ANVILFIELD Try FieldOS

American Concrete Institute

ACI 117: concrete tolerances and measurement compatibility

ACI SPEC-117-10, reapproved 2015, supplies dimensional acceptance tolerances for concrete construction and materials. Its suspended-slab thickness allowance is minus 1/4 in.; satisfying elevation tolerances does not cancel that thickness check. The companion ACI PRC-117.1-14 addresses measurement capability and the fit between concrete and adjoining assemblies. Use the specification for acceptance and the compatibility guide to determine whether the connection has enough adjustment to assemble.

Current edition: ACI SPEC-117-10, reapproved 2015 (2010 specification); ACI PRC-117.1-14 (2014 compatibility guide)
Updated

Official publisher page

Applies to

Specifiers select the tolerances, surveyors establish the measurements, concrete contractors control construction, and inspectors compare the completed element with its intended geometry. Owners use the resulting record to distinguish an installation conflict from a concrete dimensional failure.

Use the construction layout guide to establish the survey framework, then identify the drawing dimension, datum, instrument setup, and acceptance stage for each tolerance check. A benchmark identifier and survey date make the result traceable when the structure is measured again under different loading.

Key topics

Why two passing elevations can still make a thin slab

ACI 117-10(15) treats dimensional tolerances as concurrent checks; an allowance for one dimension cannot enlarge another. ACI's tolerance seminar identifies the suspended-slab thickness allowance in Section 4.5.3 as minus 1/4 in., with no positive thickness limit in that provision. Other elevation, cover, and loading requirements still apply. Put top elevation, soffit elevation, and thickness on one section sketch so acceptance of one dimension cannot conceal failure of another.

Can the survey resolve the specified tolerance?

ACI 117.1R-14 recommends measurement capability no coarser than one-third of the tolerance being checked. A 3/8 in. tolerance therefore calls for a method that reliably measures 1/8 in. or less. Record a repeated check from independent control along with instrument, target, and sight distance. A scanner displaying many decimal places still needs evidence that its registration and control support the required measurement capability.

Concrete tolerances at steel and enclosure interfaces

ACI PRC-117.1-14 addresses compatibility at embeds, elevator hoistways, openings, reinforcing couplers, stairs, cladding, and floor finishes. Translate each interface into available adjustment: slot travel, bearing length, grout space, shim range, or opening clearance. A concrete member and an attached assembly can each meet their own fabrication tolerance while the connection lacks enough adjustment to assemble. Resolve that dimensional fit in coordinated details before fabrication.

How it is used in the field

An 8 in. suspended slab measures 7-5/8 in. thick at a surveyed location. Its 3/8 in. shortfall exceeds the cited 1/4 in. thickness allowance by 1/8 in. Record the top elevation, soffit elevation, and thickness individually; extra allowance from an elevation check cannot be transferred to the thickness check. The disposition record should identify the affected location and the accepted correction or engineering resolution.

For an equipment opening, make a dimensional budget with separate lines for concrete variation, equipment fabrication variation, required installation space, and attachment travel. Compare the tightest permitted opening with the largest permitted equipment envelope. A connection with nominal clearance but insufficient adjustment needs a revised detail before fabrication; averaging its two clearances will not establish fit.

Separate initial construction acceptance from later movement. A repeat survey should identify its date, loading condition, support condition, benchmark, and instrument. The slab curling guide explains the subsequent slab behavior; the tolerance record establishes the geometry at the specified acceptance stage.

Edition history

The 2015 reapproval retains the 117-10 designation. ACI's Committee 117 listing still identifies that edition and the 2014 compatibility guide. A reference to 'ACI 117-15' obscures the actual document being specified.

Adoption

ACI publishes 117 as a reference specification for specification writers and other standards committees. Its use on a project comes through the controlling construction documents or a governing reference. Record the selected edition and any project changes on the inspection plan, including the measurement method and acceptance stage.

Frequently asked questions

What must accompany a scan used for tolerance acceptance?

Identify the control points, registration checks, measurement capability, survey date, and loading or shoring condition. Then show which drawing dimension each reported deviation tests. A colored deviation map without those references leaves the acceptance reviewer unable to reproduce the comparison.

Is ACI 117.1 another mandatory tolerance schedule?

It is a compatibility guide. Use it to coordinate the allowances of adjoining materials and the reliability of measurements; use the project specification and its invoked tolerance provisions for acceptance.

Sources checked

Field guides that apply ACI 117

Browse all codes and standards