Field glossary · measurement
kVA / MVA
kVA (kilovolt-amperes) and MVA (megavolt-amperes) express the same apparent-power quantity at different scales: divide kVA by 1,000 to obtain MVA. Retain a transformer's rating with its cooling stage, voltage, and temperature-rise basis. Changing 2,500 kVA to 2.5 MVA is only a unit conversion; changing a self-cooled rating to a fan-cooled rating changes the operating capacity being claimed.
Apparent power rating, in thousands or millions of volt-amps; the transformer's size
Normalize transformer units before comparing submittals
NIST assigns kilo the multiplier 10 to the third power and mega 10 to the sixth power, so 1 MVA equals 1,000 kVA. Thus 750 kVA is 0.750 MVA, and 2.5 MVA is 2,500 kVA. Keep the decimal point visible when entering a transformer rating into software that requests MVA.
A 2.5 entry in a field expecting kVA is a thousandfold input error. Put the original nameplate value and the normalized value in separate columns rather than changing the source record. Use the same unit basis for all units in a transformer receiving packet.
Fan-on capacity is a different rating basis
Eaton's PS202009EN specification provides a 25 percent forced-air capacity increase for the listed 2,500 to 10,000 kVA HDC substation-transformer designs. At a 2,500 kVA base rating, that gives 3,125 kVA, or 3.125 MVA, with the specified fan-cooled equipment and operating basis. The additional 625 kVA is a cooling-stage rating, not a benefit of writing the nameplate in MVA.
Eaton assigns the 15 percent increase specifically to its 750 to 2,000 kVA designs, not to every transformer below 2,500 kVA. The specification also distinguishes installed KNAN/KNAF cooling from KNAN with provision for future KNAF operation. Translate those codes in the schedule as natural-air cooling versus the additional forced-air stage, and retain the actual temperature-rise rating with each capacity.
Convert the rating to current on each winding
Schneider Electric's three-phase transformer formula gives rated line current as kVA x 1,000 / (1.732 x line-to-line V). For a 2.5 MVA transformer, that produces approximately 104.6 A at 13.8 kV and 3,007 A at 480 V. The apparent-power rating transfers between windings while the current changes with voltage.
These are total three-phase rating calculations. Do not multiply the transformer nameplate by three again. On a one-line review, retain the transformer rating and each winding voltage together so a primary current is not copied into the secondary feeder schedule. The one-line reading guide shows where those annotations belong.
Distinctions
- MW
- MW measures real power. Converting MVA to MW requires the load power factor; changing metric prefixes alone does not perform that conversion.
Frequently asked questions
Does an MVA label mean it is a power transformer rather than a distribution transformer?
The prefix only scales the apparent-power number. Construction, voltage class, cooling, application, and the specified equipment standard describe the transformer type; 2.5 MVA and 2,500 kVA identify equal capacity on the same rating basis.
Sources checked
Also defined as
- Datacenter: Apparent-power rating of the transformer; 1 MVA equals 1000 kVA
- Apparent power rating of transformers and gear, thousands or millions of volt-amps