Usable capacity
Usable capacity is the load an installed system can support at its defined delivery boundary under the required operating conditions. It is calculated from the limiting equipment, application conditions and reserve arrangement. It is not obtained by applying one percentage to every nameplate. A capacity figure should state its units, ambient and site conditions, required maintenance or failure state, and the downstream point at which that capacity is deliverable.
Installed capacity minus the redundancy reserve and the continuous-load derate
Read continuous-use limits from the installed assembly
UL's Molded Case Circuit Breaker Marking and Application Guide limits an unmarked standard breaker to 80% of rated current for continuous loading. ABB's application paper defines that duty by maximum current expected for at least three hours, not simply equipment being energized for three hours. A 400 A breaker supplying an entirely continuous load therefore has a 320 A allowance in that application.
UL makes a breaker's 100% continuous rating conditional on the marked enclosure or cubicle arrangement. Reading 400 A on the handle does not establish which continuous-use arrangement was installed. Keep the breaker marking and assembly documentation with the capacity calculation before choosing 320 A or 400 A as the applicable device limit.
ABB's Circuit Breaker Ratings application paper identifies minimum enclosure size, wire-temperature requirements and any required ventilation as conditions of a 100%-rated breaker installation. Its code examples use the 2014 NEC; the cited enclosure and conductor conditions must be verified from the installed product's markings and instructions. A catalog's 100% claim alone does not establish usable output from the assembled equipment.
Treat the breaker allowance as one input to the power-density and capacity plan, rather than an 80% factor for every UPS, transformer and generator. Express the other constraints at the same downstream load boundary, including distribution losses and the cooling available at the intended racks.
Subtract reserve after establishing each module's output
For three modules each rated to deliver 500 kW at the site's specified conditions, a design requiring one module unavailable has 1,000 kW of usable module capacity: (3 - 1) x 500. With 750 kW already committed on that basis, module headroom is 250 kW. Applying another blanket 80% factor would change the answer without identifying an additional limiting condition.
If the documented site correction reduces each module's output to 450 kW, the same arrangement supports 900 kW with one module unavailable, leaving 150 kW above that 750 kW commitment. Calculate the site output first, then the reserve condition. Finally, verify that the remaining distribution path can deliver the result; spare module output is not proof of spare capacity at a particular rack.
Distinctions
- Available headroom
- Usable capacity is the operating limit. Headroom is what remains after existing demand or committed demand is deducted on the same basis. A 1,000 kW usable system carrying 750 kW has 250 kW of measured headroom before other reservations.
Frequently asked questions
Can installed capacity and usable capacity be equal?
They can match at a stated boundary when the installed equipment's documented rating already covers the required duty and no additional reserve is deducted there. The stranded-capacity guide explains why an upstream usable total still needs a deliverable downstream path.