Field glossary · measurement
Leakage class (CL)
Turn a specified leakage class into a section allowance using the measured duct skin area and required test pressure. With TSI's SMACNA relationship, a 600-ft² section at CL 4 and 2 in. wg permits about 37.66 CFM on the applicable air-density basis. Doubling the entered area doubles the allowance without improving the duct. Temporary seals, instrument range and flow correction must be documented to make that acceptance result reproducible.
Allowable leakage in cfm per 100 sq ft at 1 in. w.g.; a lower number is a tighter duct
Count the duct skin inside the test boundary
TSI's PANDA Light PAN341 procedure requires calculation of the surface area of the selected duct section before testing. That area is the duct skin, not its floor footprint or airflow cross-section. Break changing sizes into separate pieces and retain the dimensions behind the total.
A straight 24-by-12-inch rectangular duct has a perimeter of 6 feet. Over 100 feet of length, its four longitudinal surfaces total 600 ft². Its 2-ft² cross-section describes the opening air flows through and has no place in the leakage-area denominator. Account for transitions and other included surfaces separately.
For that 600-ft² section at CL 4 and 2 in. wg, the TSI manual's SMACNA relationship gives an allowance of approximately 37.66 CFM. Entering 1,200 ft² by mistake doubles the allowance to 75.32 CFM without changing the physical duct. The CL calculation entry works through the pressure-normalized coefficient.
Separate duct leakage from the temporary test assembly
TSI instructs the operator to temporarily seal every opening except the connection to the leakage tester. A loose blank, access cover or test adapter contributes to the makeup airflow measured during the test. Mark these temporary boundaries on the test sketch so a retest uses the same section.
The TSI procedure also calls for airtight connections at the flexible test tube and adapters. Repair a leaking temporary connection before attributing its airflow to permanent duct construction. Conversely, an unintended open connection to additional duct can enlarge the actual tested section beyond the area written on the report.
Use the section identifier from the duct leakage test plan on the as-built sketch, photographs and instrument export. List any terminal equipment left inside the boundary so the result can be reproduced.
Keep instrument accuracy visible near the limit
Record whether the tester reports actual or standard CFM and the basis required for acceptance. For a standard-air comparison, TSI's SMACNA summary converts a 37-ACFM reading at 0.060 lb/ft³ to 29.6 SCFM using SCFM = ACFM × density / 0.075. Retain the test-air density or its temperature and absolute pressure with the report. An instrument's accuracy specification does not correct a mismatched flow basis.
TSI specifies PAN341 airflow accuracy as ±2.5% of reading or ±0.02 CFM, whichever is greater. At a 37-CFM reading on the allowance's basis, the stated flow-accuracy contribution is ±0.925 CFM. That is larger than the 0.66-CFM difference between the reading and the 37.66-CFM allowance above.
The measured result is below the allowance, but its small margin should not be described as proof of a large tightness reserve. Apply the project's stated acceptance rule and retain instrument accuracy, pressure and area information. The flow specification alone is not the uncertainty of the complete test.
TSI requires both the PVM610 and TA465-P meters to be zeroed before entering the leakage-test application. SMACNA's published reference for this work is the second-edition HVAC Air Duct Leakage Test Manual, ANSI/SMACNA 016-2012. Name the test reference and instrument configuration with the acceptance result.
Distinctions
- Seal class
- A construction requirement identifying which joints and seams are sealed. A leakage test measures the resulting tightness of the defined assembly.
Frequently asked questions
Does a passing section establish the whole system leakage?
Only the defined section was measured. Report the tested extent and apply the project's sampling and acceptance requirements to the remaining system.
Can I compare two sections by leaked CFM alone?
Their areas and test pressures must also be considered. A larger section can leak more total CFM while achieving the same normalized class.
Sources checked
Also defined as
- Allowable leakage in cfm per 100 sq ft at 1 in w.g., used in F = CL x P^0.65