ACI 522: pervious pavement specifications, lots, and acceptance evidence
Pervious pavement needs two distinct ACI 522 references: PRC-522-23 explains the material and its applications, while SPEC-522.1-20 supplies construction requirements when incorporated into the contract. Acceptance depends on identifying the specified property, test method, and pavement lot. Fresh density, hardened density, and surface infiltration describe different aspects of the work; a passing result for one does not answer the other two questions.
Applies to
Civil designers select the pavement and stormwater requirements. Concrete producers, placing contractors, testing agencies, and inspectors use the construction specification to coordinate mixtures, submittals, test panels, production, and acceptance.
Before paving, identify who accepts the fresh mixture, the hardened pavement, and the stormwater system. Tie those decisions to the placement sequence in the pervious concrete installation guide so a delivery approval cannot be mistaken for acceptance of the completed lot.
Key topics
Write the report and specification as separate references
ACI SPEC-522.1-20 superseded the 2013 specification; ACI PRC-522-23 superseded the earlier pervious-concrete report. Updating one does not update the other. The specification governs construction within its scope after incorporation by the contract documents, which retain their own project provisions. Name both complete identifiers on the submittal register and establish the project-specific acceptance requirements before the first demonstration placement.
A 5,000-square-foot lot gives test records a defined area
ACI SPEC-522.1-20 defines a pavement lot as 5,000 square feet. Draw lot boundaries on the placement plan and attach the applicable production and acceptance records to those areas. A truck number identifies material delivered, while a lot identifies pavement represented by the acceptance evidence. Keep both identifiers. The 2020 specification preview provides the lot definition.
Separate fresh mixture density from hardened pavement density
ACI SPEC-522.1-20 identifies ASTM C1688/C1688M for the mixture's density-based design void content and ASTM C1754/C1754M for hardened dry density. One measures fresh pervious material under its prescribed test; the other characterizes hardened material. Label each report with the property and method instead of using density as an undifferentiated acceptance heading. Connect hardened specimens to their actual pavement location and placement date.
A material drainage range is not the site's infiltration requirement
ACI PRC-522-23 gives a general material drainage range of 2 to 18 gallons per minute per square foot, with aggregate size and mixture density influencing the result. Converted to water depth, that is approximately 193 to 1,733 inches per hour. This describes flow through the pervious material, not a guaranteed rate through the complete pavement, reservoir, and underlying soil. Use the civil design's infiltration criterion for site acceptance rather than the report's material range.
How it is used in the field
An acceptance register should distinguish mixture approval, demonstration work, production tests, hardened pavement results, and the civil system's drainage acceptance. Assign a responsible reviewer to each. A producer's mixture approval establishes what is to be delivered; it does not close the testing agency's pavement record or the civil designer's stormwater handoff.
A 100-by-150-foot parking area contains 15,000 square feet, equivalent to three 5,000-square-foot lots under ACI 522.1-20. Assign lot IDs on the placement plan before paving. Where one lot contains concrete from two placement days, keep both dates and their truck records attached to it; where one delivery crosses a lot boundary, identify both locations. The area designation and material-delivery trail serve different purposes.
When a result is disputed, first establish which property failed and which pavement it represents. An infiltration result, a fresh density report, and a dry core density answer different questions. Match any resampling or corrective work to the affected lot and retain its original result so the disposition remains traceable.
Complete the handoff with a clean pavement map, approved deviations, the drainage acceptance record, and the owner's maintenance requirements. The permeable pavement overview explains the surface and reservoir as a combined stormwater asset; the construction specification supplies the pervious-concrete portion of that record.
Edition history
ACI published SPEC-522.1-20 in November 2020 after its May 15, 2020 effective date. PRC-522-23 followed in June 2023. The Committee 522 publication register lists both as the current report-and-specification pairing.
Adoption
ACI 522.1 becomes a construction requirement through the project specification. The local stormwater approval establishes the site's runoff and drainage obligations. Neither the report's material ranges nor a general reference to pervious concrete establishes the site's permit acceptance number.
Site-paving contractors tracking additions to their territory use PorchRocket Asset Search for scheduled monitoring of visible parking areas, with dated changes and the owner of record attached to each find.
Frequently asked questions
Is ACI 522.1-13 still the latest specification?
ACI lists SPEC-522.1-20 as its construction specification. Retain a 2013 reference where that is the contract basis, and identify any accepted change explicitly instead of silently substituting the newer edition.
Can one density result serve as the infiltration acceptance?
A density result characterizes the material under its named method. Drainage acceptance uses the project's specified infiltration or system-performance evidence. Give each property its own result and acceptance decision.
Sources checked
- ACI PRC-522-23: pervious-concrete report and material drainage range
- ACI PRC-522-23 public preview: publication and material properties
- ACI SPEC-522.1-20 official construction specification
- ACI SPEC-522.1-20 public preview: lots, density definitions, and contract scope
- ACI Committee 522: published report and specification register