

The design submission should connect each battery operating mode to its gas and heat assumptions, fan operating state, and monitoring response. Include the temperature represented by the charging data. This makes a later charger or battery substitution a defined engineering change rather than a replacement with an unchanged room worksheet.

During acceptance, reconcile the installed block count and cabinet arrangement with the mechanical calculation. Record measured air delivery at the boundary assumed by that calculation. Retain battery model, charger configuration, and operating-state assumptions with the accepted ventilation evidence.

Edition history

ASHRAE lists Guideline 21-2022, and IEEE's publisher record identifies IEEE/ASHRAE 1635-2022 as approved September 21, 2022 and published November 30, 2022. Cite both designations on interdisciplinary submissions so electrical and HVAC reviewers retrieve the same guide. The IEEE record also identifies lithium-ion as part of the 2022 scope; older descriptions omitting that chemistry do not describe the complete current publication.

Adoption

This guide supplies engineering practice for stationary battery environments. The project's electrical, mechanical, and fire requirements establish the installation's enforceable provisions. An engineering calculation should identify those provisions separately from manufacturer operating data and the joint guide's design method.

Frequently asked questions

Are IEEE 1635 and ASHRAE Guideline 21 different documents?

The current 2022 publication is jointly identified by both numbers. Use the full joint designation when exchanging battery-room design information between electrical and mechanical disciplines.

Does a float hydrogen rate cover a recharge condition?

A float table establishes its stated operating condition. Keep recharge and abnormal states separately identified and use the corresponding battery and charger data in the environmental design.