Bond beam

A bond beam is a reinforced horizontal member incorporated into a masonry wall, usually made by filling a channel course with grout around longitudinal bars. The channel must provide a continuous load path while admitting grout around intersecting steel. Its height on the elevation, continuity at corners, and treatment at movement joints identify its structural job more reliably than the block shape alone.

A horizontal grouted, reinforced course built in channel units, continuous through the wall

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Choose units that preserve the grout passage

CMHA TEK 03-02A describes reduced-web and knockout-web bond-beam units as ways to accommodate horizontal reinforcement. A solid-bottom channel retains grout in that course; an open-bottom unit needs an approved grout stop where the wall below is not being filled. Keep openings available at vertically reinforced cells so the horizontal and vertical grouted regions connect as detailed.

CMHA TEK 03-02A specifically rejects roofing felt and other materials that interrupt the mortar-to-unit bond as grout stops. Approved screening retains the grout without substituting a slip plane for the bed joint. Inspect the installed stop from the course above before bars conceal the intersection.

Carry the right reinforcement through the joint

A bond beam serving as a diaphragm collector has a different continuity requirement from a course used only for crack control. Mark that function on the elevation before deciding which bars cross a masonry control joint. An uninterrupted bar drawn through a deliberate separation is a design decision, not a default field shortcut.

CMHA's Annotated Design and Construction Details directs builders to fully mortar the cross webs beside a control joint where horizontal bond-beam reinforcement is discontinued, preventing grout from bridging the separation. This detail preserves the intended movement while retaining grout in each adjoining panel.

Measure the channel before releasing the grout

CMHA TEK 03-02A gives an 8 to 11 inch placement slump for conventional masonry grout to reduce bridging in restricted spaces. That is a masonry-grout value, not a target for ordinary slab concrete. At a splice or corner, the remaining passage around the steel matters more than the apparent width of the empty channel.

Before grouting a CMU wall, mark each channel closure, intersecting bar, end dam and cut unit on the course elevation. That map distinguishes intentional stops from accidental obstructions and records where the grout must pass between courses.

Estimate the horizontal grout channel separately from the vertical cells. Multiply its measured clear cross-sectional area by the filled length, subtract displaced steel where the takeoff requires it, and add intersecting-cell volumes without counting the intersection twice. Nominal block width does not give the channel's grout volume.

Distinctions

Lintel
Spans an opening. A bond beam can also act as a lintel where its reinforcement, bearing and support are designed for that span.
Pool bond beam
A thickened reinforced-concrete rim of a pool shell. Masonry channel-unit and grout-stop details do not describe that assembly.

Field example

An 80 foot run on a 16 inch horizontal module has 60 unit positions before corner and closure adjustments. A measured 6 by 6 inch grout channel along that run contains 20 cubic feet, or about 0.74 cubic yard, before steel displacement. Add the specified vertical-cell fill separately and keep its connections open at the bond-beam course.

Frequently asked questions

Can the bond-beam block name establish its capacity?

No. The member depends on its reinforced section, grout, development, support and continuity. The unit name describes the shape delivered to the wall.

Sources checked

Also defined as

  • A horizontal course of reinforced, grouted block running as a continuous band

Where this shows up

Next step: Find masonry packages

Back to the full field glossary