Decay test
An HVAC vacuum decay test measures absolute pressure over time in a sealed refrigerant circuit after pumping stops. Acceptance depends on both the pressure ceiling and hold duration: Desert Aire's SP service procedure specifies below 500 microns for more than 10 minutes. Refrigerant leaving compressor oil can raise the reading even without an inward leak. Record the applicable procedure and pressure trace so the result identifies what passed and under which equipment conditions.
Isolating the pump and watching the micron gauge for a rise; proves the vacuum holds, not just that it was reached
Read the hold limit as an equipment requirement
Desert Aire's SP service instructions specify evacuation to 400 microns, followed by a vacuum below 500 microns for more than 10 minutes. Its sectioned-unit reconnection instructions recommend a starting pressure around 350 microns to achieve the required hold. Those figures identify both a pull-down condition and a separate acceptance condition.
A trace that starts at 350 microns, rises steadily and reaches its maximum of 470 microns after 12 minutes meets that pressure-and-time criterion. The rise is 120 microns, averaging 10 microns per minute. Two endpoint readings alone do not establish that pressure stayed below the ceiling throughout the hold; retain the trace or intermediate readings. The average rate does not replace the pressure ceiling.
The evacuation guide explains the pump and hose arrangement. Add the exact equipment manual and test boundary to that record so another technician knows which connected components the result represents.
Refrigerant in oil complicates the decay curve
Desert Aire specifically identifies residual refrigerant outgassing from oil as interference with vacuum decay testing after service. A previously charged circuit therefore has another gas source beyond moisture and incoming air. The curve's shape directs further diagnosis, but does not identify the gas by itself.
The SP manual restricts its alternative evacuation process to previously charged equipment after at least 24 hours of unsuccessful standard evacuation, with original cleanliness and tightness established. It excludes circuits with possible water entry or significant time open to the atmosphere. Only after completing the manual's preceding nitrogen-purge and evacuation stages does its final hold permit a rise from 500 to no more than 1,000 microns in 10 minutes.
Connect the decay trace to the preceding leak-detection and repair record. Include whether the circuit was newly installed, previously charged or exposed to water. That service history explains why two equipment procedures can use different hold criteria.
One-micron resolution does not mean one-micron accuracy
AccuTools specifies the μBluVac Micro's accuracy as plus or minus (5 percent of reading plus 5 microns), with 1-micron resolution below 1,000 microns. At a 500-micron reading, the stated accuracy corresponds to approximately plus or minus 30 microns. A single displayed digit is much smaller than that uncertainty.
At an indicated 480 microns, that specification gives an accuracy band of approximately 451 to 509 microns. The display is below 500, but its stated absolute accuracy extends across the limit. Absolute accuracy and repeatability are different instrument properties; the accuracy figure alone does not establish the smallest detectable pressure change. Keep gauge identification, calibration status and sensor condition with the result. AccuTools provides an oil-contamination indication and cleaning instructions for that sensor.
Distinctions
- Pump blank-off test
- Blanking the pump inlet establishes the pump and gauge combination's attainable pressure in that small volume. A circuit decay record represents the isolated equipment volume, including any connected service fittings.
Frequently asked questions
Why does vacuum decay make the micron number rise?
Microns describe absolute pressure. As gas enters or evolves inside the isolated volume, pressure increases and the vacuum weakens. Record a rising pressure in microns rather than describing the gauge number as falling vacuum.
Sources checked
Also defined as
- Isolating the vacuum pump and watching the micron gauge for a rise that signals a leak or remaining moisture
- Isolating the pump and watching the micron gauge for a rise; a fast rise is a leak, a slow stall is moisture