Field glossary · business
Labor unit
Labor units express installation effort per stated quantity, so an estimator must carry both the hours and the denominator: per item, foot, hundred feet, or defined assembly. They measure person-hours rather than elapsed crew time. A useful labor record also identifies its included operations, estimating method, source revision, and conditions; mixing those bases changes an estimate even when the takeoff quantity is correct.
The labor hours to install one item, from SMACNA, MCAA, or your own job-cost history
Check the denominator before importing hours
MCAA's WebLEM brochure expresses a labor unit as person-hours for a material quantity, an individual component, or a particular task. Those bases are different database fields. A quantity measured in feet cannot multiply a rate per hundred feet until the quantity is divided by 100.
For a 1,280 ft takeoff entered at 3.75 person-hours per 100 ft, the extension is 48 person-hours: 1,280 / 100 x 3.75. The 3.75 is the estimating input in this calculation, not a published allowance for a specified pipe or raceway. Importing it as hours per foot produces 4,800 hours. Preserve the quantity basis, material size, and joining method when transferring an assembly into the electrical estimating recap.
Component labor and activity labor include different work
MCAA's WebLEM Component Method includes receiving, handling, joining, installation, and normal pressure testing within the component's labor allowance. MCAA includes one joint per standard length of pipe in that method, including the associated cutting, beveling, and threading or welding. Adding another allowance for that same joint duplicates labor. Its Work Activity Method separates these operations into individual labor units.
MCAA states that WebLEM units are developed for field assembly; shop-fabrication savings require a productivity adjustment. Selecting the Work Activity Method separates the tasks but does not itself establish faster shop production. Preserve the shop adjustment separately from the publisher's base hours.
MCAA specifically excludes hanger installation from its pipe installation labor units. Carry the hanger work separately. An assembly should identify whether its support labor was added by the estimator or came from another assembly, so a later takeoff revision does not add it again. Keep the same boundary when comparing pipe installation hours with the plumbing takeoff.
Translate person-hours into a crew schedule
The 48-person-hour allowance above represents 16 elapsed working hours for three people working together, or two eight-hour shifts. A four-person crew would consume the same allowance in 12 elapsed working hours at the same output per person. Crew size changes the scheduled duration; it does not change the estimate's unit of effort.
Keep a crew-hour field separate from a person-hour field. A three-person crew working eight hours records 24 person-hours, and an hourly wage or employment-cost rate must multiply those 24 hours. The HVAC estimating guide carries that labor cost alongside equipment and subcontract quotes.
Save the labor record's identity when data changes
MCAA's WebLEM FAQ explains that unique identifiers connect individual labor data points to estimating vendors' databases when updates occur. Save that identifier, the database revision or download date, the component or activity method, and any company adjustment with the estimate.
An archived bid should retain its original labor basis after a software update. Otherwise, reopening the estimate can conceal whether a changed total came from revised quantities, new publisher data, or a deliberate adjustment for the work. A dated export makes that difference recoverable.
Distinctions
- Production rate
- Hours per foot and feet per person-hour are reciprocals. The 3.75 hours per 100 ft allowance equals 0.0375 hours per foot, or about 26.67 ft per person-hour. Label the direction before entering a rate.
Frequently asked questions
Do MCAA labor units include purge or X-ray-quality welding?
MCAA's public WebLEM brochure excludes purge and labor for X-ray-quality welding from its base allowances. Identify the welding requirement in the takeoff and carry the corresponding labor separately from ordinary joint labor.
Sources checked
Also defined as
- Electrical: The labor hours to install one item under normal conditions, from the NECA MLU or your own data
- Plumbing: Installed hours assigned to a fixture, a linear foot of pipe, or a fitting