ASTM E1155: floor-profile measurement and valid test sections
An E1155 report assigns FF flatness and FL levelness estimates to a defined floor surface using measured profile lines. ASTM E1155/E1155M-23 is the current method. A valid survey needs planned sections, line locations and statistical coverage, not just an instrument printout. ASCC's published measurement checklist sets a useful layout check: a test section needs at least 320 square feet and every side must be at least 8 feet.
Applies to
The testing agency defines the survey geometry, the concrete contractor supplies the placement map, and the owner or designer supplies the acceptance criteria. Link each test section to the FF/FL specification and the pour identified in the inspection and test plan. The geometry and report details below are attributed to ASCC's January 2010 checklist; the project must name its governing E1155 edition separately.
Key topics
Draw the test sections before the profiler arrives
ASCC's January 2010 E1155 checklist calls for at least 320 square feet per test section, with no side shorter than 8 feet. It also keeps a section boundary from crossing a concrete construction joint and prohibits assigning the same surface area to multiple sections. Put the section map beside the pour plan so the proposed boundaries can be checked before the agency collects data. A section name alone does not establish its geometry.
Different tolerance zones need different test surfaces
The ASCC checklist treats portions with different specified tolerances as separate test surfaces. A general warehouse area and a more demanding equipment zone should therefore retain their own criteria and reported populations. Mapping both under a single overall heading makes the acceptance requirement ambiguous. The approved survey plan should identify the surface, sections within it and the criterion assigned to each, rather than sorting the readings after their values are known.
Orient profile lines to the joint, not the rectangle diagonal
ASCC's 2010 checklist places the diagonal layout at 45 degrees to the longest construction joint bordering the test section, explicitly excluding corner-to-corner diagonals. Its other layout uses equal numbers of lines, with equal aggregate lengths, parallel and perpendicular to the longest section boundary. When the section width is below 25 feet, the checklist requires the 45-degree arrangement. A 20-by-60-foot rectangle therefore does not qualify by running its long corner diagonal.
Require the confidence interval and original profile lines
ASCC's E1155 checklist calls for section F-numbers with a 90 percent confidence interval, line profiles and calculated results for the complete test surface. Retain the equipment identification, calibration date, placement date and measurement date with those outputs. The interval describes uncertainty in the statistical profile estimate; it is separate from the specified minimum and does not replace the acceptance comparison.
How it is used in the field
A 60-by-40-foot placement contains a construction joint dividing it into two 30-by-40-foot areas. Draw two sections of 1,200 square feet each, preserving the joint as their common boundary. Identify each measurement line on that map and report the corresponding section result. A later correction can then be located within the original survey instead of becoming an unnamed floor repair.
A narrow strip measures 6 by 60 feet. Its 360-square-foot area exceeds 320 square feet, but its 6-foot width misses the ASCC checklist's 8-foot minimum side. Increasing the strip length does not solve that geometry problem. Identify the appropriate measurement and acceptance arrangement for that portion before collecting readings that will be presented as a compliant test section.
Keep the coordinate or elevation survey alongside the F-number report. E1155 evaluates differences in the surface profile; moving an otherwise identical profile vertically by 2 inches does not change those differences. The same profile can therefore retain its FF and FL while the floor's absolute elevation is wrong by 2 inches. The construction layout guide provides the datum and elevation checks that address that separate requirement.
For a later curling investigation, reproduce the earlier line locations where useful and label the investigation date and surface condition. ASTM expressly recognizes curling and deflection investigations as uses of the method. Preserve the original acceptance dataset so the new profile documents change rather than replacing the record of the placed floor.
Edition history
ASTM lists E1155/E1155M-23 as active and identifies the older E1155-20 and E1155-14 publications separately. The current designation includes both unit systems. ASTM requires those systems to be used independently, so retain the chosen units with the raw profile data and the calculation software settings.
Past public construction awards in PorchRocket's Bid Control identify who won the work, giving floor-testing firms a starting point for contractor outreach.
Frequently asked questions
Does an F-number report prove the slab is at design elevation?
The method describes surface profiles through relative measurements. Absolute elevation needs the project datum and an elevation survey; a vertical offset of the whole profile is invisible to its relative differences.
Can the same F-number acceptance be applied to fixed wheel paths?
A narrow-aisle truck repeats known wheel tracks. ASTM E1155/E1155M-23 directs attention to measuring those actual profiles with a continuously recording profiler configured for the wheel paths; it excludes enforcing fixed-path floor tolerances through the statistical FF/FL results. Put the wheel-path measurements and their acceptance criteria in the truck-floor scope.