ANVILFIELD Try FieldOS

HVAC

Fan coil unit (FCU) installation and commissioning field guide for HVAC

Hang the FCU, flush and balance the water, set the airflow, prove the condensate drain and overflow, stroke the valve, and write the start-up report.

Fan Coil UnitFCU CommissioningCondensate DrainChilled Water CoilHVAC

Direct answer

A fan coil unit (FCU) is a small terminal unit, a fan and a coil, that heats or cools one zone using hot or chilled water or direct-expansion refrigerant. Commissioning means flushing and balancing the water, setting the fan and airflow, proving the condensate drain and overflow, and stroking the valve against the thermostat.

On this pageWhat a fan coil unit is and where it fitsThe types: 2-pipe, 4-pipe, ducted, exposed, and stackWhat is the difference between a 2-pipe and 4-pipe fan coil?The coil, the water, and the delta-TThe control valve: 2-way, 3-way, modulating, and PICVCondensate: the pan, the trap, and the overflow floatThe air side: fan speed, filter, static, and the grilleMounting the unit: access, clearance, and levelPiping the coil: the valve kit, the strainer, and flush firstThe electrical: disconnect, fan power, and controlsControls: the thermostat, the changeover, and the BMSCommissioning the water sideCommissioning the air sideHow do you test a fan coil condensate drain?How do you commission a fan coil unit?Keeping it running after turnoverStack units, DX coils, and the hotel contextWhat to documentCommon mistakesField checklistStandards and referencesUnits, terms, and conversions

Key takeaways

  • A fan coil unit is a fan and coil terminal unit that heats or cools one zone using hot or chilled water or DX refrigerant.
  • Chilled-water design delta-T often runs near 10 to 16 degrees F and wider on hot water, but use the unit schedule and spec for real targets.
  • A condensate trap is mandatory on a draw-through unit, deep enough to hold against running static, or the negative-pressure pan never drains.
  • Mount the FCU dead level so condensate runs to the outlet and the overflow float reads the pan; off-level lets a corner flood while the float sits dry.
  • Flush, clean, and passivate the loop before opening the coil to it, since construction debris packs a fine coil and PICV seat permanently.

What a fan coil unit is and where it fits

A fan coil unit is a small terminal unit, a fan and a coil in one cabinet, that conditions a single room or zone. Hot or chilled water from a central plant runs through the coil, the fan pushes room air across it, and the air comes off warmer or cooler. Some units carry refrigerant in the coil instead of water and run as a direct-expansion, or DX, head. Either way the FCU is the last device in the chain, the one the occupant actually feels.

It sits below the big equipment. A rooftop unit or an air handler conditions a whole floor or a large zone and moves a lot of air. The FCU serves one room and moves a little. That is why you find them by the hundreds in hotels, apartments, and offices, where every room wants its own setpoint and a central air handler cannot give each one its own control.

The work splits cleanly into two sides, and a job goes wrong when a crew treats them as one. There is the water side, the coil and the flow and the delta-T, which is the same physics our hydronic balancing guide covers at the system level. And there is the air side, the fan and the filter and the airflow off the coil. Commissioning is proving both, plus the condensate drain that protects the room underneath, plus the controls that tie it to the thermostat. Miss any one and the unit runs wrong quietly.

The types: 2-pipe, 4-pipe, ducted, exposed, and stack

Fan coils come in a handful of arrangements, and the ones on your job were chosen by the engineer for the building, not by you. Knowing the type tells you what to expect at the connections before you open the box.

By piping, a unit is 2-pipe or 4-pipe. A 2-pipe FCU has one coil with a single supply and return, and that coil gets hot water in winter and chilled water in summer as the plant changes the whole loop over. A 4-pipe FCU has two coils, a heating coil and a cooling coil, each with its own supply and return, so it can heat or cool at any time. The 4-pipe unit costs more in pipe and valves and gives the most control. The 2-pipe is cheaper and locks the whole building into one mode at a time.

By cabinet, a unit is concealed or exposed. A concealed unit hides above a ceiling or in a soffit and ducts its air to grilles. An exposed unit, the cabinet on the wall or floor in older hotels and schools, blows straight into the room with no ductwork. By orientation it is horizontal, slung above the ceiling, or vertical, standing in a closet or under a window. In high-rise apartments you also get the vertical stack FCU, a unit that stacks floor to floor and shares a riser that passes straight through each unit. That stack is its own animal, and it gets its own section.

What is the difference between a 2-pipe and 4-pipe fan coil?

A 2-pipe fan coil has one coil fed by a single supply and return. The plant sends hot water to the whole building or chilled water to the whole building, never both at once, and the same coil does whatever the loop is carrying. A 4-pipe fan coil has two separate coils, heating and cooling, each on its own pair of pipes, so any unit can call for heat while the unit next door calls for cooling.

The catch on the 2-pipe unit is that the controller has to know which mode the loop is in, or it will open the valve to cool when the pipe is full of hot water. That is what the changeover sensor does. It is a temperature sensor strapped to the supply pipe, and it reads the water temperature to tell the controller heat or cool. On a 4-pipe unit there is no changeover sensor, because hot and chilled are both always available and the controller just picks the coil it needs. Confirm the exact changeover setup against the specified controller, because the threshold and deadband are settings, not defaults.

The field consequence is the shoulder season. A 2-pipe building stuck in cooling cannot heat a cold north room on a chilly spring morning, no matter what the occupant does at the thermostat, until the plant changes the loop over. That is a design limit baked into the pipe count, not a fault you can commission out. Know which building you are in before the complaints start.

The coil, the water, and the delta-T

The coil is a finned tube heat exchanger, and the heat it moves depends on the water flow through it and the temperature difference the air pulls out of that water. Flow is measured in gallons per minute, and every unit has a design flow on the schedule. Hit that flow and the coil performs as rated. Starve it and the room never reaches setpoint no matter how long the fan runs.

Delta-T is the temperature difference between the water going into the coil and the water coming out. It is the single number that tells you the coil is doing work. On chilled water the design delta-T is often somewhere near 10 to 16°F, and on hot water it is usually wider, but the unit schedule and the project specification carry the real targets, so read them rather than carrying a number in your head. The flow and the delta-T are linked: at design flow a healthy coil produces design delta-T, and a coil that passes the right flow but shows a flat delta-T is fouled, air-bound, or moving no air on the other side.

This is the same flow and delta-T logic our hydronic balancing guide works through for the whole system. At the unit, the question is narrower. Is this one coil getting its design GPM, and is it pulling the design temperature out of that water? When both are true the unit is right. When the delta-T runs low across many units at once, the problem is usually the system, oversupplied and short-circuiting, not the individual coils, and that is a balancing problem rather than a unit problem.

The control valve: 2-way, 3-way, modulating, and PICV

The control valve is what turns the room's call for heating or cooling into water flow through the coil. It comes in a few forms, and the form drives how you commission the unit.

By porting it is a 2-way or a 3-way valve. A 2-way valve sits in the supply, opens and closes, and either lets water through the coil or stops it, which means closing valves across the building reduce total flow and the system needs variable-speed pumping to keep up. A 3-way valve has a bypass port: when it closes off the coil it diverts the water around it, so flow through that branch stays roughly constant. By action it is on-off or modulating. On-off snaps fully open or fully shut. A modulating valve, driven by a proportional actuator, throttles to part flow and gives steadier room temperature with less hunting.

The arrangement worth knowing is the pressure independent control valve, the PICV. It packs a control valve, a differential pressure regulator, and a flow limiter into one body, so you dial the design flow on the valve and it holds that flow as system pressure swings around it. Danfoss, Belimo, Honeywell, and others build FCU PICV kits, so confirm the model and the flow setting against the submittal. The reason it matters at commissioning is direct: with a PICV you set the design flow at each unit and skip the iterative proportional balancing a plain 2-way valve forces, because the valve self-balances against pressure. The actuator on any of these has to stroke the full travel, and a valve that buzzes, sticks part way, or never seats is the failure you find on the functional test, not before it.

Condensate: the pan, the trap, and the overflow float

The cooling coil pulls water out of the air, and that condensate has to leave the building cleanly or it ruins the room below. This is the classic fan coil callback, and it is almost never the equipment. It is the drain.

Under the coil is the drain pan, pitched so water runs to the outlet, never flat and never sloped back. From the outlet the condensate goes to a drain line. On a draw-through unit, where the fan sits downstream of the coil and pulls air through it, the pan compartment runs at negative pressure, and a trap is not optional. Without a properly sized trap the negative pressure holds the water in the pan and it never drains, then it overflows. On a draw-through coil the trap is mandatory, on a blow-through unit it is not, and the trap has to be deep enough to hold against the unit's static pressure when it is running. A trap that is too shallow gets sucked dry and pulls air instead of passing water.

Because the drain will eventually plug with the biofilm that grows in any condensate line, the second line of defense is an overflow protection. A water-level float in the pan, or a float in a secondary pan under the unit, rises with the water and shuts the unit down before the pan spills. A water-level monitoring device is commonly required where there is no secondary drain, but confirm the exact requirement against the adopted mechanical code edition and local amendments. One blunt rule carries this whole section: an FCU sitting above a finished ceiling without a working trap and a working overflow float is a leak waiting for a tenant, and the unit has to be dead level for the float to read the pan at all.

The air side: fan speed, filter, static, and the grille

The air side is the half crews forget, because the water connections look like the real work. The fan moves the room air across the coil, and if it moves the wrong amount the coil temperature is academic.

Older units run a multi-speed fan, high, medium, low, tapped off the motor, and the design picks a speed to hit the rated airflow. Newer units use an ECM motor that holds a commanded airflow as the filter loads up, which is the better setup and the one more specs call for now. Either way the airflow off the coil has to match the design, because the rated capacity assumes that airflow. Run the fan too slow and the coil can freeze on chilled water or the room never gets enough air.

The filter is upstream of the coil and it is the first thing to load. A dirty filter chokes airflow, and on a concealed ducted unit it does it invisibly, behind a ceiling, until the room goes warm. On a ducted FCU the fan has to overcome the external static pressure of the duct, the grille, and the filter, so a unit set up free-blow on the bench will not hit airflow once it is pushing through real ductwork. The throw and the grille selection decide whether the conditioned air actually reaches the occupant or dumps down the wall, which is the same register-and-throw work our air balancing guide covers at the room level. Set the fan, then prove the airflow at the grille, not at the motor.

Mounting the unit: access, clearance, and level

Hang the unit so it can be serviced, because everything on a fan coil is maintenance, the filter, the pan, the coil, the valve, and a unit you cannot reach is a unit nobody maintains. The most common install sin is burying a concealed FCU above a hard ceiling with no access panel under the filter and the valve package. The first filter change reveals it, and by then the drywall is up.

Mount it dead level, or pitched only the way the pan needs to drain. A unit racked off level sends condensate to the wrong corner, away from the drain outlet and away from the overflow float, so the pan can overflow while the float sits dry. Support a horizontal unit from all its hanger points with vibration isolation, because a fan coil hums and that hum telegraphs into the structure and into the room below if it is hung rigid.

Leave clearance the manufacturer calls for at the coil connections, the valve package, and the electrical box, and leave room to pull the filter without dismantling the duct. Plan the access panel before the ceiling closes, sized to reach the filter, the drain pan cleanout, and the valve actuator. The clearances on the submittal are minimums for service, not suggestions, and the inspector who has seen the leaks checks for drain access and a working overflow before signing off.

Piping the coil: the valve kit, the strainer, and flush first

The connection between the coil and the riser is a small valve package, and a good one makes the unit serviceable for twenty years. A typical kit carries an isolation valve on the supply and the return, usually ball valves, so the unit can be shut and pulled without draining the riser, a strainer to keep debris out of the coil and the control valve, the control valve or PICV itself, unions so the unit comes apart, and a means to read flow. An automatic air vent at the high point lets trapped air out of the coil.

The strainer is there because the system will hand the coil debris, and it earns its keep at flush. Flush the piping before you connect the coil, every time. Standard practice is to dynamically flush, chemically clean, and passivate the loop before the coils are opened to it, because construction debris, pipe scale, and weld slag will pack a fine coil and a PICV seat and you will never get it back out. Where the unit is connected before the system is clean, the strainer protects it, and that strainer screen gets pulled and cleaned after commissioning before handover, because it has caught the junk.

Once the coil is connected and the loop is clean, fill it and vent it. Air trapped in a coil blocks flow as surely as a closed valve and gives you a flat delta-T on a unit that looks plumbed correctly. Open the automatic air vent or the manual bleed at the coil high point until water runs without sputter, then close it. This filling, venting, and flow-setting is the unit-level slice of the hydronic balancing guide, done one coil at a time.

The electrical: disconnect, fan power, and controls

A fan coil needs power for the fan motor and for the controls, and it needs a means to kill that power at the unit for service. Provide the disconnect the code and the manufacturer require within sight of the unit, because the tech changing a motor or clearing a pan should not have to trust a breaker two floors away.

The fan motor is small, but it is still a motor, and the controls power, the 24 V transformer that runs the thermostat, the valve actuator, and the float switch, is what makes the unit smart. Wire the overflow float so that when it trips it actually stops the thing causing the water. On a hydronic unit that means closing the cooling valve or dropping the unit, and the wiring detail matters, so follow the manufacturer's diagram rather than guessing which leg to break.

Keep the line voltage and the low-voltage control wiring separated and landed where the diagram shows, and confirm the unit is grounded. The electrical on an FCU is simple enough that it gets rushed, and a controls transformer wired wrong or a float left unconnected is how the safety you installed does nothing on the day it is needed.

Controls: the thermostat, the changeover, and the BMS

The controls turn a room's call into water and air. At the simplest it is a zone thermostat that reads room temperature, runs the fan, and drives the control valve. The fan can be set to run continuously or to cycle with the call, and the spec usually says which, because continuous fan helps mixing and keeps the room reading honest while cycling saves energy and noise.

On a 2-pipe unit the changeover sensor feeds the controller the supply water temperature so it knows whether to allow heating or cooling, and that changeover threshold is a setting you confirm at commissioning, not a default you assume. On a 4-pipe unit the controller drives the heating valve or the cooling valve directly with no changeover to set.

Most commercial FCUs today land on a building management system over a network, commonly BACnet, so the controller reports room temperature, valve position, fan status, and alarms back to a head end. That ties into occupancy and setback: the room runs a comfortable setpoint when occupied and drifts to a wider band when empty, which on a few hundred hotel rooms is real money and real plant load. The functional test has to prove every one of these paths actually works, the local stat, the changeover, and the BMS point, not just that the unit blows cold air when you jumper it.

Commissioning the water side

Water-side commissioning starts before the coil ever sees flow. The loop has to be flushed and clean, because a coil balanced on dirty water gets fouled and falls off its numbers within the season. Confirm the system has been filled and vented, with the air bled at the risers and at each unit, before you trust any reading.

With clean, vented water, set the flow at the unit to its design GPM. On a plain balancing valve that means reading flow across the valve and adjusting it, the proportional balancing our hydronic balancing guide lays out in full, working from the index unit outward. On a PICV it means setting the design flow on the valve dial and letting the valve hold it, which is faster and why so many fan coil systems specify them now. Either way, the target is the design GPM on the schedule, and the manufacturer's valve flow data, not a guess, tells you what setting gives that flow.

Then prove the coil with delta-T. With the valve full open to the coil and the air side running, read the water temperature in and out. A delta-T at or near design says the coil is passing its flow and pulling its heat. A low delta-T on a unit that shows the right flow means trapped air, a fouled coil, or no airflow on the other side, so check the air bleed and the fan before you blame the coil. Record the flow and the delta-T for every unit. That record is the water-side proof that the coil works.

Commissioning the air side

Air-side commissioning proves the unit moves the right air and conditions it. Start with a clean filter installed, because a unit set up around a dirty or missing filter is set up around the wrong static pressure and the numbers will not hold once the real filter goes in.

Set the fan speed the design calls for, the motor tap on a multi-speed unit or the commanded airflow on an ECM, then confirm the airflow. On a free-blow exposed unit you can read it at the discharge. On a ducted concealed unit you read it at the grilles and total it, the same room-level airflow work the air balancing guide covers, because the external static of the duct and grille pulls the delivered airflow below the bench figure. If the unit cannot make airflow, the duct is too restrictive, the filter is wrong, or the fan is set too low.

Then read the temperature change across the coil on the air side. With the valve open and water flowing, the air should come off the cooling coil colder, or the heating coil warmer, by an amount that fits the design and the entering conditions. An air-side temperature drop that is too small, on a unit with good water flow and delta-T, points back to airflow that is too high for the coil or a coil that is fouled. The air-side temperature change and the water-side delta-T are two views of the same heat transfer, and they have to tell the same story.

How do you test a fan coil condensate drain?

Test the condensate drain by making it work, not by looking at it. Pour water into the drain pan until it fills toward the outlet, and watch it run out through the trap and the drain line with no backup and no spill over the pan lip. If the water sits, the pan is sloped wrong, the trap is dry or wrong, or the line is blocked, and you fix it before the unit ever runs in cooling.

Then prove the overflow protection. Plug the drain line downstream so the pan fills, and confirm the water-level float rises and shuts the unit, or shuts its cooling, before the pan overflows. If the float never trips, the only thing standing between a plugged drain and the ceiling below is luck. Confirm the unit is dead level while you do this, because a unit racked off level can overflow the low corner while the float sits dry in the high one.

This test is cheap and it is the one that prevents the most expensive callback in the trade. A fan coil above a finished space that floods a room costs more in drywall, paint, and a furious tenant than the entire unit. Run the drain test on every unit, document it, and do not take a verbal that the drains are fine. The room below is the backup, and that is not a backup.

How do you commission a fan coil unit?

Commissioning a fan coil is proving the whole sequence works together, then writing it down. The water and air are set in their own steps. The functional test ties them to the controls and proves the unit does what the thermostat asks.

Drive the unit through its modes from the stat or the BMS. Call for cooling and confirm the cooling valve strokes open, water flows, the fan runs at the right speed, and the supply air goes cold. Call for heating and confirm the heating side does the same, watching the valve actuator move its full travel and seat. On a 2-pipe unit, confirm the changeover holds the unit out of the mode the loop cannot serve. Drop the call and confirm the valve closes and the fan follows its programmed behavior. Then check the BMS shows the right room temperature, valve position, and fan status, and that occupancy or setback shifts the setpoint as programmed.

Capture the start-up readings as you go, because a unit is not commissioned until the numbers are recorded against a unit tag. The deliverable is a per-unit record: the unit identifier and type, the water flow and delta-T, the air-side temperature change, the condensate drain and overflow result, and the controls check. On a hotel or apartment job with hundreds of units, the value is consistency, the same set of readings on every unit so the one that is wrong stands out against the ones that are right.

TestWhat to confirmPass condition
Cooling callValve strokes, water flows, fan runs, air goes coldSupply air drops per design
Heating callHeating valve full stroke, seats, fan runsSupply air rises per design
2-pipe changeoverSensor reads supply temp, controller picks modeNo cooling call into hot loop
Call removedValve closes, fan follows programCoil isolates, no creep flow
BMS / setbackPoint values report, setpoint shifts on occupancyHead-end matches the field

Keeping it running after turnover

Hand the owner a unit that can be maintained, and tell them what it needs, because the way a fan coil fails after handover is predictable. The filter is the first thing and the most neglected. A clogged filter starves airflow, drops capacity, and on chilled water can freeze the coil, and on a concealed unit it does all that out of sight. Filter changes on a schedule are the single highest-value thing the owner does, and on a few hundred units that means a route, not a memory.

After the filter, the condensate pan and drain. The biofilm that grows in any condensate line is the eventual plug, so the pan and the trap and the line get cleaned on a schedule, not after the leak. The coil face loads with dust that slips past the filter and needs cleaning to hold capacity. The control valve and actuator should still stroke fully, and a valve that has stuck part open or closed is a room that runs hot or cold for no reason the occupant can see.

None of this is exotic, and that is the point. The fan coil is a simple machine that fails from simple neglect. The commissioning record you leave is also the maintenance baseline, the flow and delta-T and airflow the unit had when it was right, so the tech three years later has a number to compare against instead of a guess.

Stack units, DX coils, and the hotel context

A few fan coil situations change the work enough to call out. The vertical stack FCU in a high-rise apartment is the first. These units stack floor to floor and the supply and return risers pass straight through each unit, so the riser is part of the unit and a leak or a connection deep in a stack can mean opening finished apartments above and below to reach it. The pressure-test and the connection quality on a stack riser are not a place to save time, because the access cost after handover is brutal.

The DX fan coil is the other common variant. Instead of water it carries refrigerant, paired with a remote condensing unit or running as the indoor head of a split or VRF system, and AHRI 440 specifically does not cover volatile refrigerant coils, so the rating basis is different. The air side, the condensate, and the controls commission the same as a hydronic unit, but the heat-transfer side moves to the refrigerant, the charge, the line set, and the superheat or subcooling, which is its own charging procedure rather than a water balance.

Then there is the context that makes fan coils their own discipline: volume. A hotel, an apartment tower, or an office floor has hundreds of nearly identical units, and the win is consistent commissioning, the same readings taken the same way on every unit, so the outlier is visible. Comfort-cooling fan coils also show up in data centers and equipment rooms as room-level trim, and there the consistency and the condensate protection matter even more, because the thing under the leak is not a carpet, it is hardware.

What to document

The fan coil report is per unit, and it has to tie a set of readings to a unit tag, because on a job with hundreds of units a reading with no tag is a reading you cannot use. Capture the unit identifier and location, the type, the water flow and delta-T, the air-side temperature change, the condensate drain and overflow result, and the controls check. Note any deficiency you could not fix and who owns it.

That record does two jobs. It proves the unit was commissioned, and it is the baseline maintenance compares against for the life of the unit. The reading that means nothing the day you take it is the one that tells the next tech, three years out, whether the unit has drifted or held.

Field to recordWhy it matters
Unit tag and locationTies the readings to one device among hundreds
Type (2-pipe / 4-pipe / DX)Sets what was tested and how it is controlled
Water flow (GPM)Confirms the coil got its design flow
Water delta-TProves the coil is doing work, catches fouling and air
Air-side temperature changeCross-checks the water side from the room side
Condensate drain and overflowThe leak protection actually proven, not assumed
Controls / BMS checkStat, changeover, valve stroke, and point values verified

Common mistakes

  • No trap, or a too-shallow trap, on a draw-through unit, so the pan never drains and overflows.
  • Overflow float left unwired or untested, so a plugged drain floods the room with no shutdown.
  • Unit hung off level, so condensate runs to the wrong corner while the float sits dry.
  • Coil opened to the system before the loop was flushed, fouling the coil and the valve seat.
  • Coil left air-bound after fill, giving a flat delta-T on a unit that looks plumbed right.
  • Flow never set or balanced, so near units rob the far ones and rooms at the end never reach setpoint.
  • Fan speed wrong or filter dirty, so the airflow is below design and the capacity follows it down.
  • Changeover sensor not set on a 2-pipe unit, so the controller calls for the mode the loop cannot serve.
  • Concealed unit buried with no access panel, so the filter, pan, and valve cannot be serviced.

Field checklist

0 of 10 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

Fan coil performance ratings come from AHRI Standard 440 (I-P), with the metric companion 441 (SI), Performance Rating of Fan-coil Units. It covers room fan-coils up to about 1500 cfm and sets how total cooling, sensible cooling, and power input are tested and published so units compare against each other. It does not cover volatile refrigerant coils or steam-only coils, so a DX head is rated on a different basis. Confirm the edition referenced by the project; the standard has been revised across cycles.

ASHRAE standards carry the design side, ventilation and comfort and energy, that set what the unit was sized to deliver. The water-side flow setting and the air-side measurement follow the test, adjust, and balance procedures from AABC and NEBB, the same bodies behind the hydronic and air balancing this guide cross-references. The condensate drain, the trap, and the overflow protection are governed by the adopted mechanical code, and the requirement for a water-level shutoff device varies with the edition and local amendments, so confirm it with the AHJ.

Above all of these sit the manufacturer's installation instructions and the project specification. The trap depth, the clearances, the flow setting, the changeover threshold, and the wiring of the float are unit-specific and spec-specific. Cite the standard that governs the point, and let the manufacturer and the contract documents control the numbers.

Units, terms, and conversions

Fan coil work crosses water units, air units, and control terms, so the same unit reads differently across a schedule, a submittal, and a controls drawing.

Water flow is in gallons per minute (GPM) on most US drawings and liters per second (L/s) on metric ones. Delta-T, the water or air temperature difference, is in degrees Fahrenheit here and Celsius on metric sheets. Airflow is in cubic feet per minute (cfm) or liters per second. Capacity is in Btu/h or tons of cooling on US sheets and kilowatts on metric. Static pressure on the air side is in inches of water column (in. w.c. or in. wg). Keep the changeover, PICV, ECM, and BMS terms straight, because they decide how the unit is controlled and commissioned.

FCU
Fan coil unit, a terminal fan-and-coil that conditions one zone from central water or its own refrigerant
2-pipe / 4-pipe
One coil on a seasonal changeover loop, versus separate heating and cooling coils available at once
Delta-T
The temperature difference across the coil, water side or air side, that shows the coil is doing work
PICV
Pressure independent control valve, combining control, differential-pressure regulation, and flow limiting in one body
Changeover sensor
Supply-pipe temperature sensor that tells a 2-pipe controller whether the loop is hot or chilled
Draw-through
Fan downstream of the coil, so the pan runs at negative pressure and a condensate trap is mandatory
ECM
Electronically commutated motor that holds a commanded airflow as filter resistance changes

Related tools

Field notes

Public fan-coil installations need the same per-unit commissioning record; PorchRocket's Bid Control surfaces school and municipal HVAC replacement bids for firms that install, balance and document room equipment.

Next step: Build a hotel service list

FAQ

What is a fan coil unit?

A fan coil unit is a small terminal unit, a fan and a coil in one cabinet, that conditions a single room or zone. It runs on hot or chilled water from a central plant, or on its own refrigerant, and serves hotels, apartments, and offices where each space needs its own control.

What is the difference between a 2-pipe and 4-pipe fan coil?

A 2-pipe fan coil has one coil and one supply and return, so the same pipe carries hot or chilled water by season and a changeover sensor tells the controller which mode it is in. A 4-pipe unit has separate heating and cooling coils, needs no changeover, and can heat or cool any time.

Why does my fan coil leak?

Most fan coil leaks are condensate, not the piping. The drain trap is missing or dry on a draw-through unit, the pan is sloped wrong, or the drain is plugged with biofilm. A unit above a ceiling then overflows into the room below. A water-level float in the pan should shut it down first.

How do you commission a fan coil unit?

Flush and vent the water, set the coil flow to design at the balancing valve or PICV, then check delta-T across the coil. On the air side, set the fan speed, confirm airflow, and read the temperature change across the coil. Fill the pan to prove the drain and overflow float, then stroke the valve from the thermostat.

What is a PICV on a fan coil?

A PICV is a pressure independent control valve. It combines the control valve, a differential pressure regulator, and a flow limiter in one body, so you dial in the design flow and the valve holds it as system pressure swings. On a fan coil it removes the separate balancing step.

What delta-T should a fan coil show?

Delta-T is the temperature difference between the water entering and leaving the coil, and it should track the design on the unit schedule, often near 10 to 16°F on chilled water and wider on hot water. A low delta-T usually means too much flow, a fouled coil, or trapped air, not a bad unit.

How do you test a fan coil condensate drain?

Pour water into the drain pan until it fills, and watch it run out through the trap and drain line with no backup. Then plug the line so the pan fills to the float, and confirm the overflow switch shuts the unit or its cooling. If the float never trips, the room below is the backup.

What maintenance does a fan coil need?

The filter is the first thing and the most neglected. A clogged filter starves airflow and freezes coils, so change or wash it on a schedule. After that, clean the condensate pan and drain to stop the leak, clean the coil face, and check the valve and actuator still stroke. Hotels need a route, not a memory.

What is a DX fan coil?

A DX fan coil uses refrigerant in its coil instead of water, paired with a remote condensing unit or as the indoor head of a split or VRF system. Commissioning shifts to the refrigerant side, the charge, line set, and superheat or subcooling, while the air side, condensate, and controls work the same as a hydronic FCU.

People also ask