CL
Calculate a measured duct leakage class, CL, as 100Q / (A × P^0.65), using leakage Q in CFM on the required air-density basis, duct skin area A in ft² and pressure magnitude P in inches of water. Under TSI's SMACNA equation, 90 CFM from 1,800 ft² at 2 in. wg gives CL 3.19. Compare that coefficient with the specified maximum, rather than comparing unnormalized CFM or percent fan flow.
Leakage class, the allowable leakage in cfm per 100 sq ft at 1 in. w.g.
Calculate CL from a measured leakage result
The TSI PANDA Light manual expresses the U.S. leakage relationship as F = CL x P^0.65, where F is CFM per 100 ft² and P is pressure in inches of water. Inverting it gives measured CL = 100Q / (A x P^0.65), with total leakage Q in CFM and tested duct surface A in ft².
A section with 1,800 ft² of surface leaks 90 CFM at 2.0 in. wg. Its leakage factor is 100 x 90 / 1,800 = 5.0 CFM per 100 ft². Dividing by 2^0.65 gives a measured CL of approximately 3.19. Against a specified CL 4 maximum, that measured result passes.
Keep the calculation's full precision until the result is compared. Calling the first intermediate result CL 5 would ignore the pressure normalization and incorrectly fail this section. Attach the boundary sketch from the duct leakage test so the reported area can be traced to the measured section.
Carry the pressure and airflow units into the formula
TSI specifies inches of water for P in its SMACNA equation. NIST's conventional conversion is approximately 249.089 Pa per inch of water; a 500 Pa test therefore enters the equation as about 2.007, not 500. An instrument accepting pascals handles the conversion internally only when the correct test standard and unit settings are selected.
Use the airflow basis required by the test method and project. For acceptance in standard CFM, TSI's SMACNA summary gives SCFM = ACFM × density / 0.075, with density in lb/ft³. A meter reading 90 ACFM at 0.060 lb/ft³ therefore supplies 72 SCFM and gives CL 2.55 for the section above. Record the test-air density or its temperature and absolute pressure; the class equation itself does not convert actual flow to standard flow.
For a suction test, record the negative test direction and use the pressure-difference magnitude in the exponent. The direction still matters to the assembly and test setup. A numerical class computed from positive pressure does not establish the result that a separately required negative-pressure test would produce.
Name the reference and the instrument range
SMACNA identifies its HVAC Air Duct Leakage Test Manual as ANSI/SMACNA 016-2012; the second edition remains the publisher's listed edition for this reference. Put that designation alongside the specified class instead of treating CL as a self-contained test specification.
TSI lists the PAN341 low-flow nozzle range as 2 to 27.5 CFM and its flow-grid range as 21 to 424 CFM. The 90-CFM result above belongs in the flow-grid range. Choosing a class does not extend the calibrated range of the nozzle or meter used to establish it.
The calculation record needs the measured airflow, duct surface, held pressure, pressure direction, instrument configuration and required maximum. That lets a reviewer reproduce the coefficient without reconstructing the installation from a pass stamp.
Distinctions
- Leakage factor F
- The leakage rate per 100 ft² at the actual test pressure; it equals CL numerically only at 1 in. wg.
Frequently asked questions
Is CL a percentage of fan airflow?
No. Fan airflow does not appear in the CL equation. A percent-leakage specification needs its own airflow basis before it can be compared with a class.
Does a lower measured CL indicate tighter duct?
Yes, for results computed with the same convention and a properly defined test boundary. Check the area and pressure inputs before comparing coefficients.