Direct answer

A blocked cold plate becomes more likely when its pressure drop rises at the same coolant flow and its GPU runs hotter at matched inlet temperature and power. With manifold differential pressure held constant, the warning can instead be falling branch flow while pressure stays steady. Compare the branch with its clean baseline, separate the plate from hoses and quick disconnects, and check GPU thermal slowdown before deciding whether the fault is flow restriction or poor thermal contact.

On this pageIs the cold plate blocked, or is the GPU simply hot?What must you measure before touching the branch?How do you build and compare branch resistance curves?Is the restriction in the plate, hose, valve or quick disconnect?How do you calculate cold plate thermal resistance?Does the GPU telemetry show thermal throttling?How do you tell a contact fault from a flow fault?What should the contamination register record?Should you clean the plate or replace it?How do you retest the replacement cold plate?What belongs in the service scope and cost estimate?Field checklist and closeout record
Need to run this in the field?

Open the related tool for the calculation, checklist, or packet.

HydroTest DCPressure-test package math, hold timing, thermal drift verdicts, witness signatures, and PDF/CSV records.

Is the cold plate blocked, or is the GPU simply hot?

A hydraulic restriction changes the pressure-flow relationship; GPU temperature supplies its thermal consequence. Match inlet temperature and workload power to separate warmer supply, increased load and deteriorated contact from a flow fault.

In Anvilfield's interpretation of OCP Cold Plate Cooling Loop Requirements Rev 2, added branch resistance raises pressure drop at fixed flow and reduces branch flow at fixed manifold differential pressure. Use this hydraulic relationship to interpret measurements; the installed assembly's accepted envelope sets its limits.

This investigation covers pumped, single-phase water and inhibited water-glycol systems. Identify series versus parallel paths using the direct-to-chip architecture guide: series plates share flow; parallel passages can conceal maldistribution. Two-phase and passive loop-heat-pipe assemblies require different models.

Why normal manifold pressure does not clear a branch

A common-header pressure controller can maintain its setpoint while one restricted branch loses flow. Total CDU flow can conceal that loss, as the shared-manifold discussion in OCP Loop Requirements Rev 2, section 8, explains. At fixed pump speed, both pressure and flow can move with the network operating point; record the actual control mode.

Raising pump speed until an alarm clears does not establish recovery. Retest against the accepted pressure budget and the unaffected branches' operating limits.

What must you measure before touching the branch?

Map CDU supply, row supply, supply quick disconnect, hose, plate or series plates, return connector and row return. Locate pressure taps, branch flowmeter, inlet/outlet probes and GPU UUID together. Retrieve the CDU manifold baseline from CDU commissioning.

Record fluid product, batch, concentration and temperature, component revisions, flow direction, valve positions and pump control mode. Use a calibrated local meter within its supported tube/fluid/range combination, a suitably ranged differential-pressure sensor and matched temperature sensors. Purge sensing lines, check zero and tap elevation, and retain installation and calibration effects in the measurement uncertainty record.

Table 1. Measurement boundary and retained readings. Selected values belong to the worked calculations.
MeasurementBoundary/unitFilled example or required identifierWhat it resolvesBasis
Available branch pressureSupply-to-return header taps, kPaSelected 20.00 kPaDriving pressure and controller behaviorOCP Loop Rev 2; selected input
Branch differential pressureSame header boundary, kPaSelected 20.00 kPa while flow fallsTotal assembly resistance at operating pointOCP Loop Rev 2/OCP qualification paper
Branch flowFlow through named branch, L/minCalculated 1.00 clean, 0.71 restrictedLocal starvation hidden in total flowTable 2
Plate differential pressurePlate ports or baseline-subtracted bench fixture, kPaSelected 14.00 clean, 34.00 suspect at 1.00 L/minComponent localizationOCP qualification paper; Table 3
Local inlet temperaturePlate coolant inlet, °CSelected 35.0Thermal referenceOCP qualification paper
GPU temperatureSame GPU sensor/UUID, °CSelected 65.0 clean, 80.0 suspectApparent thermal changeNVIDIA nvidia-smi/NVIDIA DCGM 3.0; Table 5
GPU powerSame supported board/device field, WSelected 500 in both statesSeparates loading from coolingNVIDIA nvidia-smi/NVIDIA DCGM 3.0; Table 5
Filter differential pressureAcross named filter, kPaActual value and supplier dirty-filter limit requiredCommon supply restrictionVertiv Rev A 2025
Event recordTimestamp, workload, driver and protective limitsNative values and version strings requiredThermal versus power throttlingNVIDIA nvidia-smi/NVIDIA DCGM 3.0

How long should the test run?

Plan a five-minute stable analysis window at each point after temperatures settle, with one-second synchronized records where supported: these are Anvilfield-selected test settings. OCP's qualification white paper, section 1.3.2.1, requires constant processor power until case and inlet temperatures stabilize, rather than a prescribed fixed dwell. Allow stabilization time in addition to the recording window.

For this worked protocol, Anvilfield selects inlet-temperature span no greater than 0.5 °C, power within ±2% of target and no monotonic thermal rise across five minutes. Stop a load ramp at the actual equipment limit or approved protective stop, whichever comes first. Retain each signal's update rate, averaging period and timestamp offset: one-second polling does not create fresh one-second data from a slower sensor. Resolve stale values with the telemetry calibration procedure.

How do you build and compare branch resistance curves?

Measure several approved flows at matched fluid conditions, retaining pressure readings, repeatability and fit residuals. Plot clean, suspect and replacement points together: OCP Loop Requirements Rev 2 calls for pressure-flow and thermal-resistance-flow data, and the qualification white paper tests multiple flows.

Table 2. Anvilfield estimates: matched-fluid quadratic curves, clean/replacement K = 20 and restricted K = 40 kPa/(L/min)².
Flow, L/minClean branch Δp, kPaRestricted branch Δp, kPaReplacement target Δp, kPaInterpretation
0.505.0010.005.00Same flow, twice the selected resistance
0.7511.2522.5011.25Intermediate comparison point
1.0020.0040.0020.00Selected reference flow
At 20 kPa available1.00 L/min0.71 L/min1.00 L/minConstant-pressure operating points, not a fourth flow sweep point

Method note: Anvilfield estimates pressure by multiplying the selected resistance coefficient by flow squared: Δp = Kq². Divide measured pressure drop by squared flow to compare this model's coefficient. At 20 kPa, take the square root of 20/K for the operating flow. The restricted operating flow is 29% below the clean value.

Keep the diagnostic pressure boundary identical. Place any temporary flow-control valve outside those taps or subtract its independently characterized loss; otherwise its changing position manufactures a false curve. Real curves can contain linear and quadratic terms: OCP Universal Quick Disconnect Specification v2.0.0 (September 22, 2026), section 9.1.4, uses a best-fit relationship Δp(Q) = AQ² + BQ. A quadratic-only fit should stay within its demonstrated fluid and flow range.

What changes when the coolant temperature or glycol concentration changes?

OCP's qualification white paper, section 1.2.1.3, shows temperature-dependent flow for 25% propylene glycol. Use the exact supplier's matched-fluid curve or a measured baseline at the same temperature; a water-only connector coefficient needs the alternative-fluid correction or test data addressed by OCP UQD v2.0.0, footnote 7.

What if there is no branch flowmeter or clean baseline?

Obtain local flow with a qualified meter or characterized bench; estimating flow from the old curve assumes the restriction away. Without a commissioning curve, use an exact supplier curve or accepted identical assembly, retaining configuration and uncertainty. Otherwise report suspected restriction and proceed to component testing. Pressure ratios cannot reveal percentage of channels blocked.

Is the restriction in the plate, hose, valve or quick disconnect?

Inspect kinks, valve position, flow direction, connector seating and both QD halves against the approved assembly. A familiar UQD size does not establish its coefficient; use the QD selection guide for interface and pressure-budget selection.

OCP's undated Cold Plate Development and Qualification white paper, section 1.3.2.2, determines plate pressure drop by subtracting bypass-loop loss from plate-installed-loop loss at the same flow. Apply that bench method through approved service access and a clean characterized fixture. Re-characterize ancillary loss whenever hose, valve, connector or bypass geometry changes.

Table 3. Anvilfield estimates at 1 L/min, identical fluid, temperature and pressure boundary.
ConfigurationTotal Δp, kPaReference fixture/ancillary loss, kPaCalculated plate contribution, kPaDecision
Clean plate installed20614Retained clean component reference
Suspect plate installed40634Additional loss follows the plate in this test
Replacement installed20614Matched hydraulic recovery
QD fault test branch402614Additional loss is outside the plate

The QD-fault row settles an expensive ambiguity: high branch loss can coexist with a normal plate contribution. Pressure-integrity testing answers a separate question. A connector's working or burst pressure is neither a blockage threshold nor authorization to pressure-test an installed GPU assembly at that value.

Worked manufacturer check: how much loss can the connectors add?

Anvilfield estimates connector loss from the minimum Cv values published in Gates UQD specification sheet (©2025): 0.54 for UQD02 and 1.53 for UQD04. Select water at specific gravity 1.00 and flow 1.00 L/min. Following OCP UQD v2.0.0's coefficient method, divide flow in US gpm by Cv, square the result and multiply by specific gravity to obtain psi.

Table 4. Anvilfield estimates using Gates ©2025 minimum Cv values and OCP UQD v2.0.0; selected water flow 1 L/min, specific gravity 1.
ItemGates UQD02Gates UQD04Basis
Published minimum Cv0.541.53Gates 2025, p.1
Selected water flow, L/min1.001.00Anvilfield calculation input
Calculation flow, US gpm0.260.26US gallon-to-liter conversion
Drop per connected set, psi0.240.03SG × (Q/Cv)², OCP UQD v2.0.0
Drop per connected set, kPa1.650.21Psi-to-kPa conversion
Supply plus return, two connected sets, kPa3.300.41Twice individual calculated loss
Approximate loss ratio8 times UQD04ReferenceSquared Cv ratio, before rounding

Method note: hold published minimum Cv constant at the selected flow; use 3.785411784 L per US gallon and 6.894757 kPa per psi, then round results. Two connected sets mean complete mated supply and return paths. Verify actual curves for low-flow/viscous-fluid service. Use the supplied connector revision for its compliance record.

How do you calculate cold plate thermal resistance?

Subtract plate inlet temperature from component case temperature, then divide by applied component power at a stated stabilized flow. OCP's undated qualification white paper, section 1.3.2.1, defines R = (Tc − Tin)/P, in °C/W, for the assembly mounted with its recommended TIM2 thermal-interface material. That case-to-inlet result includes the specified interface.

Preserve the measurement endpoints. Boyd Hi-Contact datasheet BC 06.2022 plots mounting-surface-to-inlet-water resistance, while Boyd Liquid Cooled Cold Plates datasheet (©2020) gives 0.02 °C/W as a typical product-family value. Neither is a universal GPU acceptance limit. In series paths, use the plate's local inlet; rack supply temperature can miss heat added by upstream processors.

What can GPU telemetry tell you about thermal resistance?

Call a ratio using GPU sensor temperature and reported GPU/board power apparent GPU-to-inlet resistance. Its boundary includes package, interface, spreading, plate and coolant effects. Preserve the exact power-field definition: reported board power is different from module power, memory-subsystem power and applied heater power. TDP is not a measured denominator.

Table 5. Anvilfield estimates: selected GPU sensor and board-power inputs for a constant-pressure branch.
StateBranch Δp, kPaCalculated flow, L/minSelected inlet, °CSelected GPU, °CSelected reported power, WGPU rise above inlet, KApparent resistance, K/kWInterpretation
Clean baseline201.0035655003060Reference assembly
Restricted branch200.7135805004590Hydraulic restriction plus higher apparent thermal resistance
Replacement calculation201.0035655003060Recovery at matched load and inlet
Contact-fault comparison201.0035805004590Same apparent thermal degradation without changed bulk hydraulics
Warmer-supply comparison201.0040705003060GPU temperature rises but apparent resistance is unchanged

Anvilfield estimates an apparent GPU-to-inlet resistance of 60 K/kW for a selected 65 °C GPU, 35 °C inlet and 500 W reported board power, rising to 90 K/kW when the GPU reaches 80 °C at the same inlet temperature and power. Divide the temperature difference by power in kW to reproduce the 50% increase. Kelvin and Celsius temperature differences are numerically equal.

Method note: Anvilfield estimates uncertainty using NIST Technical Note 1297 (1994), with selected independent standard uncertainties of 0.5 K for GPU temperature, 0.2 K for inlet and 10 W for power. Root-sum-square propagation gives standard uncertainties of 1.61 and 2.10 K/kW; selected coverage factor k = 2 gives expanded uncertainties of 3.22 and 4.20 K/kW. Use actual sensor uncertainty, repeatability and covariance for acceptance; the selected inputs are not NVIDIA accuracy specifications.

Thermal slowdown can reduce power enough to hide deterioration behind a temperature plateau. Compare a controlled lower load both assemblies sustain or the same pre-slowdown interval, with workload throughput retained.

Does coolant temperature rise prove a blockage?

Coolant temperature rise reflects heat pickup relative to mass flow. At steady conditions, multiply coolant mass flow by fluid-specific heat and outlet-minus-inlet temperature to calculate heat carried across that boundary, using supplier properties at measured concentration and temperature. OCP Loop Requirements Rev 2 describes heat split and fluid-property boundaries. Greater rise can follow less flow or more heat; throttling can reduce both power and rise. Board power is not automatically the heat reaching one plate's coolant.

Does the GPU telemetry show thermal throttling?

Capture UUID, model, driver, utilization, SM/memory clocks, measured power and enforced limit, supported temperatures, throughput, event reasons and thermal limits. Tie readings to the physical plate; clock reduction alone does not identify a cooling fault.

NVIDIA's nvidia-smi documentation (live edition checked November 5, 2026) distinguishes SW Thermal Slowdown and HW Thermal Slowdown from SW Power Capping and HW Power Brake. HW Slowdown alone combines thermal and power-brake causes. Use supported GPU Max Operating Temp and Slowdown Temp values from the actual device; a blanket 80 °C or 85 °C threshold would misstate model-specific behavior. N/A means unavailable evidence.

NVIDIA DCGM 3.0 Field Identifiers defines DCGM_FI_DEV_THERMAL_VIOLATION as thermal violation time in microseconds. Plot its increment over the test interval, preserving collector units and marking resets or restarts as discontinuities. An unavailable counter is not a zero-event interval.

How do you capture the GPU evidence?

Verify query fields with the installed driver's help, then replace GPU-UUID with the affected physical UUID for this read-only capture.

nvidia-smi -L
nvidia-smi --help-query-gpu
nvidia-smi -i GPU-UUID -q -x > gpu-before.xml
nvidia-smi -i GPU-UUID --query-gpu=timestamp,uuid,temperature.gpu,power.draw,clocks.sm,utilization.gpu --format=csv -l 1 > gpu-trend.csv

Stop recording after the window and capture gpu-after.xml with the same full query. Add supported events/counters and memory temperatures from DCGM/NVML or the collector; retain software versions and power-field definition. NVIDIA defines Average Power Draw as preceding-second board power on Ampere (except GA100) or newer devices. Record whether the selected field is averaged or instantaneous, and align hydraulic averages to that interval.

Align the hydraulics and workload on one timeline

Plot hydraulics, temperatures, power/throughput and thermal events on synchronized axes. Annotate workload/pump/service changes and averaging periods. Use the GPU burn-in workload guidance for repeatable loading. A neighbor is a valid comparison only when hardware, firmware, workload, series order and supply conditions match.

How do you tell a contact fault from a flow fault?

Resolve mapping and uncertainty, then use the matrix to separate hydraulic restriction from contact, deposits and maldistribution.

Table 6. Anvilfield diagnostic synthesis: patterns direct the next test; component evidence establishes location.
Suspected causeMatched-flow pressure curveOperating branch flowGPU-to-inlet rise at matched powerOther discriminating evidenceNext test
Plate hydraulic restrictionPlate contribution risesFalls under constant header ΔpOften risesExtra loss follows plate on a characterized benchPlate/bypass comparison; retain removed part
Kinked hose, valve or QD restrictionBranch rises; plate-only can remain normalFalls at fixed header ΔpOften risesLocalized ancillary loss, wrong routing or connectionCharacterize/substitute affected ancillary component
Poor TIM/contact/mountBulk hydraulic curve can remain normalNormal for accepted boundaryRisesMount/interface deviation or localized thermal patternApproved mount/TIM inspection and matched retest
Partial internal channel blockage/maldistributionSmall or unresolved bulk changeCan stay near baselineCan rise locallyHot region at matched bulk flow; plate examinationCompare matched-flow thermal behavior, then approved internal examination
Insulating deposit with little channel closureBulk curve can remain near baselineNear baselineRisesDeposit/analysis and wetted-material historySupplier examination and supported deposit analysis
Warmer supply or series inletCurve comparable after property matchingCan remain normalCan remain normal although GPU is hotterLocal inlet rise explains sensor changeCorrect boundary and check CDU/preceding plate load
Gas or unstable circulationVariable/nonrepeatableVariable or intermittentVariableChanges after approved de-air procedureDe-air and repeat stabilized comparison
Common filter/pump/supply faultIndividual plate curve can remain normalSeveral branches fallSeveral riseSupply/filter Δp, pump state or header pressure changesInvestigate shared loop and controls
Power cap, external power brake or low workloadNo necessary changeNo necessary changeNo necessary riseNVIDIA event reason and power/throughput changeCorrect workload/power diagnosis before mechanical service

Normal bulk flow does not establish clean heat-transfer surfaces. A thin insulating deposit can degrade heat transfer before its hydraulic effect is measurable. Partial closure of parallel microchannels can redirect flow away from a hot region while total branch flow remains near baseline. Compare matched-flow thermal behavior, then use approved component examination to distinguish those paths from mounting loss.

State the narrowest supported finding. “Branch restriction” follows a changed assembly curve; “restriction localized to the plate” requires component evidence. “Particle blockage confirmed” needs recovered particles, inspection or supplier analysis. A temperature correlation alone cannot identify the obstructing material.

Where does trapped gas fit?

OCP's qualification white paper requires a bubble-free loop before thermal testing. De-air under the loop commissioning procedure, then repeat the stable comparison. Persistent hydraulic penalty after correct de-airing keeps solid restriction in the investigation. Intermittent behavior alone does not distinguish gas, debris or cavitation; record the response to the approved procedure.

What should the contamination register record?

Preserve the as-found condition before flushing or teardown redistributes the evidence. Link fluid and deposit samples, removed filters and the plate serial number to the same incident. Photograph recovered material before alteration; use “not analyzed” where composition is unknown. Dark deposits require analysis before being called copper oxide, scale or biofilm.

Table 7. Contamination decision register: enter actual sample results and retain the listed evidence.
Register categoryRetain/measureFilled interpretation ruleLaboratory or document evidenceDisposition
Construction debrisFilter patch and recovered particles; size distributionRestriction after installation warrants source tracingParticle microscopy/composition, flush recordsCorrect cleanliness before reconnecting IT
Corrosion productsFluid and solid fractions; dissolved metalsMetal rise alone does not identify the blocked componentTargeted metals/ion analysis and surface examinationTrace wetted alloys, inhibitor state and damage
Scale/precipitateDeposit and coolant; hardness/ions as appropriateAppearance alone does not identify mineral compositionDeposit chemistry and coolant product historyResolve incompatible makeup, dosing or contamination
Biological materialMatrix-appropriate sample and chain of custodyCloudiness or slime needs microbiological confirmationMethod, handling time and matrix suitabilitySupplier-approved remediation and repeat verification
Polymer/sealant materialPart lot, recovered fragments, assembly consumablesFragments following service warrant material tracingMicroscopy/chemical identification and BOMCorrect source and approved sealing method
Fluid mixing/degradationDelivery/batch samples, concentration, pH, inhibitor and acidsAbnormal trend triggers product-specific analysisMatched product/batch data and qualified lab reportResolve fluid identity before treatment
Removed plateSerial, revision, capped ports, as-found photographsPreserve pre-cleaning conditionSupplier inspection and hydraulic/thermal reportsSeparate mechanism finding from restored operation

For every entry record incident/time, loop/branch/GPU, fluid/batch/concentration, source location, sample/filter/part ID, collection procedure/organization, lab-specified handling, chain of custody, method/revision, result/units, product limit, report ID, corrective action and retest link.

OCP's PG guideline Rev 2.0/Version 1.0.0, section 11.2, calls for a representative well-mixed circulating-fluid sample and discarding stagnant sampling-port fluid before collection. Label deliberate low-point or deposit samples separately: they answer different questions from circulating-fluid health. Select microscopy, elemental/chemical analysis or matrix-suitable microbiology to resolve the suspected material.

Correct the contamination source before reconnecting the replacement. Vertiv Guidelines for Deployment of Single Phase Technology Cooling System, SL-80056_REVA_02-25 (©2025), sections 6.1 and 6.4, addresses cleaning third-party equipment and establishing cleanliness before IT connection. Connect findings to coolant chemistry and treatment and wetted-material/leachables qualification.

Which filtration and chemistry numbers actually apply?

Vertiv SL-80056_REVA_02-25, section 6.4, specifies strainer rating at 10% to 50% of the narrowest channel and describes full-flow filtration typically at 25% to 40%. For a selected 100 µm channel, Anvilfield estimates 10 to 50 µm and 25 to 40 µm respectively by multiplying channel width by those fractions. Record nominal/absolute efficiency, location and clean/dirty pressure loss alongside the micron rating.

OCP Guidelines for Using Water-Based Transfer Fluids (undated final edition) recommends side-stream filtration below 5 µm and describes component-approved inline examples such as 50 µm. Distinct locations and duties explain those different values.

Table 8. Source-specific qualification, chemistry and product ratings.
Authority / editionValue or methodApplication
OCP UQD v2.0.0, Sept. 2026Water 25 ±5 °C; ≥6 flows spanning 25% to 150% rated, including 100%; averages n≥5Qualification, not installed-branch test instruction
OCP water, undated final; OCP PG Rev 2.0/Version 1.0.0, Sept. 2026Water pH 8.0 to 10.5; PG new fluid: non-OAT 8.0 to 10.5, OAT 7.0 to 10.5; PG in service: IAT 8.0 to 10.5, OAT/hybrid 6.5 to 9.5OCP PG Table 1 versus Table 14; actual fluid supplier limits govern
Gates ©202520 bar working maximum; -40 to 120 °C; UQD02 minimum Cv 0.54Installed assembly envelope governs
Danfoss AI423953312825en-000106, Sept. 2026Assembly 5 to 65 °C; connected UQD02/04/06: 20/16/6.9 bar; UQD08: 8.9 bar connected, 6.9 bar individual halvesPreserve size/state; seal temperature is not assembly rating

OCP PG Rev 2.0/Version 1.0.0 gives new-fluid pH in Table 1 and different in-service OAT/hybrid guidance in Table 14. OAT means organic acid technology; IAT means inorganic acid technology. Use the fluid supplier's maintenance range for the installed formulation when judging a circulating sample.

Resolve incompatible instructions for the exact assembly and coolant. Choosing the numerically narrower pH range or a stronger cleaner without checking inhibitor chemistry does not establish compatibility. Use the approved product program rather than applying an untreated-DI-water conductivity target to inhibited operational coolant.

Should you clean the plate or replace it?

Replace an assembly that leaks, is sealed and non-serviceable, or cannot be restored by approved cleaning to accepted hydraulic and thermal performance. This is Anvilfield's service decision logic; the purchased assembly's manual determines serviceability. Preserve samples and the removed part before cleaning changes the evidence.

Remove the affected assembly from load under its approved service procedure when flow, leakage, thermal limits or protective alarms require it. Use the concurrent-maintenance isolation plan to preserve cooling service and retain leak detection and intervention results.

Vertiv's 2025 deployment guide, section 6.1, restricts chemical cleaners/detergents except with new-fluid-supplier guidance; OCP's PG guideline, section 10, describes controlled cleaning and rinsing. Resolve one compatible component/fluid procedure before work. A diagnosis does not supply a generic acid dose, backflush pressure or ultrasonic duty.

Vertiv Rev A, section 1, requires de-energized maintenance and safe component temperatures. For servicing covered by OSHA 29 CFR 1910.147(d)(5) and (d)(6), checked November 5, 2026, control stored energy and verify isolation before work. Use the assembly procedure to isolate cooling and relieve trapped hydraulic pressure before opening it.

OCP UQD v2.0.0, section 9.1.5, calls for progressive filling and draining within ratings to prevent seal washout.

Record failed and replacement serials, revisions, lots, connector changes, mounting hardware and interface materials. Use the processor/assembly specification for torque and compression. The OEM acceptance and responsibility guide defines supported configuration and service authority.

How do you retest the replacement cold plate?

Repeat the accepted pressure boundary and flow points with the same fluid product, concentration and temperature, inlet reference, power definition, workload and firmware. Complete approved leak checks and de-airing before loading. Retest once at accepted header pressure to prove restored service, and again at matched flow/power to separate remaining thermal degradation from reduced-flow effects.

Tables 2 and 5 return from 0.71 to 1.00 L/min at 20 kPa and from 90 to 60 K/kW: Anvilfield estimates of paired recovery. Itemize every changed hose, connector, plate and interface; simultaneous changes leave component cause unresolved.

Table 9. Anvilfield retest decision rules using the accepted envelope and NIST TN1297 uncertainty method.
Retest outcomeEvidence requiredDisposition and next action
Hydraulics and thermal performance recoveredAccepted curve; matched workload/inlet; expected throughput; supported thermal indicators; leak/alarm checks passRelease the tested assembly within the accepted envelope; schedule follow-up
Flow recovered but GPU-to-inlet rise remains highRepeated thermal comparison at the same flow, power and inletHold thermal acceptance; inspect mount/TIM, retained deposits, internal distribution and mapping
GPU cools but flow remains deficientLow load or power cap identified, or curve still outside accepted envelopeHold full-load release; restore flow and repeat the required workload
Hydraulic and thermal readings recovered after several parts changedQD, hoses, plate and/or mounting changes itemizedRecord restored assembly performance; keep component cause unresolved until isolated evidence exists
Repeat curve difference lies within uncertaintyRepeatability, instrument uncertainties and comparison tolerance retainedReport no resolved hydraulic shift; improve measurement or use another diagnostic test
Restriction returns after replacementTrend worsens at a comparable load and fluid conditionReopen shared coolant, filtration and material-source investigation; retain new sample evidence

Before testing, enter the model-specific minimum flow, pressure range, inlet-temperature range, device thermal limits and baseline comparison tolerance, each with source/revision. Compare corrected readings with the accepted supplier curve or clean baseline using the uncertainty and decision-rule method.

Anvilfield selects a conservative guard-band rule: measured flow minus expanded uncertainty must meet the specified minimum flow; measured pressure drop plus expanded uncertainty must stay at or below the specified maximum drop. A result overlapping the limit is held for better measurement or corrective work. For a selected minimum of 0.90 L/min and measured 0.94 L/min with expanded uncertainty 0.06 L/min, Anvilfield estimates a lower bound of 0.88 L/min: hold release. NIST TN1297 supplies uncertainty methods, not this acceptance rule.

Release requires expected power and throughput, no new thermal slowdown during the matched workload, stable temperature, acceptable flow, no leak and correct protective alarm response. A cooler idle GPU leaves the delivered-load requirement unresolved.

How often should you look again?

Anvilfield selects post-repair reviews at the stabilized retest, 24 hours, 7 days, 30 days and first comparable high-load event. For each checkpoint retain UTC window, component IDs, fluid condition, inlet/flow/pressure/GPU/power readings, apparent resistance, event increment/reset flag, throughput, criterion/revision, pass/hold and raw-file link. Repeat invasive curve sweeps when the approved program or changed trend calls for them.

OCP's PG guideline Rev 2.0/Version 1.0.0, section 11.2, recommends at least annual qualified-laboratory analysis generally. Its low-risk schedule is commissioning baseline then annual; medium risk uses baseline then six-monthly laboratory testing for 18 months, reducing to annual only if stable; high risk uses baseline then quarterly for 18 months, reducing to six-monthly only if stable. Medium risk separately includes six-monthly on-site checks.

Those scenarios retain their assumptions: low risk includes inline pH/refractive monitoring, acceptable materials and a familiar user; medium lacks inline monitoring and has an unfamiliar user; high additionally describes materials as “mostly acceptable.” That sampling description does not approve an incompatible material.

For loops below 100 gallons, section 11.2 separately recommends startup pH and glycol-concentration/refractive-index verification at every rack, then qualified-lab analysis of a statistically significant rotating subset at least every six months where regular every-rack testing is impractical. Similar racks and wetted materials are prerequisites. Document population, selection and coverage; no universal sample count is supplied. Take incident samples promptly, and reopen shared-fluid/filtration/material investigations if restriction recurs.

What belongs in the service scope and cost estimate?

Separate workload coordination, instrument setup, curve testing, sample handling/analysis, OEM service, consumables, leak/de-air checks, witnessed replacement retesting and follow-up reviews. Keep plate cost, laboratory quote, lead time and downtime value separate. Use the commissioning subcontract and retest guide to define attendance and repeat visits.

A public cooling scope should separate branch diagnosis, coolant analysis and witnessed replacement retests; PorchRocket's Bid Control finds public HVAC and refrigeration bids and early capital-plan signals where contractors price that work.

Anvilfield estimates eight technician-hours for a selected two-person, four-hour diagnosis/retest visit, plus four technician-hours for a separate two-hour repeat visit. Method: multiply crew size by elapsed time. Add actual stabilization, service, laboratory turnaround, delivery and outage allowances to the work order; instrument access and workload coordination control the schedule.

Who decides whether the branch is ready for service?

The server/plate supplier governs assembly limits, the coolant supplier governs its fluid's treatment constraints, and the owner accepts the restoration evidence against approved project criteria. Name who supplies workload, isolates cooling, witnesses results, retains the failed part and funds repeat tests. Record “repair scope changed” separately from “same plate retested.”

Field checklist and closeout record

Package raw trends, curves, uncertainty, samples, photographs, part changes, limits, exceptions and signed retest results together. Enter results and disposition beside each item; assign unresolved work.

  1. Identify GPU UUID, plate, branch, loop and part revisions; correct unmapped telemetry. Result: ______ Disposition: ______
  2. Retrieve clean hydraulic/thermal curves and operating limits; resolve missing release criteria. Result: ______ Disposition: ______
  3. Draw pressure boundaries, including hoses, valves and connected QDs between taps. Result: ______ Disposition: ______
  4. Confirm zeros, sensing-line fill/elevation, meter range, mapping and calibration; reject invalid readings. Result: ______ Disposition: ______
  5. Record fluid product/batch/concentration/temperature; match baseline conditions. Result: ______ Disposition: ______
  6. Capture header pressure, filter loss and neighbor behavior; investigate shared faults first. Result: ______ Disposition: ______
  7. Synchronize supported temperatures, power, limits, clocks, utilization, throughput and event reasons. Result: ______ Disposition: ______
  8. Stabilize supported load; retain analysis window and protective stop conditions. Result: ______ Disposition: ______
  9. Compare loss at matched flow or flow at matched pressure; identify controlled condition. Result: ______ Disposition: ______
  10. Inspect routing, valves and QD seating/identity; record changed parts. Result: ______ Disposition: ______
  11. De-air by approved procedure; repeat unstable measurements before diagnosing solid blockage. Result: ______ Disposition: ______
  12. Localize plate loss with characterized bench/bypass; protect IT from dirty test equipment. Result: ______ Disposition: ______
  13. Retain fluid, debris and removed part with lab-agreed handling; distinguish unconfirmed identities. Result: ______ Disposition: ______
  14. Use approved cleaning/replacement/mounting; record assembly and interface material. Result: ______ Disposition: ______
  15. Retest matched conditions, expected workload, protection behavior and leak/alarm results. Result: ______ Disposition: ______
  16. Sign restoration decision; assign mechanism follow-up, operational reviews and risk-based fluid analysis. Result: ______ Disposition: ______

Close restoration and mechanism findings separately. The replacement can pass its service test while deposit identity remains pending; retain the removed part and assign that analysis explicitly. Link the closeout to the branch curves, fault matrix, contamination register and replacement decision.

Sources checked and reviewed by Anvilfield: 2026-11-05. Update log: 2026-11-05: reviewed source editions and calculations; distinguished new-fluid and in-service pH, clarified thermal events and service controls, and added a flow-acceptance example.

The primary-source register below identifies editions and application boundaries. The OCP Cold Plate project index is the discovery index; use the linked document edition for technical claims. Retain queried device, driver and collector versions with each service record. Cite the specific table fragment when reusing a calculation or decision register.

How to cite this page: Anvilfield, Is a cold plate blocked? Compare pressure drop with GPU temperature, 2026, https://anvilfield.com/field-guides/datacenter/cold-plate-blockage-pressure-drop-diagnosis/

Related tools

Next step: Find public cooling bids

FAQ

How do cold plate blockage pressure drop and GPU temperature relate?

At matched flow a restriction raises pressure drop, while at matched header pressure it reduces flow; rising GPU-to-inlet temperature at matched power supplies the thermal evidence.

What is cold plate thermal resistance?

OCP's qualification white paper defines it as component case temperature minus plate inlet temperature, divided by applied power at a stated stabilized flow.

Can normal branch pressure coexist with GPU throttling?

Yes; a constant-pressure controller can hold header differential pressure while a restricted branch loses flow and the GPU reaches its thermal limit.

How do you retest a replacement cold plate?

Repeat the accepted flow/pressure curve and matched inlet-temperature/power test, then retain workload, thermal-event and leak-check results.

Does a hot GPU prove the cold plate is blocked?

No; warmer inlet fluid, higher power, poor contact, deposits and a supply problem can produce the same temperature symptom.

Can a quick disconnect cause the same symptoms as a blocked plate?

Yes; localize the added pressure loss before assigning it to the plate.

Can you use GPU temperature and power to calculate plate-only resistance?

Use them for an apparent GPU-to-inlet trend; OCP's case-to-inlet method uses the specified mounted assembly, including its TIM2 interface, rather than isolating bare-plate resistance.

Is 50-micron filtration correct for every GPU loop?

No; filter location, efficiency, narrowest passage, approved component limits and coolant program determine the required rating.

Should every fouled plate be chemically flushed?

Use the named assembly and fluid suppliers' approved cleaning procedure, or replace the non-serviceable assembly and correct its contamination source.

How often should coolant be sampled after a blockage?

Take incident samples promptly; follow the approved fluid program, with OCP PG Rev 2.0 §11.2's risk-based laboratory schedule and separate small-loop sampling provision where applicable.

Can you diagnose blockage without a branch flowmeter?

Header pressure and GPU temperature can flag a problem; local flow measurement or a characterized component test is needed to establish changed hydraulic resistance.

What if flow returns to normal but the GPU stays hot after replacement?

Repeat at matched flow, inlet and power, then investigate mounting/contact, deposits, internal flow distribution and sensor mapping.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.