ANVILFIELD Try FieldOS

Field glossary · process

TAB

TAB, testing, adjusting and balancing, establishes documented HVAC air and water flows under specified operating conditions. Its scope includes taking the original readings, making adjustments and producing the report; acceptance verification remeasures selected reported results. Under UFGS 23 05 93, a 25-percent acceptance sample is rounded up and has a three-device minimum where at least three exist. That sample does not reduce the original TAB measurement scope.

Testing, adjusting, and balancing: measuring an air system, adjusting it, and setting it to design, then reporting it

Used across 2 Anvilfield field guides, most in HVAC.
Updated

Make every reading traceable to a device and a condition

NEBB's public report-compliance article for its 2019 9th edition describes an instrument list containing type, manufacturer, model, serial number and calibration date. Each data form identifies the person reporting the information and the date the data was collected. These details are traceability examples from the named older edition; the project specification and applicable certification requirements establish the reporting basis for the current job.

Extend that traceability to the operating condition. A VAV box with design minimum and maximum flows of 150 and 500 CFM, measured at 152 and 498 CFM, has deviations of approximately +1.3 and -0.4 percent. Its worksheet should identify the command used for each reading and connect both readings to the same terminal tag and measuring instrument. Otherwise, two good-looking numbers do not show that both operating points were measured.

The HVAC estimating guide carries TAB as a defined scope. Specify report preparation and return verification along with the initial measurements so the priced deliverable includes reproducible evidence.

Count terminal units separately from terminal devices

UFGS 23 05 93, May 2025, specifies field verification of all Category 1 air-system equipment and 25 percent of its associated air terminal devices, with sample quantities rounded up and a minimum of three where at least three exist. This is the federal guide specification's verification scheme; the issued project section establishes its use on the job.

Eight directly associated terminal devices produce a calculated sample of two, increased to three by that minimum. Category 3 works differently: UFGS selects 25 percent of air terminal units such as VAV boxes, then verifies every air terminal device associated with each selected unit. For eight VAV boxes serving four diffusers apiece, the sample is three boxes and all 12 diffusers attached to them.

These are acceptance rechecks of reported data. A quote that covers only the sample omits original TAB work. UFGS 23 05 93 also expands verification after a failure: the corrected point, an additional selection for each failure and new selections under the category's sampling rule require return labor. Carry that potential scope in the estimate.

Retain the selected sample, repeated readings and correction history with the approved report. The same evidence matters on the water side, where the hydronic balancing guide ties circuit flows to the pump and valve settings.

Name the TAB edition and the measurement basis

NEBB released the 10th edition of its Procedural Standard for Testing, Adjusting and Balancing of Environmental Systems on September 1, 2026. Its release notice identifies reporting standards, instrumentation guidelines and certification requirements among the covered topics. A specification copied from a previous job needs an explicit edition review.

ANSI/ASHRAE Standard 111-2024 is the current measurement, testing, adjusting and balancing standard, with a published errata sheet dated September 5, 2025. Identify that edition when it forms the measurement basis. The air-balancing guide covers the field sequence; the named documents establish the requirements against which the submitted work is reviewed.

Distinctions

Certification and project acceptance
NEBB's public guidance distinguishes certification of firms, individuals and reports from certification of an entire project. Identify who certifies the TAB submission and who accepts the installed work instead of using the phrase certified project as a substitute for both.

Board-meeting and capital-plan signals in PorchRocket Bid Control let balancing firms track school and municipal HVAC upgrades before the bid package is published.

Frequently asked questions

Does a tablet identifier cover all the wireless probes on a TAB job?

The instrument record should identify the measuring devices that produced the readings. Keep probe serial numbers and calibration dates associated with the exported data; the display tablet's asset number alone does not identify those sensors.

Sources checked

Also defined as

  • Test and balance of the air and water systems to design quantities

Where this shows up

Related guides

Next step: Map rooftop TAB accounts

Back to the full field glossary