Three-way match
Three-way match approves the invoiced portion of a purchase by checking its ordered price and received quantity. A 400-foot receipt against a 1,000-foot cable order supports a 400-foot invoice; it does not require the invoice to equal the whole order total. Match quantities in a common unit, retain separate controls for charges and inspection acceptance, and route any out-of-tolerance difference through the accounting system's approval process.
Checking the PO, the receiving record, and the invoice against each other before paying
A partial delivery can pass without matching the whole order
Oracle Procurement 26A distinguishes three-way approval, which includes received quantities, from four-way approval, which also includes quantities accepted by inspection. That fourth record matters for materials quarantined after delivery: receiving can confirm arrival while inspection still withholds acceptance. A three-way configuration alone does not enforce the inspection condition.
An order calls for 1,000 feet of cable at 0.40 dollars per foot. The first receipt records 400 feet, and the invoice requests 160 dollars for those 400 feet. The invoice is smaller than the 400-dollar order total and still matches the received portion. The outstanding 600 feet remains an open commitment, not an invoice discrepancy.
Normalize the unit before interpreting a price variance
Microsoft Dynamics 365 calculates net unit price from the line's net amount divided by its quantity, with line charges and discounts included in that net amount. Comparing a supplier's spool price with a purchase order's price per foot without converting units creates a false exception.
Two 500-foot spools contain 1,000 feet. At 200 dollars per spool, the converted price is 0.40 dollars per foot. At 225 dollars per spool it is 0.45 dollars per foot, a 12.5 percent increase. A 5 percent unit-price tolerance flags that comparison as a discrepancy even when receiving confirms both spools; the configured approval controls determine whether posting is blocked or an authorized exception is approved.
Store the spool-to-foot conversion with the purchase line and preserve the original packing slip. The field receipt record then supports both physical quantity and the unit used in the invoice comparison. Keep the unmatched balance open rather than changing a delivery quantity to force a price match.
A match setting and an approval level are separate controls
Oracle treats the invoice match option, meaning purchase order or receipt, independently from the two-, three- or four-way approval level. Choosing receipt matching does not by itself select four-way inspection approval. Record both settings when configuring material categories that require an accepted inspection quantity.
Microsoft also distinguishes unit-price matching from price-total and charge matching. A passed unit-price comparison is therefore narrower than approval of every invoice charge. Route a freight discrepancy to the charge rule, an unrecorded delivery to receiving, and an inspection hold to acceptance rather than editing the invoice until one status turns green.
Frequently asked questions
Can an invoice with a price discrepancy still be posted?
Microsoft Dynamics 365 documents approval of price-match discrepancies as well as correction by the vendor. A failed tolerance comparison identifies an exception; the organization's posting and approval settings determine how it is resolved.