Field glossary · material
Ballast
Roof ballast restrains a roofing assembly by distributed weight. Carlisle's July 2026 Sure-Seal guide starts rounded gravel and interlocking concrete pavers at 10 lb/ft², while individual concrete pavers require at least 18 lb/ft². The specified wind protection still controls the distribution. A roof-wide weight average cannot establish adequate coverage in each zone, and solar-rack blocks do not automatically satisfy the roofing ballast schedule.
Stone or pavers laid over a loose membrane to hold it with weight, designed per ANSI/SPRI RP-4
Stone and pavers carry different minimum weights
Carlisle's July 2026 Sure-Seal ballasted-system guide specifies at least 10 lb/ft² for rounded water-worn gravel or interlocking concrete pavers, subject to the required wind protection. The same Carlisle guide requires individual concrete pavers to weigh at least 18 lb/ft². Substituting individual paving slabs for an interlocking product therefore changes the manufacturer's minimum weight criterion.
Carlisle also requires complete ballast coverage of the loose-laid membrane in that system. An exposed strip beside a walkway is not explained away by excess stone elsewhere. Identify the approved aggregate or paver product on the placement drawing, and retain the zone-specific quantities with the delivery records.
Convert the placement plan into delivery quantities
Anvilfield's ballast takeoff for 20,000 ft² at Carlisle's 10 lb/ft² minimum is 200,000 lb, or 100 short tons, before handling losses. Delivery tickets totaling 90 short tons leave only 9 lb/ft² available on average. Assign each ticket to a placement zone; the roof-wide total does not locate the missing material.
Divide the roof into the actual placement zones before reconciling quantities. Use the net area receiving each material, deduct areas occupied by different assemblies, and keep replacement stone separate from retained stone. The single-ply attachment guide explains why assembly restraint must match the wind demand.
| Takeoff item | Calculation | Quantity |
|---|---|---|
| Scheduled ballast | 20,000 ft² × 10 lb/ft² | 200,000 lb = 100 short tons |
| Delivered ballast | 90 short tons × 2,000 lb | 180,000 lb |
| Quantity shortfall | 200,000 - 180,000 lb | 20,000 lb = 10 short tons |
A stockpile is a separate loading condition
Staging concentrates the same material differently: 4,000 lb spread over 400 ft² produces 10 lb/ft², but a temporary pile over 40 ft² produces 100 lb/ft². Locate unloading and staging areas on the load plan independently of the finished ballast zones.
Carlisle's system description also requires separate membrane securement at perimeters, curbs, penetrations, and specified angle changes. Ballast quantity cannot replace those connections. During a repair, document the exposed membrane and restored distribution so a small opening does not become a permanent unballasted patch.
Distinctions
- Aggregate surfacing
- Aggregate embedded in a bituminous roof surface protects that surface. Loose ballast restrains an assembly and has its own aggregate specification.
- Solar ballast
- Solar-rack blocks resist forces on the array through its racking system. Verify the roofing ballast distribution independently of the array blocks.
Frequently asked questions
Can total truck weight prove the roof is correctly ballasted?
It proves the delivered quantity, subject to the ticket basis. Installed compliance also requires the specified material, distribution, coverage, and attachment details.
Are short tons and metric tonnes interchangeable?
No. The calculation here uses a short ton of 2,000 lb. State the delivery unit before reconciling tickets with a roof schedule in pounds per square foot.
Sources checked
Also defined as
- Concrete weight that holds a non-penetrating low-slope array down against wind uplift