ANVILFIELD Try FieldOS

Concrete

Pervious concrete installation field guide for concrete crews

Hit the water window, build a draining reservoir under it, place fast without troweling, then cover and cure before it ravels.

Pervious ConcreteACI 522StormwaterPermeable PavementConcrete

Direct answer

Pervious concrete is an open-graded, near-zero-fines mix with roughly 15 to 25 percent interconnected voids that lets stormwater drain straight through into the ground below. It is placed fast, compacted with a roller, never troweled, and covered for curing within about 20 minutes. Hold the water window and cure it, or it ravels. ACI 522 and the project spec control.

Key takeaways

  • Pervious concrete is an open-graded, near-zero-fines mix with roughly 15 to 25 percent interconnected voids that drains stormwater straight through.
  • Cover pervious with 6 mil or thicker plastic within about 20 minutes of placement and keep it covered, undisturbed, for at least 7 days (10 with SCMs).
  • Never trowel or bull float pervious; place fast and compact once to grade with a roller, leaving the surface open and rough.
  • Hold the water-cement ratio tight, roughly 0.27 to 0.34, and add no water at the chute; check each load with the snowball test for a metallic sheen.
  • Acceptance is fresh density per ASTM C1688 and in-place infiltration per ASTM C1701, with ACI 522 and the project spec governing.

Pervious concrete, and why it is placed nothing like a normal slab

Pervious concrete is a porous pavement that drains water straight down through the slab instead of shedding it across the surface to an inlet. It is made by leaving the sand out. Take a normal concrete mix, pull most or all of the fine aggregate, hold the water tight, and you get a near-zero-slump material that is mostly coarse stone glued together at the contact points, with open channels between the stones that run all the way through.

That one change rewrites the whole job. A standard slab is a closed, workable material you place, consolidate with a vibrator, and finish with a float and trowel to a tight, dense surface. Pervious is the opposite of all of that. You place it fast, compact it once with a roller, never trowel it, and the surface you walk away from looks open and rough by design. A finisher who reaches for a bull float out of habit closes the voids and kills the only reason the slab exists.

Two siblings to this guide cover the parts of normal flatwork that pervious deliberately throws out. The consolidation and vibration guide explains how a dense slab is worked, which is exactly what you do not do here. The curing guide explains why dense slabs need moisture protection, and pervious needs that protection more, faster, and for longer than any normal pour. Read those for the contrast. This guide is about the open-graded version, where the rules invert.

What is pervious concrete?

Pervious concrete is an open-graded mixture of portland cement, coarse aggregate, water, and admixtures, with little or no fine aggregate, engineered to hold a connected void structure that water passes through. The voids are the product. ACI 522, the family of documents covering pervious concrete, describes a void content that commonly runs about 15 to 25 percent and ranges up to roughly 35 percent depending on the mix and how it is compacted. Below about 15 percent the voids start to disconnect and it stops draining.

The drainage is the part people do not believe until they see it. A well-built pervious slab takes water at hundreds of inches per hour, far faster than any storm can deliver it, so rain disappears into the surface instead of sheeting toward a drain. The trade-off is strength. Pervious runs lower than structural concrete, commonly cited in the few-hundred to a couple-thousand psi range, because the same voids that pass water also remove the dense paste that carries load. You are trading compressive strength for permeability on purpose.

It goes by several names on drawings and specs: pervious concrete, porous concrete, permeable concrete, and sometimes no-fines or enhanced-porosity concrete. Permeable interlocking pavers and porous asphalt solve the same stormwater problem with different materials, so confirm the spec is calling for cast-in-place pervious concrete and not one of its cousins before you price the crew and the mix.

Why use pervious concrete?

Pervious concrete is a stormwater tool first and a pavement second. It is specified to manage rain where it falls: water drains through the slab, into an open-graded stone reservoir below, and then infiltrates into the soil, which cuts the volume and the peak rate of runoff leaving the site. That is the whole pitch, and on a tight site it can replace or shrink a detention pond, freeing the land the pond would have eaten.

On the design side it earns its keep through the site civil and stormwater requirements. It can reduce or remove the need for a detention basin, help a project meet the runoff-reduction and water-quality targets in the stormwater permit, and contribute toward green-building credits such as the rainwater-management and heat-island categories under rating systems like LEED. The voids and the lighter surface color also run cooler than dense black pavement, which is the heat-island argument.

There is a recharge benefit too. Water that infiltrates instead of running to a pipe returns to the ground rather than being shipped off-site, which matters where groundwater recharge or reduced discharge to a stressed storm system is part of the permit. None of these benefits survive if the slab clogs or was placed wrong, so the value is real but conditional. It is conditional on the install and the maintenance, which is the rest of this guide.

The mix and the narrow water window

The water-cement ratio is tight, and it is the input that makes or breaks pervious. Industry mix-proportioning guidance, including NRMCA's, points at a w/c in the range of roughly 0.27 to 0.34 for most mixes, with the final value proven in trial batches. That is a narrow band compared with normal concrete, and there is no slump cushion to hide a bad call. The spec and the mix supplier set the target. You hold it.

Miss it in either direction and you lose the slab. Too wet and the paste runs off the stones, drains to the bottom, and seals the voids into a hard, impervious crust at the base while the top ravels loose. You can watch the paste pooling at the bottom of the wheelbarrow. Too dry and the paste never bonds the stones together, so the surface sheds aggregate the moment it sees traffic or a hose. The workable middle is small, which is why pervious lives and dies on water control at the truck.

Cement content, aggregate gradation, and admixtures all interact with that water number, and a hydration-stabilizing or extended-set admixture is common because the open mix dries out fast and you need working time. This is the supplier's design, not a field recipe. Get the mix design and the target fresh density on paper before the first truck, and do not let anyone add water at the chute to make it place easier. Adding water at the chute is the single most common way a good mix becomes a failed slab.

How do you hit the water window?

You read the paste, not a slump cone. Correctly watered pervious has a wet metallic or oily sheen on the cement paste coating the stones. The paste looks glossy and sticks the aggregate together without flowing off it. A slump test means nothing here, because the mix is near-zero slump by design, so the trade checks consistency by eye and by hand instead.

The hand check is the snowball test, sometimes called the hand-squeeze test. Pull on a glove, grab a handful, and squeeze it into a ball. Right, and it holds the shape of a snowball with that metallic sheen and stays together when you open your hand, leaving only a light film of paste on the glove. Too wet, and paste runs through your fingers and the ball slumps and glistens with free water. Too dry, and the ball crumbles apart and no sheen shows. Make the call on the first load, before the truck dumps the whole batch.

Train every person who touches the mix to do this, because the window can drift load to load with aggregate moisture and heat. The driver, the foreman, and whoever runs the chute should all be squeezing test balls. When the sheen disappears as the day warms, the answer is to talk to the supplier about the mix and the admixture dose, not to garden-hose water into the truck.

The stone reservoir under the slab

Pervious concrete is only the top of a system. Under it sits an open-graded stone reservoir, usually clean, washed, single-sized crushed stone with its own large void space, and that layer does the storage work. Water drops through the slab, fills the voids in the stone, and sits there while it soaks into the soil beneath. The depth of that reservoir is sized by the civil engineer to the design storm and the soil's infiltration rate, so it is a spec number, not a field guess.

Here is where a normal grading crew ruins the job before any concrete shows up. The subgrade under a pervious system must stay open enough to infiltrate, so you do not proof-roll and compact it to a hard, impervious pan the way you would under a standard pavement. Heavy compaction of the subgrade can seal off the very infiltration the system depends on. The reservoir stone gets placed and lightly consolidated to a stable surface without crushing it closed, and the subgrade is brought to grade with minimal compaction per the geotechnical and stormwater design.

A geotextile separation fabric is commonly placed between the reservoir stone and the native soil to keep fines from pumping up into the stone and clogging it from below, while still letting water pass. Confirm the design: some details wrap the sides, some place fabric only at the bottom or omit it where the soils suit. The reservoir, the subgrade treatment, and the fabric are engineered together. Build them to the detail, not to flatwork habit.

Will the subgrade actually drain?

The whole system assumes the soil under it accepts water, so that assumption gets tested, not hoped. A geotechnical investigation with a percolation or infiltration test on the native subgrade tells the designer how fast the soil takes water, and that rate sizes the reservoir and decides whether the site can infiltrate at all. Sandy and gravelly soils drink it. Tight clay barely moves it.

When the soil will not infiltrate fast enough, the design does not abandon pervious, it adds an underdrain. A perforated pipe is run in the stone reservoir to carry the stored water to an outlet at a controlled rate, so the slab still drains through and the reservoir still buffers the storm even though the soil below is slow. Clay sites almost always need this. The pervious surface keeps the runoff-reduction and water-quality benefit even when the soil cannot take the full volume.

Two field failures trace straight back to ignoring the subgrade. One, the crew compacts a marginal soil into an impervious pan and the reservoir fills and never drains, so the slab stands in water and fails freeze-thaw. Two, nobody verified the soil and the underdrain that the design needed never got installed. Confirm the infiltration test happened and the underdrain detail, if there is one, is in the ground before the reservoir stone covers it up.

Placement: fast and with minimal handling

Place pervious fast and touch it as little as possible. The open mix has a huge surface area exposed to air, so it stiffens and dries far quicker than a normal slab, and the clock from the truck to compaction to cover is short. Plan short hauls, keep the truck moving, and do not let loaded concrete sit waiting while someone finishes another bay. A long truck wait on a hot, breezy day can age a load past usable before it ever leaves the chute.

Discharge it close to final position and spread it with as little work as the grade allows, typically off the truck or by a placement that drops it near where it lives. This is the cleanest break from the placement and consolidation guide, which is built around working a dense mix into the forms and around the steel with a vibrator. You do not do that here. Hard internal vibration drives the paste down and closes the voids, so pervious gets none of the aggressive consolidation a structural slab wants.

And there is no troweling. None. A normal crew's instinct is to float and trowel to a closed, smooth surface, and every pass of a float or trowel seals the open texture that lets water in. The surface is supposed to look open and slightly rough when you are done. If it comes out tight and shiny, the voids are gone and so is the function. Brief the crew on this before the pour, because muscle memory is strong and a single experienced finisher can close a panel out of habit in two minutes.

Strike-off and roller compaction

Strike the concrete off slightly high above the forms, then compact it down to grade. The usual method is a vibrating or static screed to level it a defined amount above final, followed by a steel pipe roller or a roller compactor run across the surface to press the slab down to the form height. The compaction is what bonds the stones at their contact points and sets the surface, and the small overbuild gives the roller something to compact into.

Get the compaction timing and pressure from the mix supplier and the spec, because too much closes the voids and too little leaves a weak, raveling surface. Cross-rolling, running the roller in two directions, helps even it out on wider placements. A second roller pass at right angles to the first catches the high spots the first pass missed. The target is a uniform, compacted surface at grade with the void structure intact, not a polished finish.

This is not a bull float operation. Do not bull float, do not steel trowel, do not power trowel. Those tools are made to bring paste up and close the surface, which is the failure you are trying to avoid. Edging with a tool that rounds the joint slightly is fine and helps the edges resist raveling, but the broad surface gets the roller and nothing else.

Jointing while it is still plastic

Control joints in pervious are usually rolled in while the concrete is still plastic, not saw cut after it hardens. A rolling jointer, a wheel with a blade ring, is pushed across the fresh slab right after compaction to press a joint into the surface, and that joint then guides any shrinkage cracking to the line. Doing it fresh means the joint is in place before the slab can crack randomly, and it avoids the slurry and clogging that wet sawing would wash into the voids.

Joint spacing can often run wider than on a normal slab because pervious shrinks less. With little or no sand and a low water content, there is less paste to shrink, so the cracking pressure is lower and panels can be larger. The spacing is still a spec call, set by the designer and the supplier for the mix and the slab thickness, so take the dimension from the drawings rather than defaulting to standard flatwork joint spacing.

If a detail does call for saw cutting, it is usually an early-entry dry cut to avoid washing slurry into the surface, and it has to happen in a tight window before random cracking. Most crews find the rolled joint simpler and cleaner on pervious. Either way, get the joint in early, because a pervious slab that cracks before it is jointed has already told you the joint was late.

How do you cure pervious concrete?

Cover it with plastic sheeting within about 20 minutes of placement and keep it covered, undisturbed, for at least 7 days. That is the rule that decides whether the slab survives. Pervious has so much exposed surface area that it dries out fast, and if the paste at the surface dries before it gains strength, the bond between the stones never develops and the surface ravels. The cover is not optional polish work. It is the structural step.

Use polyethylene sheeting, commonly 6 mil or thicker, lapped and weighted at the edges and seams so wind does not lift it and so it actually traps the moisture against the surface. Get it down right behind the roller and the jointer, panel by panel, rather than waiting for the whole pour to finish. The curing guide for normal slabs treats 7 days of moisture protection as good practice. On pervious it is closer to a hard minimum, and mixes with supplementary cementitious materials commonly want 10 days because they gain strength more slowly.

Do not water-cure pervious like a flat slab by ponding or heavy spraying, because that can wash paste down into the voids. The plastic holds the mix's own moisture in, which is what you want. Keep traffic, including foot traffic and the next trades, off the slab for the full cure. The most expensive callback on pervious is a slab that looked fine on day two, got walked on and uncovered early, and started shedding stone by the end of the week.

Why does pervious concrete ravel?

Raveling is loose stones popping off the surface, and it is the number one failure mode in pervious concrete. You see it as aggregate working free under traffic, a gritty scatter of stones at the surface, and over time a roughening and loss of the top layer. A little surface raveling in the first weeks of a new slab is common and often settles down. Progressive raveling that keeps shedding material is a build defect.

It comes from the same short list almost every time. The paste was wrong, usually too dry to bond the stones or too wet so it drained off them. The slab was not compacted enough, so the stones never bonded at their contact points. Or, most often, the curing failed: the cover went on late, came off early, or never went on, and the surface dried before it gained strength. Cold or windy weather accelerates all three by drying the surface faster.

The reason curing gets the most blame is that the other two are usually caught at the pour and curing fails quietly after everyone leaves. A slab can place beautifully, compact clean, and still ravel a week later because the plastic blew off on night two and nobody put it back. If a finished pervious slab is shedding stone, work backward through paste, compaction, and cure, and the cure is where you will usually find it.

Clogging and maintenance

Pervious clogs over time as wind-blown sediment, leaf litter, and tracked-in soil fill the surface voids, and a clogged slab is just a rough, weak pavement that no longer drains. This is the maintenance reality the owner has to own from day one. The fix is regular cleaning that pulls the sediment back out of the voids, most effectively with a vacuum sweeper or a regenerative-air sweeper, and pressure washing to break loose and flush packed fines. Cleaning frequency depends on the site, commonly once or twice a year and more where sediment loads are high.

The biggest single thing that keeps a pervious lot draining is keeping the run-on clean. Water sheeting onto the pervious from an adjacent dirt area, an eroding landscape bed, or a construction-stage slope carries the sediment that clogs it. Direct that run-on away, stabilize the upslope, and the surface stays open far longer. Protect the slab during the rest of construction too, because the fines from later sitework will clog a fresh pervious lot fast.

Winter has its own rule: do not sand it. Sand is exactly the fine material that clogs the voids, so the snow-and-ice practice that helps a normal lot destroys a pervious one. Deicing salt is generally less of a chemical problem because the slab drains rather than ponding brine, but skip the abrasive sand entirely and use mechanical removal and approved deicers per the maintenance plan.

Testing and acceptance

Pervious is accepted on different measurements than a normal slab, because compressive strength is not the controlling property. Fresh density, or unit weight, is the workhorse acceptance test, run per ASTM C1688, which measures the density and void content of the freshly mixed pervious concrete. A common acceptance band is the fresh density within about plus or minus 5 lb per cubic foot of the target set in the mix design, checked roughly once a day or whenever the mix visibly changes. Density that drifts high usually means the voids are closing.

Infiltration rate is the in-place performance test. ASTM C1701 measures how fast water passes through the finished slab by sealing a ring to the surface, pouring a known volume of water, and timing it, with the result reported in inches per hour. It confirms the slab actually drains and is the test that catches a surface that got over-worked or partly sealed. Thickness is verified too, usually from cores or measured during placement, against the design depth.

Compressive strength cylinders are sometimes taken but are not the primary acceptance criterion, since pervious strength is variable and low by nature, and the standard cylinder methods do not capture it well. The exact tests, frequencies, and acceptance limits are spec items. Take them from the project specification and the supplier's mix design and confirm who fabricates and who witnesses each test before the pour, not after a dispute.

Cold weather and freeze-thaw

Pervious durability in a freezing climate comes down to one thing: keep the reservoir draining so the voids are not full of water when it freezes. Saturated pervious that freezes is the durability risk, because water expanding in the void structure can break the bond between the stones. A system that drains freely, with a reservoir that empties to the soil or an underdrain, holds up through freeze-thaw far better than one sitting in a bathtub of trapped water.

That puts the freeze-thaw answer back on the subgrade and the reservoir, not just the surface. If the soil is slow and there is no underdrain, the reservoir stays wet, and a wet reservoir under a hard winter is asking for damage. Some cold-region specs call for the reservoir to sit below the frost line or for additional drainage, and air entrainment in the paste is sometimes specified. These are design calls for the region, so follow the spec.

Placing in cold weather follows the same caution as any concrete: do not place on frozen subgrade, protect the fresh slab from freezing while it gains strength, and remember that the fast surface drying that drives raveling gets worse in cold, dry, windy air. The plastic cover that cures it also buys some protection, but cold pours may need insulating blankets over the plastic per the cold-weather provisions and the spec.

Where should you not use pervious concrete?

Pervious is a low-speed, light-duty pavement. It is well suited to parking stalls, overflow and auxiliary lots, sidewalks, plazas, driveways, and similar surfaces. It is not the material for highways, heavy truck traffic, loading docks, or anywhere with constant heavy wheel loads, because its strength is lower than structural concrete and its open surface is not built for that abuse. High-speed roadways are generally off the table.

Soil is the other limit. A site with tight clay and no infiltration can still use pervious with an underdrain, but if the design cannot get the water away at all, pervious is the wrong tool and a conventional system with conveyance may be the honest answer. Steep grades are tricky too, because water runs down the reservoir before it infiltrates, so sloped applications need terracing or check dams in the stone, which is a design problem to solve before committing.

Sediment-heavy environments are a poor fit unless the owner commits to the cleaning. A pervious lot next to a constant source of dirt, sand, or organic litter will clog faster than maintenance can keep up, and a clogged pervious lot has all the cost and none of the benefit. Match the application to the traffic, the soil, and the willingness to maintain it. When those line up, pervious works. When they do not, force-fitting it is how a good idea becomes a failed slab.

Contractor qualification

Pervious is a specialty placement, and the most reliable way to keep a project out of trouble is to use a crew that has actually done it. NRMCA runs a Pervious Concrete Contractor Certification program with tiered levels, from technician up through installer and craftsman, where the higher levels require passing a written exam, a performance evaluation, and documented field experience placing pervious. Many specs and many owners now require a certified installer on site for the work.

The reason is simple. The skills that make someone good at finishing a dense slab, the floating and troweling, are the exact reflexes that ruin pervious. A crew that has never placed it tends to over-water it to make it handle like normal concrete, work the surface closed, and miss the 20-minute cover window, which produces the classic clogged-base-and-raveled-top failure. Experience here is not a credential for the binder. It is the difference between a slab that drains and one that does not.

Verify it before award, not after the pour. Ask for the certification level of the people who will actually be on the slab, not just the company's, and ask for pervious projects you can go look at that are a few years old, because raveling and clogging show up with time. The supplier matters as much as the crew. Pick a ready-mix producer that has a proven pervious mix design and has delivered it before, because a good crew cannot save a mix the plant cannot make consistently.

The test panel

Place a mock-up test panel before the real pour. The point is to prove the mix and the crew together under the actual site conditions, with the same concrete, the same equipment, the same compaction method, and the same people who will do the production work. You are checking that the supplier's mix arrives in the water window, that the roller produces the right density and texture, and that the cover goes on fast enough, all before the mistake is in the finished lot.

Use the panel to run the real acceptance tests. Take a fresh density per ASTM C1688 off the mock-up load, run an infiltration test per ASTM C1701 on the cured panel, and confirm the surface texture and thickness against the spec. The panel also calibrates the crew's eye for the snowball test and the metallic sheen on this particular mix, so the production pour starts with the window already dialed in rather than discovered on the first truck.

Many specs require the test panel as the basis of acceptance, meaning the production work has to match the approved mock-up. Treat it that way even when it is not required. An hour and one load spent proving the system saves a lot you would otherwise be arguing about, or tearing out, after it ravels.

What to document

A pervious pour is defended by its record, because the failures show up weeks or months later when the question is whether it was built right. The high-value records are the ones tied to the steps that fail: the mix delivered, the water window calls, the time from placement to cover, the cure duration, and the infiltration test. Capturing the cover time matters most, because late or short curing is the leading cause of raveling and it is the hardest thing to prove after the fact.

Record it as you go, not from memory after the crew packs up. Logging the batch ticket and w/c, the snowball-test result per load, the placement and cover timestamps with photos, the roller passes, the cure removal date, and the C1688 density and C1701 infiltration results gives you a defensible chain. A field tool like FieldOS that timestamps photos and notes at the point of placement makes the 20-minute cover window and the 7-day cure auditable instead of a claim, which is exactly what gets disputed when a slab ravels.

The point is not paperwork for its own sake. It is that pervious has a handful of make-or-break steps with short clocks, and a record that shows each one was hit on time is what separates a defensible install from a he-said-she-said when the surface starts shedding stone.

StepThe pervious wayRecord this
MixTight w/c, roughly 0.27 to 0.34 per the supplierBatch ticket, w/c, mix design ID
Water windowMetallic sheen, snowball test, no water at chuteSnowball result per load, who checked
PlacementFast, minimal handling, no trowelPlacement start time, photos
CompactionStrike high, roller to grade, cross-rollRoller passes, surface texture
JointingRolled in while plastic, spec spacingJoint method and spacing
CoverPlastic within about 20 minutesCover timestamp, photos
CureCovered and undisturbed 7 days, 10 with SCMsCover-on and cover-off dates
AcceptanceDensity C1688, infiltration C1701, thicknessTest results vs. target

Common mistakes

Almost every failed pervious slab traces to a normal-concrete habit applied to a mix that punishes it. The list below is the same handful, in roughly the order they cost the most.

  • Troweling, bull floating, or otherwise working the surface so the voids close and the slab stops draining.
  • Missing the water window: too wet and the paste drains and seals the base, too dry and it never bonds and ravels.
  • Adding water at the chute to make a tight mix place easier, which blows the w/c and the void structure.
  • Failing to cover within about 20 minutes or pulling the cure short, which is the leading cause of raveling.
  • Compacting the subgrade into an impervious pan so the system cannot infiltrate and the reservoir stays full.
  • Skipping the soil infiltration test or the underdrain the clay site needed, so the slab stands in water.
  • No vacuum or pressure-wash maintenance and dirty run-on, so the surface clogs and stops draining.
  • Sanding it in winter, which packs the voids with exactly the fines that clog it.
  • Running a normal crew with no certified installer and no test panel to prove the mix and the method first.

Field checklist

0 of 12 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

ACI 522 is the home base for pervious concrete. ACI 522R, the report on pervious concrete, covers the materials, mix proportioning, placement, compaction, jointing, curing, and durability, and ACI 522.1 is the specification for pervious concrete pavement that a project can reference for construction and acceptance. Treat the report as the reasoning and the specification as the contract language, and let the project's own stormwater spec override either where it is stricter.

The acceptance tests are ASTM methods. ASTM C1688 measures the density and void content of freshly mixed pervious concrete, which is the common fresh-property acceptance test, and ASTM C1701 measures the in-place infiltration rate of the finished pavement in inches per hour. NRMCA publishes mix-proportioning guidance and runs the Pervious Concrete Contractor Certification program, which is the credential many specs require for the placing crew.

The water-cement ratio range, the target void content and fresh density, the joint spacing, the cure duration, and the acceptance limits are all values to confirm against ACI 522, the project specification, and the mix supplier's design rather than carrying as fixed numbers from any guide. The numbers in this guide are common industry figures to orient the crew. The spec and the supplier set the ones you build to.

Units, terms, and conversions

Pervious shows up under several names and a few unit systems across a drawing set, a spec, and a supplier's mix sheet, so the same property can read differently from page to page.

Pervious concrete is also called porous concrete, permeable concrete, or no-fines concrete. Void content is given as a percent of total volume. Fresh density, or unit weight, is in pounds per cubic foot in US specs and kilograms per cubic meter in metric, with a common acceptance band of plus or minus 5 lb per cubic foot. Infiltration rate is in inches per hour in US practice and millimeters per hour in metric. Water-cement ratio, w/c or w/cm when supplementary cementitious materials are included, is a unitless weight ratio of water to cementitious material.

Pervious concrete
Open-graded, near-zero-fines concrete with interconnected voids that water drains through; also porous or permeable concrete
Void content
The percent of the volume that is connected air space, commonly about 15 to 25 percent, that carries the water
Water-cement ratio (w/c, w/cm)
Weight of water to cementitious material, tight in pervious at roughly 0.27 to 0.34 per the mix design
Stone reservoir
Open-graded crushed-stone layer under the slab that stores water while it infiltrates into the soil
Raveling
Loose aggregate shedding from the surface, the leading pervious failure, from bad paste, low compaction, or poor curing
Infiltration rate
How fast water passes through the in-place slab, measured per ASTM C1701 in inches per hour
Fresh density
Unit weight of the fresh mix, measured per ASTM C1688, the common acceptance check against the mix-design target

Related tools

Calculators and readiness checks for this work

Compare your options

FAQ

What is pervious concrete?

Pervious concrete is an open-graded mix of cement, coarse aggregate, water, and admixtures with little or no sand, leaving roughly 15 to 25 percent interconnected voids that water drains straight through. It is used for parking, walks, and stormwater credit. Strength is lower than normal concrete because the voids replace dense paste.

How do you cure pervious concrete?

Cover pervious concrete with 6 mil or thicker plastic sheeting within about 20 minutes of placement and keep it covered, undisturbed, for at least 7 days, or 10 days for mixes with supplementary cementitious materials. The open surface dries fast, and if the paste dries before it bonds, the surface ravels. Confirm the cure with the spec.

Why does pervious concrete ravel?

Pervious concrete ravels, shedding loose stones from the surface, mainly from failed curing: the plastic cover went on late, came off early, or never went on, so the paste dried before it bonded the stones. Wrong water content and too little roller compaction cause it too. Curing is the most common culprit because it fails after the crew leaves.

Can you trowel pervious concrete?

No. Troweling, bull floating, or power floating pervious concrete presses paste to the surface and closes the voids, which destroys the drainage the slab exists for. Place it fast, compact it once to grade with a roller, and leave the surface open and slightly rough. A finisher closing it by habit is a common cause of a sealed slab.

How fast does water drain through pervious concrete?

A properly built pervious slab drains at hundreds of inches per hour, far faster than any storm delivers rain, so water soaks in instead of sheeting to a drain. The in-place rate is verified with ASTM C1701, in inches per hour. A slab draining far below target is over-worked, clogged, or was placed too wet and sealed at the base.

What water-cement ratio is used for pervious concrete?

Pervious concrete uses a tight water-cement ratio, commonly in the range of about 0.27 to 0.34 per industry mix-proportioning guidance, with the final value proven in trial batches. Too wet and the paste drains off and seals the voids; too dry and it never bonds. The mix supplier and the project spec set the target, not the field.

Do you compact the subgrade under pervious concrete?

Not the way you would under a normal pavement. The subgrade under pervious must stay open enough to infiltrate, so heavy compaction that seals it into an impervious pan defeats the system. Bring it to grade with minimal compaction per the geotechnical design, and add an underdrain where clay or slow soils cannot accept the water fast enough.

How is pervious concrete maintained?

Keep pervious draining by vacuum sweeping or regenerative-air sweeping and pressure washing periodically, commonly once or twice a year, to pull sediment out of the voids. Keep dirty run-on off the surface, since that is what clogs it. Do not sand it in winter, because sand packs the voids with exactly the fines that block drainage.

Where should pervious concrete not be used?

Avoid pervious concrete for highways, heavy truck traffic, loading docks, and high-speed roadways, because its strength is lower than structural concrete and the open surface is not built for heavy wheel loads. Clay sites need an underdrain, steep grades need terracing, and sediment-heavy sites only work if the owner commits to regular cleaning.

Should pervious concrete be saw cut or rolled for joints?

Control joints in pervious concrete are usually rolled in with a rolling jointer while the slab is still plastic, right after compaction, rather than saw cut after it hardens. Rolling avoids the slurry that wet sawing would wash into the voids and places the joint before random cracking. Spacing can run wider than normal slabs because pervious shrinks less.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.