O and P
O and P means overhead and profit, with each allowance calculated on an identified cost base. A proposal marked 10 and 10 adds 20% when both percentages use direct cost, but 21% when profit also applies to overhead. State the overhead pool, each percentage's denominator, and the permitted order of calculation so an estimator can reproduce the price from the cost recap.
Overhead and profit, the markup added on top of direct job cost
Which costs belong in the overhead pool?
For federal contract costing, FAR 31.203 requires indirect costs to be grouped and allocated using a base that reflects the benefits received by the work. A percentage without its base is incomplete: direct labor cost, total direct cost, and labor hours spread the same overhead pool differently.
FAR 31.203 also prohibits indirect allocation of costs whose counterparts, incurred for the same purpose in like circumstances, are treated as direct costs. Apply that discipline when moving between estimate formats. A project trailer charged to the job must not also remain in the overhead pool used to burden that job. The HVAC estimating guide establishes the bid buckets; the pool definition explains what each bucket actually contains.
Why lower work volume raises the required recovery rate
An annual overhead budget of $300,000 allocated over $2,000,000 of direct cost requires a 15% recovery rate. If the same overhead is spread over $1,500,000, the required rate becomes 20%. Continuing to apply 15% recovers $225,000 and leaves $75,000 unrecovered.
That shortfall appears even when every project meets its direct-cost estimate. It is a volume-and-allocation problem, so changing installation labor units will not fix it. FAR 31.203(e) identifies significant business changes as circumstances that can require revising an allocation method; it does not mandate a new method after every volume change. Reforecasting the rate on an unchanged base is different from changing the allocation method.
Does 10 and 10 add 20% or 21%?
On $100,000 of direct cost with $10,000 overhead, the order of calculation determines both the price and the remaining profit. The following recap keeps that overhead amount fixed so the three methods can be compared.
To obtain a 10% profit margin after overhead, divide the $110,000 total cost by 0.90. Applying a 10% markup to that same cost produces a 9.09% margin instead. Name each cost base on the recap and retain the contract's allowed percentages with the plumbing bid proposal.
| Calculation | Price | Profit after $10,000 overhead | Profit as share of sales |
|---|---|---|---|
| 10% overhead and 10% profit, each on $100,000 | $120,000.00 | $10,000.00 | 8.33% |
| 10% overhead, then 10% profit on $110,000 | $121,000.00 | $11,000.00 | 9.09% |
| $110,000 total cost divided by 0.90 | $122,222.22 | $12,222.22 | 10.00% |
Distinctions
- Contingency
- A $2,000 contingency for uncertain demolition quantities should remain identifiable beside overhead and profit. When the quantities become known, the estimator can revise that allowance without silently changing the office-cost recovery or profit calculation.
Frequently asked questions
Can I add overhead after pricing labor at a loaded rate?
First identify what the labor rate contains. An employment-only rate leaves company overhead outside it. A rate already carrying an overhead allocation has recovered that portion; applying the same pool again duplicates it.
Does an approved profit allowance establish the profit I will earn?
FAR 15.404-4 distinguishes the government's negotiated profit objective from the contractor's realized income: productivity, unallowable expenses, and contract type affect the result. Keep the accepted change-order calculation beside actual job costs. The approved allowance documents recovery under the contract, while the cost record establishes the return earned.