American Concrete Institute
ACI 347: formwork responsibilities, shore details, and revision control
ACI PRC-347-14, reapproved 2021, guides formwork design and construction; ACI PRC-347.2-17, reapproved 2025, addresses multistory shoring and reshoring. Their recommendations support the temporary-works design. OSHA 29 CFR 1926.703 separately requires inspections of erected shoring immediately before, during, and after concrete placement. The field review must connect the current drawings, actual bearing and bracing arrangement, placement loads, and observed condition of the erected system.
Applies to
Formwork designers, structural designers, concrete contractors, suppliers, and inspectors need an agreed responsibility map. Identify who supplies construction loads, designs temporary supports, inspects erection, and accepts revisions. Use the formwork systems guide for system selection, then record the actual load path and drawing revision for each installed bay.
Use the shoring and reshoring guide for the construction sequence and the self-consolidating concrete guide where the specified concrete changes the formwork loading assumptions.
Key topics
An offset shore-head load needs its own design
OSHA 29 CFR 1926.703(b)(7) prohibits eccentric loading on shore heads and similar members unless they are designed for it. A beam shifted away from a support's intended bearing line changes the load path even if its weight remains the same. Show offsets on the formwork detail and resolve fit-up conflicts before loading the assembly.
Stacked single-post shores trigger specific checks
OSHA 29 CFR 1926.703(b)(8) requires tiered single-post shoring to be designed by a qualified designer and inspected after erection by an engineer qualified in structural design. The rule also requires alignment, splices that prevent misalignment, bracing in two perpendicular directions at splice levels, and diagonal bracing in those directions within each tier. Treat a stacked-post arrangement as a defined system requiring those details.
Do not jack single-post shores after placement
OSHA 29 CFR 1926.703(b)(9) prohibits adjusting single-post shores to raise formwork after concrete has been placed. Set and verify the elevations before placement. An observed movement during the pour belongs in the project's response process; it is not permission to turn a shore adjustment and redistribute loads through the partially completed system.
Shoring inspection continues through the placement
OSHA 1926.703(b)(3) requires erected shoring inspections immediately before, during, and immediately after concrete placement. Under (b)(4), immediate reinforcement is required when damage or weakening reduces erected shoring below the required load capacity. A completed erection inspection cannot close these later duties. Assign the inspection stages on the placement plan and identify the current bay, observed condition, and action taken in each record.
How it is used in the field
Compare the erected formwork with the current temporary-works drawings at the locations where loads enter and leave the system. Check bearing lines, heads, splices, braces, sills, and the supporting structure. A visually straight row of posts does not establish that the members above and below it align with the designed load path.
A 4000-pound vertical load acting 3 inches from its intended support line introduces a 1000 foot-pound moment: 4000 × 3/12. That calculation identifies the consequence of the offset; member capacity still comes from the formwork design. Include the measured offset and a marked photograph in the request for a revised detail so the designer receives the actual geometry.
Maintain a current register for the jack layout, formwork and shoring, working decks, and scaffolds. OSHA 1926.703(a)(2) requires the drawings or plans, including revisions, to be available at the jobsite. Mark superseded sheets in the field set and identify the installed bays affected by each accepted revision so a crew does not build a new arrangement from an obsolete detail.
At each handoff, record the constructed configuration and outstanding deviations before the next operation begins. The erection inspection, placement authorization, and eventual removal decision answer different questions. Keeping them as identifiable records prevents a signature on one inspection from being treated as blanket acceptance of later changes.
Edition history
ACI's Committee 347 register identifies the general formwork guide as ACI 347-14, reapproved in 2021. It lists the shoring and reshoring companion as ACI 347.2-17, reapproved in 2025. Reapproval retains the underlying edition; specify the complete identifier so the 2025 reapproval is not mistaken for a rewritten guide.
Adoption
ACI 347 provides guidance that the project can turn into specified duties and details. OSHA's cited provisions are federal construction requirements for covered work. Keep their authority distinct in inspection records: a project reference to an ACI guide does not replace the employer's obligations under 1926.703.
Frequently asked questions
Is a supplier rating enough to accept an offset shore head?
OSHA 1926.703(b)(7) requires design for eccentric loading when it occurs. Supply the system designer with the measured offset, supported member, loads, and bearing arrangement. A component's concentric rating does not establish the capacity of that offset configuration.
What belongs in a request to move a shore?
Identify the bay, current drawing revision, proposed new location, reason for the move, and loads already present. Include the members and supports above and below the change so the review can follow the resulting load path.