BIL

BIL means basic impulse insulation level: Siemens assigns its 15 kV SIEBREAK gear 95 kV peak lightning-impulse withstand and 36 kV power-frequency withstand. The surge figure describes a brief specified waveform; it does not set continuous operating voltage or a field hipot voltage. Keep rated operating voltage, BIL and the manufacturer's field-test voltage in separate schedule columns when ordering insulation components or reviewing commissioning results.

Basic impulse insulation level, the impulse voltage withstand of the insulation in kV

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

What does the 1.2/50 impulse designation mean?

Maschinenfabrik Reinhausen's VI 6E 004e dielectric test report identifies the full lightning impulse as a nominal 1.2 microsecond front and a nominal 50 microsecond time to half-value on the falling tail. Its test tables record peak amplitude, front time and tail time separately. The designation does not mean a flat voltage held for 50 microseconds.

ABB's November 2025 Elastimold IEC connector catalog rates its 12 kV-class, 250 A separable connector at 95 kV BIL on a 1.2/50 microsecond wave. Its stated phase-to-phase operating voltage is 11 kV, and its five-minute AC withstand is 28.5 kV. None of those three voltages substitutes for another when selecting or testing the connector.

BIL and operating voltage are not interchangeable

Siemens's SPEEDFAX switchgear catalog, SIEBREAK specifications, assigns 60 kV BIL to the 5 kV version and 95 kV BIL to the 15 kV version. A component labeled 95 kV BIL therefore still needs its operating-voltage class identified. ABB's 12 kV-class connector and Siemens's 15 kV switchgear demonstrate why matching BIL alone does not establish interchangeability.

A switchgear receiving record with separate entries for 15 kV equipment class, 95 kV peak BIL and 36 kV power-frequency withstand preserves information that a single column headed 'voltage' loses. Keep the component's catalog designation beside those entries so an estimator can distinguish a 12 kV-class connector from 15 kV switchgear even when both advertise 95 kV BIL.

Reading a 15 kV dielectric test packet

Siemens's 2023 GM-SG instruction manual, page 94, recommends a dielectric test of the high-voltage circuit where feasible and lists 27 kV rms AC for one minute at the 15 kV equipment rating. The separate power-frequency withstand column is 36 kV rms. These are GM-SG field-test values; the SIEBREAK catalog is not the test procedure for GM-SG or the reverse.

The GM-SG manual requires voltage transformers, control power transformers, surge arresters and surge capacitors disconnected during that test. Page 105 also requires installed surge limiters disconnected for high-potential testing. Its DC reference column does not authorize substituting a DC test for AC withstand testing. Those restrictions belong with the voltage and duration in the test plan.

A 27 kV rms AC field-test result and a 95 kV peak BIL rating describe different stresses, so subtracting them produces no useful acceptance criterion. An insulation-resistance reading in megohms supplies another kind of evidence; it cannot be converted into a BIL rating.

Which test standard belongs on the report?

IEC 60060-1:2025, edition 4, covers high-voltage dielectric test terminology and requirements for AC, DC, impulse and combined voltages. Cite the equipment's specified test basis and manufacturer document alongside it. A test-method standard describes how the voltage is applied and measured; the product rating identifies the withstand level assigned to that equipment.

Distinctions

kAIC
kAIC describes interrupting current capability. Increasing an impulse-voltage rating does not increase the current a breaker can interrupt.
Surge-arrester protective level
The arrester's voltage during surge discharge and the protected equipment's BIL are separate inputs to insulation coordination. An arrester does not change the equipment's assigned BIL.

Frequently asked questions

Is BIL an rms voltage?

BIL is stated in peak or crest kilovolts. Power-frequency withstand values are normally stated in rms kilovolts. Preserve those qualifiers when transferring ratings into a schedule.

Does a higher BIL mean higher transformer capacity?

A padmount transformer order needs both capacity and insulation ratings: kVA or MVA sizes the apparent-power duty, while BIL identifies impulse withstand. Ordering a higher BIL alone adds no kVA to the specified transformer.