Standing pressure test
A standing pressure test needs an isolated volume, a model-specific hold criterion and temperature-matched readings. Nitrogen at 200.0 psig and 80°F falls to about 192.0 psig at 60°F without losing gas, using a 14.7 psi atmospheric reference. Calculate that thermal change before assigning a loss to leakage. Document the equipment, gas, pressure limit, time interval and instrument resolution so another technician can reproduce the acceptance decision.
Holding nitrogen pressure and watching the gauge over time, with temperature correction, to prove tightness
Use the test pressure and hold time for the model
Carrier's 24SCA5 installation instructions specify about 200 psi nitrogen for the pressure-proof check and require the holding charge not to decrease during a one-hour observation. Those values belong to that instruction and model. A pressure remembered from another refrigerant system is not the basis for accepting this test.
The same Carrier instruction specifies a test-gauge resolution no greater than 5% of the holding charge. At 200 psi, that stated maximum increment is 10 psi. It is an instrument-resolution provision, not permission for a 10 psi leak or an instruction to ignore a smaller repeatable loss. Write down the instrument's actual range and resolution, not merely the fact that a gauge was attached.
Use the specified gas and a controlled pressure source
Carrier's 24SCA5 instructions prohibit air or oxygen-containing gas for refrigerant leak testing. Use the specified nitrogen charge with a pressure-regulated source, then isolate that source from the test volume before the timed hold. The 200 psi example is a model instruction, not a rating for every connected valve, hose or refrigeration component.
Correct pressure with absolute temperature
NASA's ideal-gas equation uses pV = nRT with absolute temperature; for a fixed gas mass in a fixed volume, absolute pressure divided by absolute temperature stays constant. In US field units, convert Fahrenheit to Rankine by adding 459.67. Add local atmospheric pressure to psig before applying the temperature ratio, then subtract it from the predicted final absolute pressure.
Using that NASA relationship, nitrogen at 200.0 psig and 80°F predicts approximately 192.0 psig after cooling to 60°F when atmospheric pressure is 14.7 psi. The calculation is (200.0 + 14.7) × (60 + 459.67) / (80 + 459.67) - 14.7. A raw 8 psi decrease is therefore compatible with that temperature change; it is not by itself an 8 psi leakage finding.
Make the observation represent one isolated volume
Separate the gas supply from the test volume so regulator creep cannot replace escaping gas. Include hoses and valves intentionally, and identify which equipment remains isolated from the field piping. A hose that leaks makes the assembly lose pressure even when the installed joints are tight. After a temperature-corrected loss is confirmed, use the appropriate joint leak-detection method to locate it; the pressure trend does not identify the leaking fitting.
Wait for the piping and gas to reach a representative temperature before taking the baseline. Shaded pipe, sun-heated roof sections and recently filled cylinders do not necessarily share one temperature. Preserve start and finish time, both pressure readings, both temperatures and the correction calculation. Identify the field-brazed joints included in the isolated volume, so a later repair can be matched to the original test record.
Distinctions
- Vacuum decay test
- Observes isolated pressure under vacuum after evacuation. Its units, gas behavior and acceptance criteria differ from a positive-pressure hold.
- Strength test
- Demonstrates a pressure-boundary strength requirement under its governing procedure. A manufacturer's leak or pressure-proof check should retain its stated purpose and acceptance basis.
Frequently asked questions
Does a pressure drop overnight always mean a leak?
The 200 psig example loses about 8 psi from an 80°F-to-60°F temperature change alone. Compare the observed final pressure with the temperature-corrected prediction and the specified hold criterion before diagnosing leakage.
Can a constant gauge reading conceal a leak?
Yes. Gas warming or a connected nitrogen regulator can offset lost gas. Temperature records and isolation define what the pressure observation actually proves.