Fresh density

Fresh density reports concrete mass per calibrated container volume under the test's consolidation conditions. A net sample mass of 29.5 lb in a 0.25 ft3 measure gives 118.0 lb/ft3. Preserve both inputs, the tare, and the procedure designation: they let a reviewer distinguish a changed mixture from a weighing or consolidation difference. For lightweight concrete, the fresh result also needs the mixture's established relationship to its specified equilibrium density.

Unit weight of the fresh mix, measured per ASTM C1688, the common acceptance check against the mix-design target

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Which density method belongs on the delivery record?

The current methods are ASTM C138/C138M-24a for fresh concrete density and yield, and ASTM C1688/C1688M-26 for fresh pervious concrete density and void content. Identify the method before comparing loads. A result generated with different consolidation cannot be treated as a shift in mixture proportions until the test basis has been reconciled.

ASTM C1688/C1688M-26 limits its applicability to pervious mixtures with nominal maximum coarse aggregate of 25 mm [1 in.] or smaller. It also states that Procedure A and Procedure B results are comparable only when the same procedure is used. Put the procedure letter on the report beside the mixture identifier and measured density.

A tare error that moves the reported result

For a calibrated 0.25 ft3 measure, 29.5 lb of net fresh concrete gives 118.0 lb/ft3: net mass divided by container volume. An unnoticed 0.20 lb contribution from residue or an incorrect tare raises the reported density by 0.8 lb/ft3. That consumes more than a quarter of NRMCA's typical 3 lb/ft3 lightweight tolerance before the concrete itself has changed.

Keep the empty measure mass, filled mass, calibrated volume, and net calculation together. A rounded density alone prevents the reviewer from separating a weighing error from a real change in the load.

Calculate batch yield from a conventional density test

ASTM C138/C138M-24a defines yield from known batch quantities and measured fresh density. A batch mass of 39,150 lb divided by a measured density of 145 lb/ft3 gives 270 ft3, or 10.00 yd3. At 150 lb/ft3, that same recorded batch mass gives 261 ft3, or 9.67 yd3. The density difference changes the calculated volume by 0.33 yd3.

Keep the batch mass used in that calculation with the density record. Form dimensions, placement losses, and quantity ordered answer different questions from batch yield. This C138 calculation does not extend to pervious concrete: C1688 expressly excludes using its result to determine yield.

How much density does lightweight concrete lose?

NRMCA CIP 36 reports that structural lightweight concrete's equilibrium density is commonly 3 to 8 lb/ft3 below its fresh density. NRMCA CIP 36 identifies a typical fresh-density acceptance tolerance of ±3 lb/ft3 from the target. Use the mixture's established fresh-to-equilibrium relationship when setting that target, rather than subtracting the same allowance from every lightweight mixture.

ASTM C567/C567M-19 places equilibrium density approximately 3 lb/ft3 above oven-dry density. A fresh result of 118 lb/ft3 and an established 6 lb/ft3 fresh-to-equilibrium reduction predict 112 lb/ft3 at equilibrium, rather than 109 lb/ft3. The latter would subtract the separate oven-dry allowance again. Label the moisture endpoint in a lightweight concrete submittal so that these two adjustments cannot be combined inadvertently.

What a pervious cup cannot say about the slab

ASTM C1688/C1688M-26 explicitly excludes using its results to determine in-place void content or yield. The standard consolidation in the test measure characterizes the delivered material; the placement equipment determines how that material is compacted into pavement. Keep fresh-test comparisons within the same procedure and approved mixture.

Attach the fresh result to the load identifier and the finished pavement's infiltration result to its test location in the pervious pavement record. This keeps a delivery measurement from being presented as a test of connected flow paths through the completed slab.

Distinctions

Infiltration rate
Water passing through a pavement is a flow measurement. Fresh density measures the compacted contents of a test container.
Equilibrium density
This is a defined moisture condition used for structural lightweight concrete, not a fresh delivery measurement or an oven-dry result.

Frequently asked questions

Can I compare pervious results from two laboratories?

Compare their method editions, Procedure A or B designation, mixture identification, and recorded values first. C1688-26 requires the same procedure for comparable results; identical units alone are insufficient.

Sources checked

Also defined as

  • Unit weight of the plastic concrete, the primary field QC test for lightweight, per ASTM C138

Where this shows up

Next step: Build a pavement list

Back to the full field glossary